Demolition permit — Tumwater, Washington · Requirements sheet
Verified 2026-09-16 · Source: https://www.codepublishing.com/WA/Tumwater/#!/Tumwater15/Tumwater1550.html
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition permit in Tumwater, Washington
Permit to demolish, raze or remove a building or structure in Tumwater under TMC Chapter 15.50, which runs a separate regime with its own bond and completion deadline.
Verified 2026-09-16 · Source
When you need this permit
- TMC 15.50.010: the chapter “shall apply to all buildings and structures being demolished, razed or otherwise destroyed and removed from the property on which they are constructed, with the exception of those structures exempt from permits in the current edition of the building code adopted by the city of Tumwater.”
- A BOND IS DUE AT APPLICATION, NOT AT ISSUANCE, AND IT IS RETURNED IN FULL. TMC 15.50.040: “A bond shall be placed on deposit with the city at the time of permit application for the purpose of insuring completion of the demolition or, in the case of noncompletion, to insure that funds are available to pay for project completion by the city. Completion of a project by the applicant with final inspection approval by the community development department will cause said deposit to be returned to the applicant in its entirety.” THIS IS SECURITY, NOT A FEE, and the chapter publishes no amount in what was read.
- THIRTY DAYS TO FINISH, WHICH IS THE SHORTEST PERMIT DEADLINE IN THIS WASHINGTON SET. TMC 15.50.050: “All demolition work shall be completed within thirty days of permit issuance.” An extension must be requested in writing BEFORE the permit expires and must “indicate why additional time is necessary”, and is available only where circumstances beyond the permittee's control prevent completion.
- The chapter also carries 15.50.035 Application requirements, 15.50.045 Predemolition site inspection and public notice posting of property, 15.50.060 Final inspection by the city, 15.50.070 Failure to complete and 15.50.080 Order to complete. Those sections were read by title only and their contents are NOT asserted here.
- >>> TUMWATER HAS AFFIRMATIVELY OPTED OUT OF THE STATE'S PERMIT-PROCESSING CLOCKS, AND SAYS SO IN ONE SENTENCE. TMC 15.01.045, added by Ord. O2024-005 on 03/12/2024: “As authorized by RCW 36.70B.140, permits issued under this title are exempt from the timeline provisions of RCW 36.70B.060 through 36.70B.090 and 36.70B.110 through 36.70B.130.” THIS IS A PUBLISHED REASON RATHER THAN AN ABSENCE. Most cities in this Washington set simply do not state a review period, and the honest note is “not found where it would be expected”. Here the code tells you the statutory timelines have been disapplied. WHAT EXACTLY IS DISAPPLIED IS NOT ASSERTED — those RCW sections were NOT read for this entry — but the exemption itself is quoted from the code.
- TMC 15.01.100 is headed “Building code appeals – Hearing examiner”. This guide does not summarise it, so no deadline or procedure is stated here. Note that the model codes' own appeal sections — IBC 113 and IRC R112 — are expressly NOT adopted, so this section is the route.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
TMC 15.01.070: “All fees for permits or other approvals required in this title shall be as currently adopted or as may be amended from time to time by resolution of the Tumwater city council. Show full citationHide
TMC 15.01.070: “All fees for permits or other approvals required in this title shall be as currently adopted or as may be amended from time to time by resolution of the Tumwater city council. Copies of all fee schedules and any subsequent amendments thereto shall be maintained and available for public review at the office of the city clerk during regular business hours or on the city website”. NO DOLLAR AMOUNT APPEARS IN TITLE 15 and the resolution was not opened for this entry. NOTE THE STRUCTURAL REASON THE CODE HAS TO SAY THIS: Tumwater expressly DOES NOT ADOPT the model codes' own fee sections — IBC 109.2 and 109.6, IRC R108.2/.5/.6, IMC 109 and UPC 107.0 are all excluded — so the council resolution is not a supplement to the model schedules, it REPLACES them, and the model tables are not a fallback.TMC 15.01.080 publishes a refund rule, which is uncommon in this set: the building official may refund “One hundred percent of any fee erroneously paid or collected”, “Eighty percent of the permit… Show full citationHide
TMC 15.01.080 publishes a refund rule, which is uncommon in this set: the building official may refund “One hundred percent of any fee erroneously paid or collected”, “Eighty percent of the permit fee paid when no work has been done under a permit issued in accordance with this code; and further provided, that the permit has not expired”, and eighty percent of the plan review fee in the parallel case. THE EXPIRY PROVISO IS THE TRAP — letting a permit lapse forfeits the refund as well as the permit.Review timeline
Inspection process
Tips
- THIRTY DAYS FROM ISSUANCE TO FINISH, AND THE EXTENSION MUST BE ASKED FOR BEFORE THE PERMIT EXPIRES. TMC 15.50.050 gives no grace period after expiry, so diarise the date on the day the permit issues rather than when the machinery arrives.
- THE BOND IS DUE WHEN YOU APPLY, NOT WHEN YOU COLLECT THE PERMIT. That is earlier than most cities in this set ask for security, and it is refundable in full on an approved final inspection — it is not a fee.
- Structures exempt from permits under the adopted building code are outside this chapter altogether — TMC 15.50.010 carves them out by reference rather than by listing them.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tumwater building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Tumwater's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Tumwater yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Tumwater lands. Privacy.
Other permits in Tumwater
Demolition permit in other cities
Compare demolition permit fees across Washington →
Look up this fee in a different city →