Residential building permit in Kenmore, Washington
Permit to build, alter or add to a house in Kenmore, under the International Residential Code adopted at KMC 15.20.120.
Verified 2026-09-16 · Source
When you need this permit
- KMC 15.20.120 adopts “The 2021 Edition of the International Residential Code”, expressly including Appendix AT “Solar Ready Provisions”, Appendix AWU “Dwelling Unit Fire Sprinkler Systems”, Appendix AWV “Fire Sprinklers”, Appendix AWY “Construction and Demolition Material Management” and Appendix AWZ “Building Deconstruction”.
- The IRC's own Chapter 1 is excluded; KMC Chapter 15.30, the Construction Administrative Code, is used in its place.
- PERMIT LIFE IS TWO YEARS for an IRC-permitted structure or a tenant space in an existing building (KMC 15.30.245(A)).
- WITHIN THOSE TWO YEARS the exterior must be complete — “roofing, siding, windows, exterior doors and applicable site and right-of-way improvements” — and that deadline “may not be extended” unless the building official approves otherwise.
- A detached accessory structure is exempt only up to 200 square feet, and only where it is not within a critical area, shoreline, associated buffer or native growth protection area (KMC 15.30.205).
- Appendix AWZ on building deconstruction and Appendix AWY on construction and demolition material management are adopted, so demolition and material handling carry code requirements many Washington cities do not adopt.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No dollar figure is published in the code. Show full citationHide
No dollar figure is published in the code. KMC 15.30.350 says a fee shall be paid “in accordance with the schedule as established by the applicable governing authority” — IT DOES NOT NAME THE BODY — and adds that “the building official is authorized to establish fees for any permit activity not specifically set forth herein”. A plan review fee is due at submittal under KMC 15.30.355. THE VALUATION THE FEE IS COMPUTED FROM IS NOT THE APPLICANT'S NUMBER BY DEFAULT: KMC 15.30.365 requires the applicant to give an estimated value, then provides that valuation “shall be made by the applicant or building official, whichever is higher”, with the official using “the latest edition of the ICC ‘Building Safety Journal’ publication”. Ask the city for the current schedule; it cannot be derived from the code.Review timeline
Inspection process
Tips
- The exterior-completion deadline is separate from the permit's expiry and is the one the code singles out as non-extendable. Sequence the envelope early rather than leaving siding and windows to the end of year two.
- Getting the framing inspection approved is what protects your code vesting if the job later has to be re-permitted.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kenmore building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Kenmore's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Kenmore yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Kenmore lands. Privacy.
Other permits in Kenmore
Residential building permit in other cities
Compare residential building permit fees across Washington →
Look up this fee in a different city →
Related guides
Now live
Build your Kenmore project checklist
Describe your project once and get every permit, document, and fee it triggers in Kenmore — in one checklist. Free, for any city and any number of projects.
Get started →