Permit for electrical work in Pullman under the National Electrical Code and the state electrical safety standards, as adopted at PCC 2.35.010.

Verified 2026-09-16 · Source

When you need this permit

  • PCC 2.35.010: the Electrical Code “shall consist of: (1) the most current edition of the ‘National Electrical Code,’ as published by the National Fire Protection Association and adopted by the State of Washington; and (2) the ‘Electrical Safety Standard, Administration, and Installation’ regulations as adopted by the State of Washington (as codified in Chapter 296-45B WAC)”. NO EDITION YEAR IS PRINTED for either.
  • THE SECOND LIMB SITS IN THE WAC 296 SERIES, WHICH IS THE DEPARTMENT OF LABOR AND INDUSTRIES' TITLE, rather than in the 51-xx Building Code Council chapters the rest of the Construction Code cites. This entry records where the citation points and does NOT assert which agency inspects electrical work in Pullman; no such provision was read.
  • ELECTRICAL RANKS LAST IN THE CITY'S CONFLICT ORDER — seventh of seven in the list at PCC 2.10.010, so on PCC 2.10.050 it yields to every other component of the Construction Code.
  • PULLMAN HAVING AN ELECTRICAL CHAPTER AT ALL IS WORTH NOTING AGAINST ITS NEIGHBOURS: Walla Walla publishes Chapter 15.08 as “ELECTRICAL CODE (RESERVED)” with no sections, and Wenatchee's electrical chapter was repealed outright while its permit requirement survived.
  • BUDGET ROUGHLY DOUBLE THE PERMIT FEE AT THE COUNTER, AND HALF OF IT IS REFUNDABLE. PCC 2.15.070 amends IBC and IRC Section 105 to add: “To the cost of every permit authorized under Section 105 of the IBC and IRC, except a permit issued for purposes that require no earthmoving or transportation of earth or other debris, shall be added a cash deposit equal to the cost of the building permit as provided for in Section 2.15.020.” THIS IS A DEPOSIT, NOT A FEE — it secures removal of “any earth, fresh concrete, rock rubble or debris which is deposited on any portion of public right-of-way … by the permittee”, to be cleared “at the end of the work day” or as the Public Works Director directs. If the right-of-way is damaged or not restored, the Director may order restoration “as often as may be necessary”. The exemption is narrow: only permits requiring NO earthmoving or earth transport escape it. NOTE THAT IT CARRIES NO DOLLAR FIGURE AT ALL — it is defined as a multiple of a fee that is itself set by resolution.
  • PULLMAN PUBLISHES A CONFLICT ORDER AND IT IS NOT THE SAME ORDER AS ITS NEIGHBOURS'. PCC 2.10.050: “In case of a conflict between the provisions of the various codes regulating construction as listed in Section 2.10.010, the first listed code as listed in Section 2.10.010 of this Chapter shall govern unless specifically provided otherwise in Chapter 19.27 RCW, WAC 51-50 or elsewhere in this Title.” The list at 2.10.010 runs: the Washington State Building Code, then the Building Code (2.15), the Plumbing Code (2.20), the Mechanical Code (2.25), the Fire Code (3.16), the Energy Code (2.30) and the Electrical Code (2.35). >>> THE MECHANISM IS SHARED ACROSS CITIES AND THE ORDERING IS NOT. Walla Walla publishes the same first-listed-governs rule with plumbing LAST, behind the IBC, IRC, IMC and IFC; Pullman puts plumbing SECOND, ahead of mechanical, fire, energy and electrical. Wenatchee publishes the same idea again in different words. A reader who learned the rule in one of these cities would get the opposite answer about plumbing in the other.
  • THE DELEGATION IS STATED TWICE, IN TWO PLACES, WHICH IS THE OPPOSITE OF THE TRAP THE PREVIOUS CITY SET. Each chapter's own adopting sentence carries both the delegation and the roll — “the most current edition … as adopted by the State of Washington … as now existing and in accordance with any amendments that may hereafter be made thereto” — AND the definition of the Construction Code at PCC 2.10.010 repeats the roll for the Washington State Building Code as a whole. Walla Walla put its roll in a section by itself with no rolling phrase in any adopting sentence; Pullman says it in both places.
  • Appeals run to the Hearing Examiner under PCC 2.10.090 through 2.10.130, with separate sections for appeal procedures, the Examiner's determination, failure to obey a final order and appeal of the Examiner's own action. This guide does not summarise those sections, so no deadline or filing requirement is stated here.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building permit fee
PCC 2.15.020: “Fees shall be charged for building permits and any appeals to the Building Code defined in 2.15.010. Show full citationPCC 2.15.020: “Fees shall be charged for building permits and any appeals to the Building Code defined in 2.15.010. The types and amounts of such fees shall be set by resolution of the City Council except where such fees are specifically set forth in this Chapter, and such fees shall supersede any fee schedule contained in the International Building Code and International Residential Code.” NO DOLLAR AMOUNT APPEARS IN THE CODE and the resolution was not opened for this entry. TWO PARTS OF THAT SENTENCE ARE EASY TO SKIM PAST. First, the carve-out — “except where such fees are specifically set forth in this Chapter” — means the resolution is not the only source, so a reader who finds the resolution has not necessarily found everything. Second, the city's fees expressly SUPERSEDE the fee schedules printed in the IBC and IRC, so the model-code tables are not a fallback and should not be read as one. Refunds where no work has been done are also set by resolution.
Set by city council resolution

Review timeline

Plan review
Not published — contact the department

How long did your Electrical permit permit actually take in Pullman?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • ELECTRICAL IS BOTTOM OF THE CONFLICT ORDER IN PULLMAN. PCC 2.10.050 makes the first-listed code govern and electrical is seventh of seven at 2.10.010, so a clash with the building, plumbing, mechanical, fire or energy code resolves against it.
    • THE STATE LIMB IS CITED INTO THE LABOR AND INDUSTRIES RULES (Chapter 296-45B WAC), not the Building Code Council's 51-xx chapters. Ask the city who inspects electrical work before assuming it is the same counter that handles your building permit — this entry does not answer that.

    Frequently asked questions

    Pullman requires an electrical permit for: PCC 2.35.010: the Electrical Code “shall consist of: (1) the most current edition of the ‘National Electrical Code,’ as published by the National Fire Protection Association and adopted by the State of Washington; and (2) the ‘Electrical Safety Standard, Administration, and Installation’ regulations as adopted by the State of Washington (as codified in Chapter 296-45B WAC)”. NO EDITION YEAR IS PRINTED for either.; THE SECOND LIMB SITS IN THE WAC 296 SERIES, WHICH IS THE DEPARTMENT OF LABOR AND INDUSTRIES' TITLE, rather than in the 51-xx Building Code Council chapters the rest of the Construction Code cites. This entry records where the citation points and does NOT assert which agency inspects electrical work in Pullman; no such provision was read.; ELECTRICAL RANKS LAST IN THE CITY'S CONFLICT ORDER — seventh of seven in the list at PCC 2.10.010, so on PCC 2.10.050 it yields to every other component of the Construction Code.; PULLMAN HAVING AN ELECTRICAL CHAPTER AT ALL IS WORTH NOTING AGAINST ITS NEIGHBOURS: Walla Walla publishes Chapter 15.08 as “ELECTRICAL CODE (RESERVED)” with no sections, and Wenatchee's electrical chapter was repealed outright while its permit requirement survived.; BUDGET ROUGHLY DOUBLE THE PERMIT FEE AT THE COUNTER, AND HALF OF IT IS REFUNDABLE. PCC 2.15.070 amends IBC and IRC Section 105 to add: “To the cost of every permit authorized under Section 105 of the IBC and IRC, except a permit issued for purposes that require no earthmoving or transportation of earth or other debris, shall be added a cash deposit equal to the cost of the building permit as provided for in Section 2.15.020.” THIS IS A DEPOSIT, NOT A FEE — it secures removal of “any earth, fresh concrete, rock rubble or debris which is deposited on any portion of public right-of-way … by the permittee”, to be cleared “at the end of the work day” or as the Public Works Director directs. If the right-of-way is damaged or not restored, the Director may order restoration “as often as may be necessary”. The exemption is narrow: only permits requiring NO earthmoving or earth transport escape it. NOTE THAT IT CARRIES NO DOLLAR FIGURE AT ALL — it is defined as a multiple of a fee that is itself set by resolution.; PULLMAN PUBLISHES A CONFLICT ORDER AND IT IS NOT THE SAME ORDER AS ITS NEIGHBOURS'. PCC 2.10.050: “In case of a conflict between the provisions of the various codes regulating construction as listed in Section 2.10.010, the first listed code as listed in Section 2.10.010 of this Chapter shall govern unless specifically provided otherwise in Chapter 19.27 RCW, WAC 51-50 or elsewhere in this Title.” The list at 2.10.010 runs: the Washington State Building Code, then the Building Code (2.15), the Plumbing Code (2.20), the Mechanical Code (2.25), the Fire Code (3.16), the Energy Code (2.30) and the Electrical Code (2.35). >>> THE MECHANISM IS SHARED ACROSS CITIES AND THE ORDERING IS NOT. Walla Walla publishes the same first-listed-governs rule with plumbing LAST, behind the IBC, IRC, IMC and IFC; Pullman puts plumbing SECOND, ahead of mechanical, fire, energy and electrical. Wenatchee publishes the same idea again in different words. A reader who learned the rule in one of these cities would get the opposite answer about plumbing in the other.; THE DELEGATION IS STATED TWICE, IN TWO PLACES, WHICH IS THE OPPOSITE OF THE TRAP THE PREVIOUS CITY SET. Each chapter's own adopting sentence carries both the delegation and the roll — “the most current edition … as adopted by the State of Washington … as now existing and in accordance with any amendments that may hereafter be made thereto” — AND the definition of the Construction Code at PCC 2.10.010 repeats the roll for the Washington State Building Code as a whole. Walla Walla put its roll in a section by itself with no rolling phrase in any adopting sentence; Pullman says it in both places.; Appeals run to the Hearing Examiner under PCC 2.10.090 through 2.10.130, with separate sections for appeal procedures, the Examiner's determination, failure to obey a final order and appeal of the Examiner's own action. This guide does not summarise those sections, so no deadline or filing requirement is stated here.. If your project isn't listed, confirm with City of Pullman at (509) 334-4555 before starting work.

    In Pullman, the published Building permit fee is: Set by city council resolution. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Pullman does not publish a plan-review timeline for this permit. Contact City of Pullman at (509) 334-4555 for current turnaround.

    You'll need: Building permit application. See the required-documents checklist on this page for details on each.

    Apply through City of Pullman at 190 SE Crestview St., Pullman, WA 99163. Phone: (509) 334-4555. Official information: https://www.pullman-wa.gov/.

    Pullman, Washington has adopted: PCC 2.10.010 defines “the Construction Code” as: “(1) The Washington State Building Code as now existing and in accordance with any amendments that may hereafter be made thereto except as specifically provided otherwise in this Title; (2) The Building Code (Chapter 2.15); (3) The Plumbing Code (Chapter 2.20); (4) The Mechanical Code (Chapter 2.25); (5) The Fire Code (Chapter 3.16); (6) The Energy Code (Chapter 2.30); (7) The Electrical Code (Chapter 2.35)”.; IBC — PCC 2.15.010(1): “the most current edition of the International Building Code … and Appendix ‘J’ (Grading) as adopted by the State of Washington and its additions, deletions, and exceptions noted in WAC 51-50 as now existing and in accordance with any amendments that may hereafter be made thereto”.; IRC — PCC 2.15.010(2): “the most current edition of the International Residential Code … as adopted by the State of Washington”, WAC 51-51, same rolling terms.; UPC — PCC 2.20.010: “the most current edition of the Uniform Plumbing Code … as adopted by the State of Washington”, Chapter 51-56 WAC, same rolling terms.; IMC and IFGC — PCC 2.25.010: both at “the most current edition … as adopted by the State of Washington”, Chapter 51-52 WAC, same rolling terms.; Washington State Energy Code — PCC 2.30.010: “The most current edition of the ‘Washington State Energy Code’ (Commercial Provisions and Residential Provisions), as now existing and in accordance with any amendments that may hereafter be made thereto as adopted by the Washington State Building Code Council (as codified in Chapters 51-11C and 51-11R WAC).”; NEC — PCC 2.35.010: “the most current edition of the ‘National Electrical Code,’ as published by the National Fire Protection Association and adopted by the State of Washington”, together with the state “Electrical Safety Standard, Administration, and Installation” regulations at Chapter 296-45B WAC.; THE FIRE CODE IS PART OF THE CONSTRUCTION CODE BUT LIVES AT CHAPTER 3.16, OUTSIDE TITLE 2, and was NOT opened for this entry.. Local amendments apply — see the Pullman overview page for the full list.

    Two things together, and neither carries a year. PCC 2.35.010 adopts the most current edition of the National Electrical Code as published by the NFPA and adopted by the State of Washington, plus the state's “Electrical Safety Standard, Administration, and Installation” regulations at Chapter 296-45B WAC. Because both are delegated to the state, the operative edition changes without the city amending its code.

    Sources & verification

    Verified against official sources. Last reviewed 2026-09-16.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pullman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    Pullman's permit history isn't searchable here yet

    This page covers what the permit requires. What we don't have for Pullman yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.