Scottsdale building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Scottsdale, Arizona.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 7447 E. Indian School Road, Suite #105, Scottsdale, AZ 85251
- Phone
- 480-312-2500
- Office hours
- Mon 8 a.m.–5 p.m.; Tue 8 a.m.–5 p.m.; Wed 9 a.m.–5 p.m.; Thu 8 a.m.–5 p.m.; Fri 8 a.m.–5 p.m. (no new transactions after 4 p.m.); Sat–Sun Closed
- Website
- Official site
Published scheduling rules
- Inspections are scheduled through the Scottsdale SPUR portal (projects after Jan. 6, 2026) or the legacy eServices portal (older projects). (Residential Building Permit (New Single-Family / Addition / Remodel))
Inspection sequence
Applies to: Residential Building Permit (New Single-Family / Addition / Remodel)
- 1
Foundation inspection
When the excavation for footings is completed, with steel reinforcement in place, but before any concrete is placed.
- 2
Under-slab or under-floor inspection
When under-slab or under-floor plumbing, mechanical and/or electrical is installed, including the subfloor.
- 3
Masonry inspection
When required reinforcing steel is in place, but before grouting.
- 4
Roof deck — strap & shear wall
When all roof sheathing is nailed, straps and tie-downs are in place.
- 5
Framing inspection
When all walls, fire blocking, draft stops and fireplaces are completed and all electrical, plumbing and mechanical work are roughed in, but before any of this work is covered.
- 6
Insulation inspection
When insulation is in place, prior to installation of gypsum board.
- 7
Lath or gypsum board inspection
When all lath is in place, but before any plastering is applied.
- 8
Final inspection
When the building or construction is complete and all electrical, plumbing and mechanical fixtures are in place but before the structure is occupied. A Certificate of Occupancy is issued when all required inspections pass with no code violations.
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation inspection
Footings completed with steel reinforcement in place before concrete is placed.
- 2
Framing inspection
All walls, fire blocking, electrical, plumbing and mechanical rough-in completed before work is covered.
- 3
Final inspection / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued when all inspections pass.
Applies to: Commercial / Multi-Family Building Permit
- 1
Foundation inspection
When excavation for footings is complete with reinforcement in place, before concrete is placed.
- 2
Framing / rough trades
Walls, fire blocking, and all rough electrical, plumbing and mechanical inspected before work is covered.
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued when all inspections pass.
Applies to: Fire Sprinkler & Fire Alarm Permit
- 1
Rough inspection
Sprinkler piping and fire alarm wiring may not be concealed until after the rough inspection has passed (City of Scottsdale Five or Less Fire Sprinkler Declaration item 7; Five or Less Fire Alarm Declaration item 6).
- 2
Fire inspection — code 036
Performed by Fire Inspections on commercial, multi-family and single-family residential structures to assure compliance with the Fire Code, city-approved fire plans and the amending ordinance; on single-family homes an approved tag is left in the electric panel after the fire inspection is approved. Required, with the 013 off-site and 032 on-site inspections, before a Temporary Certificate of Occupancy can be requested. Schedule through Scottsdale Fire Department, 480-312-1855.
- 3
Backflow preventer inspection — code 037
Required on commercial or multi-family projects; two inspections are required — first to check size, type and location against city-approved plans and the installation against the city-approved detail, second to check testing and certification by an approved testing agency — both before issuance of either a Temporary or Final Certificate of Occupancy.
Applies to: Change of Use / Change of Occupant Permit
- 1
Certificate of Occupancy inspection
A Certificate of Occupancy is issued when all required inspections have been performed and no violations of the codes and ordinances enforced by the City of Scottsdale are found. Where no construction is involved, the Miscellaneous fee schedule prices a 'Certificate of Occupancy (visual inspection only)' at $195, indicating a visual-inspection-only path.
- 2
Temporary Certificate of Occupancy sequence (013 / 032 / 036 / 037, then 025)
Where occupancy is needed before the entire work is complete: 013 TCO Off-Site (Public Works), 032 TCO On-Site (Building Inspections, 480-312-5750), 036 TCO Fire (Scottsdale Fire Department, 480-312-1855) and, on commercial or multi-family, 037 Backflow Preventer must all be approved before the 025 Temporary Certificate of Occupancy inspection can be scheduled.
Applies to: Mechanical / HVAC Permit
- 1
Framing inspection (rough mechanical)
All mechanical rough-in work must be inspected before it is covered — inspected at the framing/rough-in stage for projects with full plan review.
- 2
Final inspection
When HVAC equipment and all mechanical fixtures are in place.
Applies to: Plumbing Permit
- 1
Under-slab or under-floor inspection (if applicable)
When under-slab or under-floor plumbing is installed, including the subfloor — required before concrete or flooring covers the work.
- 2
Final inspection
When plumbing work is complete and all fixtures are in place.
Applies to: Swimming Pool / Spa Permit
- 1
Under-slab / structural
Pool shell, bonding/grounding, and plumbing inspected before deck per the 2021 ISPSC.
- 2
Final inspection / Certificate of Occupancy
Final inspection when all work is complete and pool is ready for occupancy. A Certificate of Occupancy is issued when all required inspections pass.
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Scottsdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Scottsdale building permits
Get alerts for Scottsdale
We'll email you when Scottsdale's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.