Residential building permit in Bonney Lake, Washington
Permit to build, alter or add to a house in Bonney Lake, under the International Residential Code adopted at BLMC 15.04.020(B).
Verified 2026-09-16 · Source
When you need this permit
- BLMC 15.04.020(B) adopts the International Residential Code by reference with the Chapter 51-51 WAC exceptions AND NAMES NO EDITION YEAR.
- “Chapters 11 and 25 through 43 of this code are not adopted” — the IRC's energy chapter and its plumbing, mechanical and electrical chapters are excluded, so those subjects follow the IECC, UPC and IMC instead.
- Appendix F (Radon Control Methods), Appendix G (Swimming Pools, Spas and Hot Tubs), Appendix R (Dwelling Unit Fire Sprinkler Systems) and Appendix S (Fire Sprinklers) are expressly included.
- Design criteria are fixed by the table at BLMC 15.04.020(J), adopted “pursuant to Section R301.2 of the International Residential Code and ASCE 7-16”: 20 psf ground snow load, 85 mph wind speed with topographic effects, seismic design category D1, 12-inch frost line depth, winter design temperature 27, air freeze index 160.
- PERMIT EXPIRY IS NOT IN THE BUILDING CHAPTER. BLMC 15.04.081 is repealed; BLMC 14.10.100 applies, and a permit expires two years after issuance if the use is not commenced or the construction permits are not issued.
- Adding dwelling units to a building that has held a certificate of occupancy for at least three years may avoid current energy code on unchanged residential or conditioned portions, under BLMC 15.04.098(A)(1).
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No dollar figure is published in the code, AND THE FEE SECTIONS IN THE BUILDING CHAPTER NO LONGER EXIST. Show full citationHide
No dollar figure is published in the code, AND THE FEE SECTIONS IN THE BUILDING CHAPTER NO LONGER EXIST. BLMC 15.04.072 “Building permit – Fees” and 15.04.080 “Building plan review – Fees” both read “Repealed by Ord. 1598.” Fees moved to BLMC Chapter 3.68 in the revenue title, where 3.68.030 provides that fees “shall be set by resolution of the city council”. REFUNDS ARE DISCRETIONARY AND EFFORT-BASED: BLMC 3.68.020 lets the director refund “not more than 80 percent of the building permit fee paid when no work has been done”, and not more than 80 percent where an application is withdrawn before approval, with “the amount of the refund … based on the amount of effort expended by the city”. Ask the city for the current resolution.Review timeline
Inspection process
Tips
- The IRC's own plumbing, mechanical and electrical chapters are not adopted here, so do not design residential systems from the IRC alone — the standalone UPC and IMC govern.
- Because no edition year is named anywhere, two projects a year apart can be reviewed against different editions without any ordinance changing. Get the operative edition in writing.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bonney Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bonney Lake's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Bonney Lake yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Bonney Lake lands. Privacy.
Other permits in Bonney Lake
Residential building permit in other cities
Compare residential building permit fees across Washington →
Look up this fee in a different city →
Related guides
Now live
Build your Bonney Lake project checklist
Describe your project once and get every permit, document, and fee it triggers in Bonney Lake — in one checklist. Free, for any city and any number of projects.
Get started →