Building Permit in Lakewood, Washington
Required for construction in Lakewood. The city adopts the 2021 IBC and IRC under RCW 19.27.031 as the Lakewood Building Code, strips the IRC's administrative sections, and runs everything through IBC Chapter 1.
Reviewed 2026-09-16 · Source
When you need this permit
- Built to the 2021 IBC (with Appendix Chapters E, G and J) and the 2021 IRC
- IRC Sections R103 through R114 and Chapters 11 and 25 through 43 are NOT adopted
- IRC Appendices F, Q and U ARE adopted
- Administration for all work comes from IBC Chapter 1 (LMC 15.05.040)
- Accessibility is adopted under both RCW 19.27 and RCW 70.92, including ICC A117.1-2017
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
LAKEWOOD DOES NOT PRINT ITS PERMIT FEE AMOUNTS IN THIS CHAPTER AND THIS ENTRY DECLINES TO STATE ONE. Show full citationHide
LAKEWOOD DOES NOT PRINT ITS PERMIT FEE AMOUNTS IN THIS CHAPTER AND THIS ENTRY DECLINES TO STATE ONE. What the code DOES fix are three things you can act on. FIRST, STARTING WORK EARLY COSTS YOU THE PERMIT FEE TWICE: IBC Section 109.4 as amended provides that "Any person who commences work on a building, structure, gas, mechanical or plumbing system before obtaining the necessary permits shall be subject to a fee equal to the permit fee." - a charge equal to the permit, on top of the permit. SECOND, REFUNDS ARE PUBLISHED: Section 109.6 as amended allows "one hundred percent (100%) of any fee paid erroneously; up to eighty percent (80%) of the permit fee for a permit that is withdrawn, if no work has been done under the permit; and up to eighty percent (80%) of the plan review fee paid when an application is withdrawn prior to any plan review having been done." THIRD, THE REFUND CLOCK RUNS FROM PAYMENT AND IS EASY TO MISS: "No refund shall be authorized except on written application filed by the original applicant not later than one hundred eighty days after the date of the fee payment." Note that Shoreline publishes the same three-part refund rule with the same 180-day clock from payment and the same original-applicant restriction - two cities, one rule.Review timeline
Inspection process
Tips
- Do not start early - work begun before the permit draws a fee EQUAL to the permit fee
- The final inspection waits on SEPA, Hearings Examiner, Design Review, Development Engineering, Stormwater, the Tree Ordinance, West Pierce Fire and Rescue and outside agencies, plus finish grading
- If you withdraw, claim the refund within 180 days OF PAYMENT and it must be the original applicant who files
- Two extensions are free; further ones carry administrative fees and need written cause
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lakewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lakewood's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Lakewood yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Lakewood lands. Privacy.
Other permits in Lakewood
Building Permit in other cities
Compare building permit fees across Washington →
Look up this fee in a different city →
Now live
Build your Lakewood project checklist
Describe your project once and get every permit, document, and fee it triggers in Lakewood — in one checklist. Free, for any city and any number of projects.
Get started →