Building Permit — Tukwila, Washington · Requirements sheet
Reviewed 2026-09-16 · Source: https://www.tukwilawa.gov/departments/permit-center/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit in Tukwila, Washington
Required for construction in Tukwila under the 2021 IBC and 2021 IRC as adopted at TMC 16.04.020, with locally adopted exemptions for small sheds and low fences.
Reviewed 2026-09-16 · Source
When you need this permit
- Built to the 2021 International Building Code or 2021 International Residential Code, each with Washington statewide amendments
- Electrical work is to the 2023 National Electrical Code, a newer edition than the rest
- Applications are processed as Type 1 decisions under TMC Chapter 18.104
- A pre-application meeting is required for some permit types
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
TUKWILA'S PERMIT FEE AMOUNTS ARE NOT IN ITS MUNICIPAL CODE, AND THE CODE SAYS SO. Show full citationHide
TUKWILA'S PERMIT FEE AMOUNTS ARE NOT IN ITS MUNICIPAL CODE, AND THE CODE SAYS SO. TMC 16.04.250(A) provides that "Permit and plan review fees applicable to all development permits shall be in accordance with the permit fee schedule adopted by resolution of the City Council." So no amount is printed here - the schedule is a Council resolution, published separately and changed separately. Ask the Permit Center for the current schedule. THREE FEE RULES ARE IN THE CODE AND DO APPLY: work begun before the necessary permits are obtained is "charged double the fee established in accordance with the permit fee schedule adopted by resolution of the City Council"; the Building Official may refund "not more than 80% of the permit fee when no work has been done under a permit"; and a re-inspection fee may be charged at an hourly rate where work was covered without inspection or was not ready.Review timeline
Inspection process
Tips
- Do not start work before the permit issues - TMC 16.04.250(D) charges double the fee
- The Permit Center is closed Fridays
- Pre-application meetings are held Tuesdays at 1:30 and 2:30 PM
- Schedule inspections online by 5 PM for next-day service
- Inspections scheduled online; the Permit Center states that requests made by 5 PM are scheduled for the next day
- Work covered without inspection, or not ready at the time of inspection, may be charged a re-inspection fee at an hourly rate
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tukwila building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Tukwila's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Tukwila yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Tukwila lands. Privacy.
Other permits in Tukwila
Building Permit in other cities
Compare building permit fees across Washington →
Look up this fee in a different city →
Now live
Build your Tukwila project checklist
Describe your project once and get every permit, document, and fee it triggers in Tukwila — in one checklist. Free, for any city and any number of projects.
Get started →