Required for new single-family residential construction in the Town of Fredonia. Reviewed against the 2006 IRC/IBC as adopted by the Town (Ord. 15-003). Applications are submitted in person or by mail using the Town's paper Building Permit Packet; there is no online portal.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new residential construction within Fredonia town limits; no building or structure regulated by Town Code and adopted building codes may be erected without a permit obtained from the Building Official
  • Plans reviewed against the 2006 IRC/IBC as adopted by the Town of Fredonia (Town Code § 151.01)
  • Completed Building Permit Application listing owner, architect/engineer, general contractor, and electrical/plumbing/mechanical contractor names, addresses, phone numbers, and license numbers
  • Site/Plot Plan (2 copies): scale and north arrow; lot lines, setbacks, adjacent streets/roads/rights-of-way; location of all existing structures on subject and adjoining properties with utility lines, poles, septic tank/field fully dimensioned; location of proposed construction/improvements with signage locations; necessary explanatory notes
  • Construction Drawings (2 copies): footings detail; foundation with structural detail schedule and elevations; floor plans with room sizes/partitions/cross-section; insulation system (R-38 ceilings, R-16 interior walls, R-19 exterior walls, R-19 floors, R-9 basements); roof details; electrical, plumbing, mechanical, and gas plans; shear walls with tie-downs; porch/entry/stairs details referenced to floor/foundation/plat plans with snow load justification; material schedules and general notes
  • Owner/Builder Certificate (notarized) if applicable, in the County of Coconino, State of Arizona Owner-builder
  • Soils test and compaction test performed by a qualified engineer, with recommendations and a follow-up compliance report, completed before or during the footing inspection (using the Town's two Geotechnical Data & Compliance Report forms) — required for new commercial/residential construction and anything attached, though not every project requires it
  • Septic Permit (Health Department clearance) if outside the Town sewer service area
  • Property corner pins located and staked for setback verification (survey required if pins are missing or incorrect)
  • Res and/or Com Check energy compliance report (2 copies), per www.energycodes.gov
  • Water system approved by ADEQ and proof of legal access meeting Town Standard Specifications required before permit issuance
  • Manufactured homes must be rated for the area to meet current energy code provisions and comply with Town Code manufactured-home provisions

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review FeeTown of Fredonia Building Permit Packet, p.1: 'a non refundable plan review fee must be paid; the amount paid will be applied toward the total permit price.' No itemized fee schedule/valuation table was found published by the Town despite the packet cover letter referencing one — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for the current amount.
Non-refundable fee due at submittal (exact amount not published)
Permit Extension (before expiration)Town of Fredonia Building Permit Packet, p.8 — requested in writing with justifiable cause demonstrated, before the 180-day permit expires.
$15
Permit Renewal (after expiration, within 30 days)Town of Fredonia Building Permit Packet, p.8 — required if the original 180-day permit is allowed to lapse; new work must also comply with any Town Code/building-code changes adopted since original issuance.
$100

Review timeline

Plan reviewFredonia’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Construction) permit actually take in Fredonia?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing & Set Back

    Footing reinforcement inspected before concrete pour; property setbacks verified against zoning requirements at this inspection

  2. 2

    Foundation

    Foundation wall reinforcement inspected before concrete pour; damp-proof coating checked at a later inspection

  3. 3

    Underground Plumbing

    Inspected before it is covered and the floor is poured

  4. 4

    Shear Wall & Sheeting

    Inspected before being covered by house wrap or other material

  5. 5

    4-Way (Framing, Rough Plumbing, Rough Electrical, Rough Mechanical, Rough Gas)

    Combined rough-in inspection of framing and all rough trade work

  6. 6

    Insulation

    Inspected before being covered by sheetrock or other material

  7. 7

    Drywall/Wallboard

    Rough drywall inspected before taping and applying drywall mud

  8. 8

    Vapor Barrier/House Wrap

    Inspected on the exterior before applying siding or other finishes

  9. 9

    Final Inspection

    Required before a Certificate of Occupancy (or temporary occupancy permit) is granted; no building may be occupied before this passes

See the full Fredonia inspection guide — scheduling & re-inspection fees →

Tips

  • The Town of Fredonia's own Building Permit Packet states plainly: 'After the completed application is received, please allow 10 working days for review, approval and issuance of the building permit' — this is a directly published, town-specific figure, not an inferred or statutory-default figure. Source: Building Permit Packet, p.3.
  • Arizona's A.R.S. § 9-835 15-working-day deemed-approval mechanism for single-family residential permits applies only to municipalities with a population of 30,000 or more; Fredonia (population roughly 1,300) falls well under that threshold, so § 9-835's automatic-approval trigger is not the operative standard here — the Town's own directly published 10-working-day figure governs instead.
  • DO NOT order concrete before your inspection is scheduled and passed — the Town explicitly warns that pouring without an approved inspection is not allowed, and builders who jump the gun risk having to cancel concrete orders.
  • A permit allots a limited number of inspections (each required inspection plus one re-inspection); exceeding that allotment means per-inspection charges for the rest of the project.
  • Given Fredonia's remote location on the Utah border, confirm current fee amounts and any recent unpublished administrative changes directly with the Town Office (928-643-7241) before budgeting a project — the published packet fee schedule for itemized dollar amounts could not be located despite exhaustive search.

Frequently asked questions

Fredonia requires a residential building permit (new construction) for: Building permit required for new residential construction within Fredonia town limits; no building or structure regulated by Town Code and adopted building codes may be erected without a permit obtained from the Building Official; Plans reviewed against the 2006 IRC/IBC as adopted by the Town of Fredonia (Town Code § 151.01); Completed Building Permit Application listing owner, architect/engineer, general contractor, and electrical/plumbing/mechanical contractor names, addresses, phone numbers, and license numbers; Site/Plot Plan (2 copies): scale and north arrow; lot lines, setbacks, adjacent streets/roads/rights-of-way; location of all existing structures on subject and adjoining properties with utility lines, poles, septic tank/field fully dimensioned; location of proposed construction/improvements with signage locations; necessary explanatory notes; Construction Drawings (2 copies): footings detail; foundation with structural detail schedule and elevations; floor plans with room sizes/partitions/cross-section; insulation system (R-38 ceilings, R-16 interior walls, R-19 exterior walls, R-19 floors, R-9 basements); roof details; electrical, plumbing, mechanical, and gas plans; shear walls with tie-downs; porch/entry/stairs details referenced to floor/foundation/plat plans with snow load justification; material schedules and general notes; Owner/Builder Certificate (notarized) if applicable, in the County of Coconino, State of Arizona; Soils test and compaction test performed by a qualified engineer, with recommendations and a follow-up compliance report, completed before or during the footing inspection (using the Town's two Geotechnical Data & Compliance Report forms) — required for new commercial/residential construction and anything attached, though not every project requires it; Septic Permit (Health Department clearance) if outside the Town sewer service area; Property corner pins located and staked for setback verification (survey required if pins are missing or incorrect); Res and/or Com Check energy compliance report (2 copies), per www.energycodes.gov; Water system approved by ADEQ and proof of legal access meeting Town Standard Specifications required before permit issuance; Manufactured homes must be rated for the area to meet current energy code provisions and comply with Town Code manufactured-home provisions. If your project isn't listed, confirm with Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 928-643-7241 before starting work.

In Fredonia, the published Plan Review Fee is: Non-refundable fee due at submittal (exact amount not published). Additional published fees: Permit Extension (before expiration) — $15; Permit Renewal (after expiration, within 30 days) — $100. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town of Fredonia's Building Permit Packet directly states: 'After the completed application is received, please allow 10 working days for review, approval and issuance of the building permit.' This is a town-published figure, not a statutory default — Arizona's A.R.S. § 9-835 15-working-day automatic-approval provision for single-family permits only applies to municipalities of 30,000+ population, which does not include Fredonia.

You'll need: Town of Fredonia Building Permit Application; Site/Plot Plan (2 copies); Construction Drawings (2 copies); Res and/or Com Check (2 copies). Depending on your project, Fredonia may also ask for: Geotechnical Data & Compliance Report (Backfill and Final Grade; and Prior to Footing and Foundation); Owner Builder Certificate; Septic Permit. See the required-documents checklist on this page for details on each.

Fredonia requires 9 inspection(s) for a residential building permit (new construction), in order: Footing & Set Back, Foundation, Underground Plumbing, Shear Wall & Sheeting, 4-Way (Framing, Rough Plumbing, Rough Electrical, Rough Mechanical, Rough Gas), Insulation, Drywall/Wallboard, Vapor Barrier/House Wrap, Final Inspection. Schedule each through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) (928-643-7241).

Apply through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 25 N Main St. / PO Box 217, Fredonia, AZ 86022. Phone: 928-643-7241, email: townclerk@fredonia.net. Office hours: Monday - Thursday, 7:30 A.M. to 5:30 P.M. (Fax: 928-643-7627). Applications are submitted in person or by mail using the Town's paper Building Permit Packet (permit application, requirement checklist, soils test forms, owner/builder agreement, fee schedule and general information). Per Town Code § 151.06, the Building Inspector's administrative authority for all building, plumbing, electrical, and other inspections is vested in the Office of the Town Clerk; the Council may authorize additional persons to perform inspection work or other functions required by the chapter.. Official information: https://www.fredoniaaz.gov/forms-documents.

Fredonia, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. §§ 9-801 et seq., cited as the statutory authority in Town Code Chapter 151). The Town of Fredonia runs its own independent Building Department (administered through the Office of the Town Clerk) and adopts and administers its own construction codes; it does not defer building permitting to Coconino County. Source: Town of Fredonia Code of Ordinances, Chapter 151 (Building Regulations; Construction); Town of Fredonia Building Permit Packet (rev. 05/01/2011).; International Building Code (IBC), 2006 Edition, and International Residential Code (IRC), 2006 Edition, both copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Building Code of the Town of Fredonia' (Town Code § 151.01; 1974 Code § 7-1-1; Ord. 15-003, passed 7-14-2015). At least three copies of each code are required to be kept on file in the Office of the Clerk for public inspection. Source: Town of Fredonia Code of Ordinances § 151.01.; International Plumbing Code (IPC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Plumbing Code of the Town of Fredonia' (Town Code § 151.03; 1974 Code, Art. 7-2; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.03.; National Electrical Code (NEC), 2006 Edition, copyrighted by the National Fire Prevention Association [sic, National Fire Protection Association], adopted by reference as the 'Uniform Electrical Code of the Town of Fredonia' (Town Code § 151.04; 1974 Code, Art. 7-3; Ord. 15-003, passed 7-14-2015). Cross-reference: electricity provisions generally, Town Code Chapter 50. Source: Town of Fredonia Code of Ordinances § 151.04.; International Mechanical Code (IMC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Mechanical Code of the Town of Fredonia' (Town Code § 151.05; 1974 Code, Art. 7-4; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.05.; The Town's currently codified adoption cycle (2006 ICC family / 2006 NEC) was last legislatively re-adopted by Ord. 15-003 on 7-14-2015; the Town's Code of Ordinances library (American Legal Publishing, 2023 S-3 supplement) reflects legislation current through Ordinance 2022-003 (passed 5-3-2022), and no building-code-cycle update superseding the 2006 editions was found published anywhere on the Town's site, in the Code of Ordinances, or via Wayback Machine as of July 2026. This is a confirmed gap after an exhaustive chase, not an assumption — Fredonia's adopted code edition is genuinely older than the 2018-2024 cycles used by larger nearby Coconino County jurisdictions (e.g., City of Page runs 2018 codes; City of Buckeye runs 2024 codes). Source: Town of Fredonia Code of Ordinances Overview page (codelibrary.amlegal.com), 'current through Ord. 2022-003, passed 5-3-2022' notice.; Building Inspector authority (Town Code § 151.06; 1974 Code, Art. 7-5): the Building Inspector's administrative authority for all matters pertaining to building, plumbing, electrical, or other inspections referenced anywhere in Chapter 151 is vested in the Office of the (Town) Clerk; the Town Council may authorize additional persons as needed to perform inspection work or other required functions. Source: Town of Fredonia Code of Ordinances § 151.06.; Sidewalk construction (Town Code § 151.07; 1974 Code, Art. 7-6): unlawful for any person to construct a sidewalk, where grade has been established, except to lines and grades given by the Town Engineer (or by special Town Council permission to deviate); all sidewalks must be constructed under Town Engineer inspection. Penalty per Town Code § 10.99. Source: Town of Fredonia Code of Ordinances § 151.07.; Building must conform to zoning ordinance (Town Code § 152.090; § 152.02; 1974 Code §§ 14-6-1, 7-1-2): whenever a building permit is issued and a building inspection performed, the building must conform to the Town's Zoning Ordinance in addition to Chapter 151. No building permit may be issued by the Building Inspector or Town Clerk unless there has been full compliance with the building chapter and the planning and zoning ordinance by the owner or prior owners of the property. Source: Town of Fredonia Code of Ordinances §§ 151.02, 152.090.. Local amendments apply — see the Fredonia overview page for the full list.

The 2006 IRC and 2006 IBC, as adopted by the Town of Fredonia via Ordinance 15-003 (passed 7-14-2015), codified at Town Code § 151.01. As of July 2026, no more recent code-cycle update was found published — Fredonia's adopted edition is older than many other Arizona jurisdictions.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fredonia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.