Residential Solar Photovoltaic (PV) Permit in Fredonia, Arizona

Rooftop or ground-mount residential solar PV installation within the Town of Fredonia is not a separately named permit type — the Town's own Building Permit Packet has no solar/photovoltaic/renewable-energy line item, so a PV installation is processed through the same combined Building Permit Application used for all trades (building, electrical, plumbing, mechanical), reviewed against the 2006 NEC as adopted by the Town (Town Code § 151.04, Ord. 15-003) for the electrical/interconnection scope and the 2006 IBC/IRC (Town Code § 151.01) for the racking/mounting structural scope.

Verified 2026-07-20 · Source

When you need this permit

  • Building permit required for any structure/system regulated by Town Code and the adopted building codes, including electrical installation work — no dedicated solar exemption or shortcut exists
  • Electrical scope governed by the 2006 NEC as adopted by the Town of Fredonia (Town Code § 151.04)
  • Structural/racking scope governed by the 2006 IBC/IRC as adopted by the Town (Town Code § 151.01)
  • Completed Building Permit Application listing owner and the electrical contractor's (and, if structural modification is needed, general contractor's) name, address, phone, and license number
  • Site/Plot Plan showing PV array location and equipment placement
  • Property must conform to the Town's Zoning Ordinance in addition to Chapter 151 before a permit will be issued (Town Code §§ 151.02, 152.090)
  • No dedicated solar/PV-specific requirement, checklist, or fee line was found published in the Building Permit Packet or Code of Ordinances — confirm current process directly with the Town Office, 928-643-7241

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review FeeTown of Fredonia Building Permit Packet, p.1. No itemized solar/PV-specific or electrical-specific fee line was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.
Non-refundable fee due at submittal (exact amount not published)

Review timeline

Plan reviewFredonia’s published plan-review target
10–10 business days

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Fredonia?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    4-Way (includes Rough Electrical)

    Rough electrical (PV interconnection wiring, disconnects) inspected together with framing, rough plumbing, rough mechanical, and rough gas, per the same combined-trade inspection sequence used for all building permits

  2. 2

    Final Inspection

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified per the 2006 NEC/IBC before Certificate of Occupancy or sign-off

See the full Fredonia inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'solar permit' in Fredonia — a PV installation is submitted on the same combined Building Permit Application used for every other trade, with the electrical contractor's license information listed. Contractor
  • The Town's own Building Permit Packet directly publishes a 10-working-day review-and-issuance timeframe, which applies to solar/electrical permits the same as any other permit type processed through the same packet.
  • Fredonia's adopted 2006 NEC is a considerably older cycle than the 2017/2020 NEC editions (with their more detailed rapid-shutdown and PV-specific provisions) used by many other Arizona jurisdictions — confirm equipment listing/labeling compatibility with the Town Office before finalizing your PV design.
  • No itemized fee schedule was found published for any permit type in Fredonia, including solar/electrical — call the Town Office for a project-specific quote.

Frequently asked questions

Fredonia requires a residential solar photovoltaic (pv) permit for: Building permit required for any structure/system regulated by Town Code and the adopted building codes, including electrical installation work — no dedicated solar exemption or shortcut exists; Electrical scope governed by the 2006 NEC as adopted by the Town of Fredonia (Town Code § 151.04); Structural/racking scope governed by the 2006 IBC/IRC as adopted by the Town (Town Code § 151.01); Completed Building Permit Application listing owner and the electrical contractor's (and, if structural modification is needed, general contractor's) name, address, phone, and license number; Site/Plot Plan showing PV array location and equipment placement; Property must conform to the Town's Zoning Ordinance in addition to Chapter 151 before a permit will be issued (Town Code §§ 151.02, 152.090); No dedicated solar/PV-specific requirement, checklist, or fee line was found published in the Building Permit Packet or Code of Ordinances — confirm current process directly with the Town Office, 928-643-7241. If your project isn't listed, confirm with Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 928-643-7241 before starting work.

In Fredonia, the published Plan Review Fee is: Non-refundable fee due at submittal (exact amount not published). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's Building Permit Packet directly states a 10-working-day review-and-issuance timeframe for the combined Building Permit Application, which governs solar/electrical work the same as any other permit type.

You'll need: Town of Fredonia Building Permit Application; Site/Plot Plan. See the required-documents checklist on this page for details on each.

Fredonia requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: 4-Way (includes Rough Electrical), Final Inspection. Schedule each through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) (928-643-7241).

Apply through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 25 N Main St. / PO Box 217, Fredonia, AZ 86022. Phone: 928-643-7241, email: townclerk@fredonia.net. Office hours: Monday - Thursday, 7:30 A.M. to 5:30 P.M. (Fax: 928-643-7627). Applications are submitted in person or by mail using the Town's paper Building Permit Packet (permit application, requirement checklist, soils test forms, owner/builder agreement, fee schedule and general information). Per Town Code § 151.06, the Building Inspector's administrative authority for all building, plumbing, electrical, and other inspections is vested in the Office of the Town Clerk; the Council may authorize additional persons to perform inspection work or other functions required by the chapter.. Official information: https://www.fredoniaaz.gov/forms-documents.

Fredonia, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. §§ 9-801 et seq., cited as the statutory authority in Town Code Chapter 151). The Town of Fredonia runs its own independent Building Department (administered through the Office of the Town Clerk) and adopts and administers its own construction codes; it does not defer building permitting to Coconino County. Source: Town of Fredonia Code of Ordinances, Chapter 151 (Building Regulations; Construction); Town of Fredonia Building Permit Packet (rev. 05/01/2011).; International Building Code (IBC), 2006 Edition, and International Residential Code (IRC), 2006 Edition, both copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Building Code of the Town of Fredonia' (Town Code § 151.01; 1974 Code § 7-1-1; Ord. 15-003, passed 7-14-2015). At least three copies of each code are required to be kept on file in the Office of the Clerk for public inspection. Source: Town of Fredonia Code of Ordinances § 151.01.; International Plumbing Code (IPC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Plumbing Code of the Town of Fredonia' (Town Code § 151.03; 1974 Code, Art. 7-2; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.03.; National Electrical Code (NEC), 2006 Edition, copyrighted by the National Fire Prevention Association [sic, National Fire Protection Association], adopted by reference as the 'Uniform Electrical Code of the Town of Fredonia' (Town Code § 151.04; 1974 Code, Art. 7-3; Ord. 15-003, passed 7-14-2015). Cross-reference: electricity provisions generally, Town Code Chapter 50. Source: Town of Fredonia Code of Ordinances § 151.04.; International Mechanical Code (IMC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Mechanical Code of the Town of Fredonia' (Town Code § 151.05; 1974 Code, Art. 7-4; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.05.; The Town's currently codified adoption cycle (2006 ICC family / 2006 NEC) was last legislatively re-adopted by Ord. 15-003 on 7-14-2015; the Town's Code of Ordinances library (American Legal Publishing, 2023 S-3 supplement) reflects legislation current through Ordinance 2022-003 (passed 5-3-2022), and no building-code-cycle update superseding the 2006 editions was found published anywhere on the Town's site, in the Code of Ordinances, or via Wayback Machine as of July 2026. This is a confirmed gap after an exhaustive chase, not an assumption — Fredonia's adopted code edition is genuinely older than the 2018-2024 cycles used by larger nearby Coconino County jurisdictions (e.g., City of Page runs 2018 codes; City of Buckeye runs 2024 codes). Source: Town of Fredonia Code of Ordinances Overview page (codelibrary.amlegal.com), 'current through Ord. 2022-003, passed 5-3-2022' notice.; Building Inspector authority (Town Code § 151.06; 1974 Code, Art. 7-5): the Building Inspector's administrative authority for all matters pertaining to building, plumbing, electrical, or other inspections referenced anywhere in Chapter 151 is vested in the Office of the (Town) Clerk; the Town Council may authorize additional persons as needed to perform inspection work or other required functions. Source: Town of Fredonia Code of Ordinances § 151.06.; Sidewalk construction (Town Code § 151.07; 1974 Code, Art. 7-6): unlawful for any person to construct a sidewalk, where grade has been established, except to lines and grades given by the Town Engineer (or by special Town Council permission to deviate); all sidewalks must be constructed under Town Engineer inspection. Penalty per Town Code § 10.99. Source: Town of Fredonia Code of Ordinances § 151.07.; Building must conform to zoning ordinance (Town Code § 152.090; § 152.02; 1974 Code §§ 14-6-1, 7-1-2): whenever a building permit is issued and a building inspection performed, the building must conform to the Town's Zoning Ordinance in addition to Chapter 151. No building permit may be issued by the Building Inspector or Town Clerk unless there has been full compliance with the building chapter and the planning and zoning ordinance by the owner or prior owners of the property. Source: Town of Fredonia Code of Ordinances §§ 151.02, 152.090.. Local amendments apply — see the Fredonia overview page for the full list.

No. The Town's Building Permit Packet has no solar/photovoltaic-specific line item. A PV installation is processed through the same combined Building Permit Application used for all trades, reviewed against the 2006 NEC (electrical scope) and 2006 IBC/IRC (structural/racking scope) as adopted by the Town.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fredonia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.