Residential Building Permit (New Single-Family / Addition / Remodel) in Scottsdale, Arizona
A building permit is required for all construction work in Scottsdale including new single-family custom homes, additions, patio covers, carport enclosures, walls and fences, retaining walls, and accessory buildings greater than 200 sq. ft. Smaller residential remodels and additions under 500 sq. ft. (single story, no second-floor additions) may qualify for a Small Scope Review (SSR). All permit applications are submitted through the Scottsdale SPUR planning and permitting portal. Fees are square-footage-based, not valuation-based.
Verified 2026-07-16 · Source
When you need this permit
- Submit all permit applications through the Scottsdale SPUR portal (cityofscottsdaleaz-energovweb.tylerhost.net/apps/selfservice); create a SPUR account before applying
- Plans must comply with the 2021 International Residential Code (IRC) with Scottsdale amendments (effective January 7, 2023) and the 2021 IECC energy code
- Use the 2021 IRC Building Code Plan Review Checklist (PDF published at scottsdaleaz.gov/codes-and-ordinances/building-codes) when preparing residential plans
- Small Scope Reviews (remodels/additions under 500 sq. ft., covered patio additions, carport enclosures, garage conversions, non-habitable accessory buildings under 1,000 sq. ft., and solar compliant with placement guidelines) may be submitted as SSR in SPUR
- Projects in FEMA (A) flood zones or Environmentally Sensitive Lands (ESL) zoning do not qualify for Small Scope Review and must be submitted for full plan review
- Detached non-habitable structures smaller than 200 sq. ft. in floor area do not require a permit but a site plan is required for a courtesy plan review
- Work completed without a permit is fined double the permit fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Foundation inspection
When the excavation for footings is completed, with steel reinforcement in place, but before any concrete is placed.
- 2
Under-slab or under-floor inspection
When under-slab or under-floor plumbing, mechanical and/or electrical is installed, including the subfloor.
- 3
Masonry inspection
When required reinforcing steel is in place, but before grouting.
- 4
Roof deck — strap & shear wall
When all roof sheathing is nailed, straps and tie-downs are in place.
- 5
Framing inspection
When all walls, fire blocking, draft stops and fireplaces are completed and all electrical, plumbing and mechanical work are roughed in, but before any of this work is covered.
- 6
Insulation inspection
When insulation is in place, prior to installation of gypsum board.
- 7
Lath or gypsum board inspection
When all lath is in place, but before any plastering is applied.
- 8
Final inspection
When the building or construction is complete and all electrical, plumbing and mechanical fixtures are in place but before the structure is occupied. A Certificate of Occupancy is issued when all required inspections pass with no code violations.
See the full Scottsdale inspection guide — scheduling & re-inspection fees →
Tips
- Scottsdale adopted the 2021 I-Codes effective January 1, 2023 (IRC effective January 7, 2023) — ensure your plans are designed to the 2021 editions.
- Small Scope Reviews (remodels/additions under 500 sq. ft., single story only) can be submitted online through SPUR with faster turnaround than full plan review.
- Work done without a permit is fined double the permit fee.
- Scottsdale's permit fees are square-footage-based, not valuation-based — the fee is calculated on livable (A/C) and covered (non-A/C) square footage, not project cost.
- Inspections are scheduled through the Scottsdale SPUR portal (projects after Jan. 6, 2026) or the legacy eServices portal (older projects).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Scottsdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Scottsdale
Residential Building Permit (New Single-Family / Addition / Remodel) in other cities
Compare residential building permit (new single-family / addition / remodel) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Scottsdale project checklist
Describe your project once and get every permit, document, and fee it triggers in Scottsdale — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →