Fredonia building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Fredonia, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 25 N Main St. / PO Box 217, Fredonia, AZ 86022
- Phone
- 928-643-7241
- Office hours
- Monday - Thursday, 7:30 A.M. to 5:30 P.M. (Fax: 928-643-7627). Applications are submitted in person or by mail using the Town's paper Building Permit Packet (permit application, requirement checklist, soils test forms, owner/builder agreement, fee schedule and general information). Per Town Code § 151.06, the Building Inspector's administrative authority for all building, plumbing, electrical, and other inspections is vested in the Office of the Town Clerk; the Council may authorize additional persons to perform inspection work or other functions required by the chapter.
- Website
- Official site
Published scheduling rules
- Given Fredonia's remote location and smaller housing stock, manufactured home placement is common enough that the Town's standard packet has dedicated inspection line items (Lag; Jacks & Tie Downs) specifically for manufactured homes, alongside the standard site-built inspection sequence. (Manufactured Home Placement Permit)
- OSFM inspection requests are submitted via OSFM's own online Inspection Request form; a re-inspection caused by a violation or a missed/cancelled scheduled inspection is billed at OSFM's own re-inspection fee rate before the re-inspection is conducted (Arizona Administrative Code R4-36-303(B), R4-36-202(A)(4)) (Fire Sprinkler / Fire Alarm System Permit)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Footing & Set Back
Footing reinforcement inspected before concrete pour; property setbacks verified against zoning requirements at this inspection
- 2
Foundation
Foundation wall reinforcement inspected before concrete pour; damp-proof coating checked at a later inspection
- 3
Underground Plumbing
Inspected before it is covered and the floor is poured
- 4
Shear Wall & Sheeting
Inspected before being covered by house wrap or other material
- 5
4-Way (Framing, Rough Plumbing, Rough Electrical, Rough Mechanical, Rough Gas)
Combined rough-in inspection of framing and all rough trade work
- 6
Insulation
Inspected before being covered by sheetrock or other material
- 7
Drywall/Wallboard
Rough drywall inspected before taping and applying drywall mud
- 8
Vapor Barrier/House Wrap
Inspected on the exterior before applying siding or other finishes
- 9
Final Inspection
Required before a Certificate of Occupancy (or temporary occupancy permit) is granted; no building may be occupied before this passes
Applies to: Manufactured Home Placement Permit
- 1
Footing & Set Back
Foundation pad/footing and setback verification
- 2
Lag
Inspects lag, both roof and wall, specific to manufactured homes
- 3
Jacks & Tie Downs
Inspects tie downs and jacks on manufactured homes
- 4
Final Inspection
Required before occupancy/Certificate of Occupancy
Applies to: Electrical Permit
- 1
4-Way (includes Rough Electrical)
Rough electrical inspected together with framing, rough plumbing, rough mechanical, and rough gas
- 2
Meter Base
If applicable
- 3
Final Inspection
Devices installed and verified per 2006 NEC before Certificate of Occupancy is granted
Applies to: EV Charger / EVSE Permit
- 1
4-Way (includes Rough Electrical)
Rough electrical for the EVSE circuit inspected together with framing, rough plumbing, rough mechanical, and rough gas, per the Town's standard combined inspection practice
- 2
Meter Base
If applicable
- 3
Final Inspection
EVSE circuit and connections verified per 2006 NEC before sign-off
Applies to: Fire Sprinkler / Fire Alarm System Permit
- 1
OSFM Field Inspection (Fire Protection System)
The holder of an OSFM operational or construction permit is entitled to inspections as prescribed in Arizona Administrative Code Title 4, Chapter 36; scheduled via OSFM's own online Inspection Request form
- 2
OSFM Re-inspection (if required)
Billed at OSFM's re-inspection fee rate if a scheduled inspection is missed/cancelled without 24 hours' notice, or if the site fails inspection
- 3
Town of Fredonia Final Inspection
Required under the parallel Town building permit before the structure may be occupied and a Certificate of Occupancy issued; does not substitute for OSFM's own fire-system inspection
Applies to: Plumbing Permit
- 1
Underground Plumbing
Inspected before it is covered and the floor is poured
- 2
4-Way (includes Rough Plumbing)
Rough plumbing inspected together with framing, rough electrical, rough mechanical, and rough gas
- 3
Final Inspection
Fixtures connected and verified before Certificate of Occupancy is granted
Applies to: Certificate of Occupancy / Change of Use
- 1
Business Premises Inspection
The Business License Application states that inspections of the premises are involved 'including, but not limited to: fire, building, zoning and safety,' though no dedicated inspection checklist or schedule distinct from these general categories was found published
- 2
Final Inspection (if construction/alteration involved)
Required under the general Building Permit before a Certificate of Occupancy is issued for any construction or alteration tied to the change of use
Applies to: Mechanical / HVAC Permit
- 1
4-Way (includes Rough Mechanical)
Rough mechanical inspected together with framing, rough plumbing, rough electrical, and rough gas
- 2
Final Inspection
Equipment operational and verified before Certificate of Occupancy is granted
Applies to: Residential Solar Photovoltaic (PV) Permit
- 1
4-Way (includes Rough Electrical)
Rough electrical (PV interconnection wiring, disconnects) inspected together with framing, rough plumbing, rough mechanical, and rough gas, per the same combined-trade inspection sequence used for all building permits
- 2
Final Inspection
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified per the 2006 NEC/IBC before Certificate of Occupancy or sign-off
Final inspection only: Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fredonia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Fredonia building permits
Get alerts for Fredonia
We'll email you when Fredonia's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.