Unincorporated Natrona County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Natrona County, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 N. Center St, Room 205, Casper, WY 82601
Phone
(307) 235-9435
Office hours
Monday–Friday, 8:00 AM–5:00 PM

Published scheduling rules

  • Fire sprinkler permits are handled entirely by NCFPD, not the county Building Department — apply and schedule inspections through NCFPDpermits.com. (Fire Sprinkler System Permit)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Footing / Foundation

    Before concrete pour — required for detached ADUs with new foundations

  2. 2

    Framing

    Structural framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; separate trade permits required

  4. 4

    Final

    All work complete per approved plans, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings added)

    Before concrete pour, for additions with new foundation work

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed (separate trade permits required)

  4. 4

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Before concrete pour — verify footing dimensions, reinforcement, and foundation type

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; scheduled with the Building Department at 307-235-9435

  4. 4

    Final

    All work complete per approved plans and adopted codes, ready for occupancy

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    For any structural alterations, before wall cover

  2. 2

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed (separate trade permits required)

  3. 3

    Final

    Life-safety, egress, and code compliance verified for occupancy

Applies to: Deck Permit

  1. 1

    Footing

    Before concrete pour — footing depth and pier placement

  2. 2

    Framing

    Ledger attachment, joist hangers, beam sizing before decking installed

  3. 3

    Final

    Guardrails, stair geometry, and overall construction verified per 2024 IRC

Applies to: Plumbing Permit

  1. 1

    Underground / Under-Slab

    Before concrete pour or backfill — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, conduit, and box placement before walls are closed

  2. 2

    Final

    All devices installed, panel labeled, system energized and inspected by the county Building Department

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Wiring, conduit, and box placement inspected before walls are closed, if applicable

  2. 2

    Final

    EVSE equipment installed, circuit labeled, system energized and inspected by the county Building Department

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In / Device Placement

    Wiring and device placement inspected before concealment, if applicable to the installation

  2. 2

    Acceptance Test

    Full system acceptance testing per NFPA 72, required before the permit is closed out; must be scheduled 24-48 hours in advance through the NCFPDpermits.com portal

Applies to: Fire Sprinkler System Permit

  1. 1

    Rough-In / Underground

    Piping and underground supply inspected before concealment or backfill, if applicable

  2. 2

    Acceptance Test

    Full hydrostatic and system acceptance testing per NFPA 13/13R/13D, required before the permit is closed out; must be scheduled 24-48 hours in advance through the NCFPDpermits.com portal

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment placement and ductwork/venting before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before concealment

  2. 2

    Final

    Panel mounting/racking, interconnection point, and system energization verified

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Natrona County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Natrona County building permits

Get alerts for Unincorporated Natrona County