Commercial Building Permit (Tenant Improvements Included — Filed Under the General Building Permit) in Fredonia, Arizona

The Town of Fredonia does not maintain a distinct commercial-building-permit application, checklist, or fee schedule — commercial new construction, renovation, alteration (including tenant-improvement work), and demolition are all filed on the exact same combined Building Permit Application used for every occupancy type in Town. The application's own 'Purposed Work' line lists 'Residence ( ) Commercial ( ) Storage ( ) Garage ( ) Other' as checkbox options on one form, and the Town's Geotechnical Data & Compliance Report forms likewise list 'Commercial' alongside Dwelling/Manufactured House/Industrial/Other. Commercial work is reviewed against the same 2006 IBC (and 2006 IRC where applicable) and associated 2006 IPC/NEC/IMC codes adopted by the Town (Town Code § 151.01 et seq., Ord. 15-003), using the same paper Building Permit Packet and the same 10-working-day review-and-issuance timeframe already documented in this file's residential-building-permit entry. This was re-confirmed by directly re-fetching the Town's Forms & Documents page and the current Building Permit Packet PDF on 2026-07-29; no separate tenant-improvement product, application, or fee line was found anywhere on the Town's site.

Verified 2026-07-29 · Source

When you need this permit

  • Building permit required for any commercial construction, alteration, tenant-improvement, or demolition work within Fredonia town limits; no building or structure regulated by Town Code and the adopted building codes may be erected, altered, or demolished without a permit obtained from the Building Official
  • Filed on the same combined Building Permit Application used for residential, storage, garage, and 'other' occupancy types — the application's 'Purposed Work' line checkboxes Residence/Commercial/Storage/Garage/Other on one form; there is no separate commercial-only application
  • Plans reviewed against the 2006 IBC (and 2006 IRC where applicable) as adopted by the Town of Fredonia (Town Code § 151.01, Ord. 15-003), plus the Town's adopted 2006 IPC/NEC/IMC for the plumbing/electrical/mechanical scope of the project
  • Soils test and compaction test performed by a qualified engineer is explicitly called out for 'any new commercial, residential and anything attached to them' per the Building Permit Packet's own permit-issuance criteria — though the Town notes not every project requires it and invites applicants to call with questions
  • Completed Building Permit Application listing owner, architect/engineer, general contractor, and electrical/plumbing/mechanical contractor names, addresses, phone numbers, and license numbers
  • Site/Plot Plan (2 copies) and Construction Drawings (2 copies), with the same required content as any other building permit: footings, foundation with structural detail, floor plans, insulation values, roof details, electrical/plumbing/mechanical/gas plans, shear walls with tie-downs, and porch/stair details
  • Res and/or Com Check energy-compliance report (2 copies) — the Town's own requirement checklist explicitly covers 'Res and/or Com,' i.e., the same energy-code compliance report requirement applies to commercial buildings, using the free program at www.energycodes.gov
  • Water system approved by ADEQ, proof of legal access meeting Town Standard Specifications, and proof of ownership (recorded deed or contract) required before permit issuance, the same as for any other building permit
  • Property must conform to the Town's Zoning Ordinance in addition to Chapter 151 before a permit will be issued (Town Code §§ 151.02, 152.090)
  • No separate tenant-improvement (TI) permit, application, checklist, or fee line was found published anywhere by the Town after re-checking the Forms & Documents page and the current Building Permit Packet — TI work is filed as an 'Alteration' or 'Repair' on the same general Building Permit Application

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review FeeTown of Fredonia Building Permit Packet, p.1: 'a non refundable plan review fee must be paid; the amount paid will be applied toward the total permit price.' No itemized fee schedule or valuation table specific to commercial projects (or any project type) was found published by the Town despite the packet cover letter referencing one — re-confirmed a confirmed gap after directly re-fetching the current Building Permit Packet and the Town's Forms & Documents page on 2026-07-29 (no separate fee-schedule document is listed there). Contact the Town Office (928-643-7241) for the current amount.
Non-refundable fee due at submittal (exact amount not published)
Permit Extension (before expiration)Town of Fredonia Building Permit Packet, p.8 — requested in writing with justifiable cause demonstrated, before the 180-day permit expires. Same fee applies regardless of occupancy type.
$15
Permit Renewal (after expiration, within 30 days)Town of Fredonia Building Permit Packet, p.8 — required if the original 180-day permit is allowed to lapse; new work must also comply with any Town Code/building-code changes adopted since original issuance.
$100

Review timeline

Plan reviewFredonia’s published plan-review target
10–10 business days

How long did your Commercial Building Permit (Tenant Improvements Included — Filed Under the General Building Permit) permit actually take in Fredonia?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing & Set Back

    Footing reinforcement inspected before concrete pour; property setbacks verified against zoning requirements at this inspection

  2. 2

    Foundation

    Foundation wall reinforcement inspected before concrete pour; damp-proof coating checked at a later inspection

  3. 3

    Underground Plumbing

    Inspected before it is covered and the floor is poured

  4. 4

    Shear Wall & Sheeting

    Inspected before being covered by house wrap or other material

  5. 5

    4-Way (Framing, Rough Plumbing, Rough Electrical, Rough Mechanical, Rough Gas)

    Combined rough-in inspection of framing and all rough trade work

  6. 6

    Insulation

    Inspected before being covered by sheetrock or other material

  7. 7

    Drywall/Wallboard

    Rough drywall inspected before taping and applying drywall mud

  8. 8

    Final Inspection

    Required before a Certificate of Occupancy (or temporary occupancy permit) is granted; no building may be occupied before this passes

See the full Fredonia inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'commercial building permit' or 'tenant improvement permit' product in Fredonia — commercial new construction, renovation, and TI work all use the exact same combined Building Permit Application, checklist, and $15/$100 extension-renewal fee structure documented in this file's residential-building-permit entry; the only project-specific difference is checking 'Commercial' instead of 'Residence' on the application's Purposed Work line.
  • The Geotechnical Data & Compliance Report forms explicitly include a 'Commercial' checkbox alongside Dwelling/Manufactured House/Industrial/Other, and the packet's own criteria list singles out 'any new commercial, residential and anything attached to them' as requiring a soils/compaction test — budget for this on any new commercial building.
  • As with every other permit type in this file, no itemized fee schedule or valuation table was found published despite the packet's cover letter referencing one — re-confirmed after re-fetching the current packet and Forms & Documents page on 2026-07-29; call the Town Office (928-643-7241) for a project-specific quote.
  • If your commercial project involves a new business, a change of tenant, or a change of use, see this file's certificate-of-occupancy-permit entry for the separate Business License track (flat $50 commercial fee) that runs alongside — not instead of — this Building Permit.
  • Fredonia's adopted 2006 IBC/IPC/NEC/IMC codes are over a decade behind the 2018-2024 cycles used by larger nearby Coconino County jurisdictions — confirm code-cycle-specific commercial provisions (e.g., accessibility, energy) with the Town Office before finalizing commercial plans.

Frequently asked questions

Fredonia requires a commercial building permit (tenant improvements included — filed under the general building permit) for: Building permit required for any commercial construction, alteration, tenant-improvement, or demolition work within Fredonia town limits; no building or structure regulated by Town Code and the adopted building codes may be erected, altered, or demolished without a permit obtained from the Building Official; Filed on the same combined Building Permit Application used for residential, storage, garage, and 'other' occupancy types — the application's 'Purposed Work' line checkboxes Residence/Commercial/Storage/Garage/Other on one form; there is no separate commercial-only application; Plans reviewed against the 2006 IBC (and 2006 IRC where applicable) as adopted by the Town of Fredonia (Town Code § 151.01, Ord. 15-003), plus the Town's adopted 2006 IPC/NEC/IMC for the plumbing/electrical/mechanical scope of the project; Soils test and compaction test performed by a qualified engineer is explicitly called out for 'any new commercial, residential and anything attached to them' per the Building Permit Packet's own permit-issuance criteria — though the Town notes not every project requires it and invites applicants to call with questions; Completed Building Permit Application listing owner, architect/engineer, general contractor, and electrical/plumbing/mechanical contractor names, addresses, phone numbers, and license numbers; Site/Plot Plan (2 copies) and Construction Drawings (2 copies), with the same required content as any other building permit: footings, foundation with structural detail, floor plans, insulation values, roof details, electrical/plumbing/mechanical/gas plans, shear walls with tie-downs, and porch/stair details; Res and/or Com Check energy-compliance report (2 copies) — the Town's own requirement checklist explicitly covers 'Res and/or Com,' i.e., the same energy-code compliance report requirement applies to commercial buildings, using the free program at www.energycodes.gov; Water system approved by ADEQ, proof of legal access meeting Town Standard Specifications, and proof of ownership (recorded deed or contract) required before permit issuance, the same as for any other building permit; Property must conform to the Town's Zoning Ordinance in addition to Chapter 151 before a permit will be issued (Town Code §§ 151.02, 152.090); No separate tenant-improvement (TI) permit, application, checklist, or fee line was found published anywhere by the Town after re-checking the Forms & Documents page and the current Building Permit Packet — TI work is filed as an 'Alteration' or 'Repair' on the same general Building Permit Application. If your project isn't listed, confirm with Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 928-643-7241 before starting work.

In Fredonia, the published Plan Review Fee is: Non-refundable fee due at submittal (exact amount not published). Additional published fees: Permit Extension (before expiration) — $15; Permit Renewal (after expiration, within 30 days) — $100. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's Building Permit Packet directly states a 10-working-day review-and-issuance timeframe after a completed application is received — the same figure that applies to residential and every other permit type processed through the same packet.

You'll need: Town of Fredonia Building Permit Application; Site/Plot Plan (2 copies); Construction Drawings (2 copies); Res and/or Com Check (2 copies). Depending on your project, Fredonia may also ask for: Geotechnical Data & Compliance Report (Backfill and Final Grade; and Prior to Footing and Foundation); Septic Permit. See the required-documents checklist on this page for details on each.

Fredonia requires 8 inspection(s) for a commercial building permit (tenant improvements included — filed under the general building permit), in order: Footing & Set Back, Foundation, Underground Plumbing, Shear Wall & Sheeting, 4-Way (Framing, Rough Plumbing, Rough Electrical, Rough Mechanical, Rough Gas), Insulation, Drywall/Wallboard, Final Inspection. Schedule each through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) (928-643-7241).

Apply through Town of Fredonia Building Department (Office of the Town Clerk — Building Inspector duties vested in the Clerk's office per Town Code) at 25 N Main St. / PO Box 217, Fredonia, AZ 86022. Phone: 928-643-7241, email: townclerk@fredonia.net. Office hours: Monday - Thursday, 7:30 A.M. to 5:30 P.M. (Fax: 928-643-7627). Applications are submitted in person or by mail using the Town's paper Building Permit Packet (permit application, requirement checklist, soils test forms, owner/builder agreement, fee schedule and general information). Per Town Code § 151.06, the Building Inspector's administrative authority for all building, plumbing, electrical, and other inspections is vested in the Office of the Town Clerk; the Council may authorize additional persons to perform inspection work or other functions required by the chapter.. Official information: https://www.fredoniaaz.gov/forms-documents.

No. Commercial new construction, alteration, and demolition are filed on the same combined Building Permit Application used for residential, storage, and garage projects — the application's 'Purposed Work' line simply checkboxes 'Commercial' instead of 'Residence.' The same 2006 IBC/IPC/NEC/IMC codes, checklist, and 10-working-day review timeframe apply.

No. Fredonia has no standalone tenant-improvement permit, application, or fee line — TI work is filed as an 'Alteration' or 'Repair' on the same general Building Permit Application used for all other building-permit work.

Sources & verification

Verified against official sources. Last reviewed 2026-07-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fredonia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Fredonia.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.