Unincorporated Natrona County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Natrona County, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 N. Center St, Room 205, Casper, WY 82601
Phone
(307) 235-9435
Office hours
Monday–Friday, 8:00 AM–5:00 PM

Published scheduling rules

  • Fire sprinkler permits are handled entirely by NCFPD, not the county Building Department — apply and schedule inspections through NCFPDpermits.com. (Fire Sprinkler System Permit)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Footing / Foundation

    Before concrete pour — required for detached ADUs with new foundations

  2. 2

    Framing

    Structural framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; separate trade permits required

  4. 4

    Final

    All work complete per approved plans, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings added)

    Before concrete pour, for additions with new foundation work

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed (separate trade permits required)

  4. 4

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Before concrete pour — verify footing dimensions, reinforcement, and foundation type

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; scheduled with the Building Department at 307-235-9435

  4. 4

    Final

    All work complete per approved plans and adopted codes, ready for occupancy

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    For any structural alterations, before wall cover

  2. 2

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed (separate trade permits required)

  3. 3

    Final

    Life-safety, egress, and code compliance verified for occupancy

Applies to: Deck Permit

  1. 1

    Footing

    Before concrete pour — footing depth and pier placement

  2. 2

    Framing

    Ledger attachment, joist hangers, beam sizing before decking installed

  3. 3

    Final

    Guardrails, stair geometry, and overall construction verified per 2024 IRC

Applies to: Plumbing Permit

  1. 1

    Underground / Under-Slab

    Before concrete pour or backfill — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, conduit, and box placement before walls are closed

  2. 2

    Final

    All devices installed, panel labeled, system energized and inspected by the county Building Department

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Wiring, conduit, and box placement inspected before walls are closed, if applicable

  2. 2

    Final

    EVSE equipment installed, circuit labeled, system energized and inspected by the county Building Department

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In / Device Placement

    Wiring and device placement inspected before concealment, if applicable to the installation

  2. 2

    Acceptance Test

    Full system acceptance testing per NFPA 72, required before the permit is closed out; must be scheduled 24-48 hours in advance through the NCFPDpermits.com portal

Applies to: Fire Sprinkler System Permit

  1. 1

    Rough-In / Underground

    Piping and underground supply inspected before concealment or backfill, if applicable

  2. 2

    Acceptance Test

    Full hydrostatic and system acceptance testing per NFPA 13/13R/13D, required before the permit is closed out; must be scheduled 24-48 hours in advance through the NCFPDpermits.com portal

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment placement and ductwork/venting before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before concealment

  2. 2

    Final

    Panel mounting/racking, interconnection point, and system energization verified

Unincorporated Natrona County building permits

Get alerts for Unincorporated Natrona County