Commercial building permit in Kenmore, Washington

Permit for commercial, multifamily, institutional and industrial construction in Kenmore, under the International Building Code adopted at KMC 15.20.010.

Verified 2026-09-16 · Source

When you need this permit

  • KMC 15.20.010 adopts “The 2021 Edition of the International Building Code, excluding Chapter 1, ‘Scope and Administration,’ as published by the International Code Council… together with the amendments set forth in Chapter 51-50 WAC.”
  • PERMIT LIFE IS THREE YEARS for a “commercial, educational, institutional, multifamily, public, industrial or similar structure” (KMC 15.30.245(B)).
  • The building official may grant only “a 30-day extension of time for permits when only the final inspection is remaining and all other work has been approved” (KMC 15.30.245(D)).
  • Kenmore writes its own administrative chapter and amends the IBC section by section: KMC 15.20.015 through 15.20.115 each amend a single IBC section, including Section 3117 “Waterfront Structures”, which KMC 15.20.110 ADDS to the code.
  • The 2021 International Existing Building Code is adopted at KMC 15.20.170 for work in existing buildings, again excluding its Chapter 1.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Permit fee
No dollar figure is published in the code. Show full citationNo dollar figure is published in the code. KMC 15.30.350 says a fee shall be paid “in accordance with the schedule as established by the applicable governing authority” — IT DOES NOT NAME THE BODY — and adds that “the building official is authorized to establish fees for any permit activity not specifically set forth herein”. A plan review fee is due at submittal under KMC 15.30.355. THE VALUATION THE FEE IS COMPUTED FROM IS NOT THE APPLICANT'S NUMBER BY DEFAULT: KMC 15.30.365 requires the applicant to give an estimated value, then provides that valuation “shall be made by the applicant or building official, whichever is higher”, with the official using “the latest edition of the ICC ‘Building Safety Journal’ publication”. Ask the city for the current schedule; it cannot be derived from the code.
Set by adopted fee schedule

Review timeline

Plan review
Not published — contact the department

How long did your Commercial building permit permit actually take in Kenmore?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • A waterfront structures section was added to the IBC as Section 3117 by KMC 15.20.110 — Kenmore sits on Lake Washington, and that section has no counterpart in the model code.
    • The only extension the code offers is 30 days, and only when the final inspection is the sole outstanding item. Plan the three years as the real budget.

    Frequently asked questions

    Kenmore requires a commercial building permit for: KMC 15.20.010 adopts “The 2021 Edition of the International Building Code, excluding Chapter 1, ‘Scope and Administration,’ as published by the International Code Council… together with the amendments set forth in Chapter 51-50 WAC.”; PERMIT LIFE IS THREE YEARS for a “commercial, educational, institutional, multifamily, public, industrial or similar structure” (KMC 15.30.245(B)).; The building official may grant only “a 30-day extension of time for permits when only the final inspection is remaining and all other work has been approved” (KMC 15.30.245(D)).; Kenmore writes its own administrative chapter and amends the IBC section by section: KMC 15.20.015 through 15.20.115 each amend a single IBC section, including Section 3117 “Waterfront Structures”, which KMC 15.20.110 ADDS to the code.; The 2021 International Existing Building Code is adopted at KMC 15.20.170 for work in existing buildings, again excluding its Chapter 1.. If your project isn't listed, confirm with City of Kenmore at (425) 398-8900 before starting work.

    In Kenmore, the published Permit fee is: Set by adopted fee schedule. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Kenmore does not publish a plan-review timeline for this permit. Contact City of Kenmore at (425) 398-8900 for current turnaround.

    You'll need: Permit application; Estimated permit value. Depending on your project, Kenmore may also ask for: Submittal documents for plan review; Critical-area confirmation where an exemption is relied on. See the required-documents checklist on this page for details on each.

    Apply through City of Kenmore at 18120 68th Ave NE, Kenmore, WA 98028. Phone: (425) 398-8900. Official information: https://www.kenmorewa.gov/.

    Kenmore, Washington has adopted: IBC — KMC 15.20.010: “The 2021 Edition of the International Building Code, excluding Chapter 1, ‘Scope and Administration,’ as published by the International Code Council, is adopted, together with the amendments set forth in Chapter 51-50 WAC.”; IRC — KMC 15.20.120: “The 2021 Edition of the International Residential Code”, expressly including Appendix AT “Solar Ready Provisions”, Appendix AWU “Dwelling Unit Fire Sprinkler Systems”, Appendix AWV “Fire Sprinklers”, Appendix AWY “Construction and Demolition Material Management” and Appendix AWZ “Building Deconstruction”.; IMC — KMC 15.20.140: “The 2021 Edition of the International Mechanical Code, excluding Chapter 1”, with the amendments in Chapter 51-52 WAC.; UPC — KMC 15.20.145: “The 2021 Edition of the Uniform Plumbing Code, excluding Chapter 1, ‘Administration,’ as published by the International Association of Plumbing and Mechanical Officials”, together with Appendix A on sizing the water supply system.; NFPA 54 — KMC 15.20.150: “The 2021 National Fuel Gas Code, excluding Chapter 1, ‘Administration,’ as published by NFPA, is adopted together with the amendments set forth in Chapter 51-52 WAC.”; NFPA 58 — KMC 15.20.155: “The 2020 Liquefied Petroleum Gas Code, excluding Chapter 1, ‘Administration,’ as published by NFPA, is adopted, together with the amendments set forth in Chapter 51-52 WAC.”; IFGC — KMC 15.20.160: “The 2021 Edition of the International Fuel Gas Code, excluding Chapter 1, ‘Administration’”, with the amendments in Chapter 51-52 WAC.; WSEC — KMC 15.20.165: “The 2021 Washington State Energy Code, excluding Chapter 1, as adopted by the State Building Code Council in Chapters 51-11C and 51-11R WAC”.; IEBC — KMC 15.20.170: “The 2021 Edition of the International Existing Building Code, excluding Chapter 1, ‘Scope and Administration’”.; International Swimming Pool and Spa Code — KMC 15.20.175: “The 2021 Edition of the International Swimming Pool and Spa Code, excluding Chapter 1”. The first city in this Washington series to adopt it by name.; International Wildland-Urban Interface Code — KMC 15.20.180 IS HEADED “International Wildland-Urban Interface Code adopted” AND ITS BODY READS, IN FULL, “Repealed by Ord. 24-0610.” KENMORE DOES NOT ADOPT IT. The heading is the only thing that says otherwise.; NO ELECTRICAL CODE IS ADOPTED IN TITLE 15. Chapter 15.20's sections were enumerated end to end and none adopts the NEC or the Washington Cities Electrical Code, unlike Mountlake Terrace, Mercer Island, SeaTac and Des Moines. KMC 15.30.245(C) nonetheless sets a one-year life for “electrical, mechanical, and plumbing permits not associated with a building permit”. The usual Washington route is inspection by Labor and Industries under Chapter 19.28 RCW, BUT NO SUCH PROVISION WAS FOUND IN THIS TITLE and none is asserted here.. Local amendments apply — see the Kenmore overview page for the full list.

    Only narrowly. KMC 15.30.245(D) lets the building official grant a 30-day extension when the final inspection is all that remains and every other item has been approved. There is no general extension provision.

    Sources & verification

    Verified against official sources. Last reviewed 2026-09-16.

    Department & other records

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kenmore building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    This one’s complicated · Get an expediter

    Tell us about your project and we’ll connect you with a permit expediter who works in Kenmore.

    PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

    Kenmore's permit history isn't searchable here yet

    This page covers what the permit requires. What we don't have for Kenmore yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

    Your email, and the place — never an address. We only use it to tell you when Kenmore lands. Privacy.