Commercial Building Permit in Longview, Washington
Required for commercial construction, alteration and occupancy in Longview, under the 2021 International Building Code adopted through Chapter 51-50 WAC.
Verified 2026-09-16 · Source
When you need this permit
- “Chapter 51-50 WAC (2021 International Building Code), including the Appendix Chapters E, as further amended by Chapter 51-50 WAC, I and J” (LMC 16.02.010)
- The code is locally retitled “the Building Code of the City of Longview, Washington”
- PLAN REVIEW IS AN EXTRA 70 PERCENT of the building permit fee for all non-IRC reviews
- The building official also enforces land use approval conditions as they relate to permit issuance and certificates of occupancy (Section 104.1 as amended)
- Violations are a MISDEMEANOR under Section 114.1 as amended
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
LMC 16.02.020 replaces IBC Section 109.2 and adds 109.2.1: “The fee for each building permit shall be as established in the community and economic development department master fee schedule.” The… Show full citationHide
LMC 16.02.020 replaces IBC Section 109.2 and adds 109.2.1: “The fee for each building permit shall be as established in the community and economic development department master fee schedule.” The same wording covers mechanical (109.2.2) and plumbing (109.2.3) permits. NO DOLLAR AMOUNT APPEARS IN THE CODE and none is asserted here — but unlike most of this Washington set, the PERCENTAGES that sit on top of that schedule ARE published, and they are recorded separately below.LMC 16.02.020 Section 109.6: “Not more than 80 percent of the permit fee paid when no work has been done”, and the same cap on plan review fees where an application is withdrawn or cancelled “before… Show full citationHide
LMC 16.02.020 Section 109.6: “Not more than 80 percent of the permit fee paid when no work has been done”, and the same cap on plan review fees where an application is withdrawn or cancelled “before any plan review effort has been expended.” Written application required “not later than 180 days after the date of fee payment.”Review timeline
Inspection process
Tips
- Seventy percent on top is the number to plan around: for anything that is not a one- or two-family IRC review, plan review is 70 percent of the building permit fee and the code states it is additional rather than inclusive.
- Incomplete or changed submittals cost more, and so do deferred submittals. Section 109.2.1.3 charges an additional plan review fee at the Table 1-A rate where documents are incomplete or altered so as to require further review, or where the project uses deferred submittal items under Section 107.3.4.2.
- Note who enforces what: Section 104.1 as amended makes the building official responsible for enforcing land use approval conditions as they bear on permit issuance and the certificate of occupancy — so a planning condition can hold up a building sign-off.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Longview building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Longview.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Longview's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Longview yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Longview lands. Privacy.
Other permits in Longview
Commercial Building Permit in other cities
Compare commercial building permit fees across Washington →
Look up this fee in a different city →
Now live
Build your Longview project checklist
Describe your project once and get every permit, document, and fee it triggers in Longview — in one checklist. Free, for any city and any number of projects.
Get started →