Mechanical permit in Kenmore, Washington
Permit for mechanical work in Kenmore, under the International Mechanical Code adopted at KMC 15.20.140.
Verified 2026-09-16 · Source
When you need this permit
- KMC 15.20.140 adopts “The 2021 Edition of the International Mechanical Code, excluding Chapter 1, ‘Scope and Administration’”, with the amendments in Chapter 51-52 WAC, and substitutes KMC Chapter 15.30 for the code's own Chapter 1.
- A MECHANICAL PERMIT NOT ASSOCIATED WITH A BUILDING PERMIT EXPIRES IN ONE YEAR (KMC 15.30.245(C)) — the shortest of Kenmore's three permit lives.
- Where mechanical work is part of a building permit it takes that permit's life instead, two years for an IRC structure and three for a commercial one, as an “associated ancillary permit” under KMC 15.30.245(A) and (B).
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No dollar figure is published in the code. Show full citationHide
No dollar figure is published in the code. KMC 15.30.350 says a fee shall be paid “in accordance with the schedule as established by the applicable governing authority” — IT DOES NOT NAME THE BODY — and adds that “the building official is authorized to establish fees for any permit activity not specifically set forth herein”. A plan review fee is due at submittal under KMC 15.30.355. THE VALUATION THE FEE IS COMPUTED FROM IS NOT THE APPLICANT'S NUMBER BY DEFAULT: KMC 15.30.365 requires the applicant to give an estimated value, then provides that valuation “shall be made by the applicant or building official, whichever is higher”, with the official using “the latest edition of the ICC ‘Building Safety Journal’ publication”. Ask the city for the current schedule; it cannot be derived from the code.Review timeline
Inspection process
Tips
- Whether your mechanical permit runs one year or rides on a two or three year building permit depends on whether it is associated with one. A standalone equipment replacement gets the short clock.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kenmore building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Kenmore's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Kenmore yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Kenmore lands. Privacy.
Other permits in Kenmore
Mechanical permit in other cities
Compare mechanical permit fees across Washington →
Look up this fee in a different city →
Now live
Build your Kenmore project checklist
Describe your project once and get every permit, document, and fee it triggers in Kenmore — in one checklist. Free, for any city and any number of projects.
Get started →