Residential Building Permit (New Single-Family / Addition / Remodel) in Scottsdale, Arizona

A building permit is required for all construction work in Scottsdale including new single-family custom homes, additions, patio covers, carport enclosures, walls and fences, retaining walls, and accessory buildings greater than 200 sq. ft. Smaller residential remodels and additions under 500 sq. ft. (single story, no second-floor additions) may qualify for a Small Scope Review (SSR). All permit applications are submitted through the Scottsdale SPUR planning and permitting portal. Fees are square-footage-based, not valuation-based.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Single Family Custom (new home) — permit fee$237 base fee + $0.94/sq. ft. (livable area with A/C) + $0.54/sq. ft. (covered area non-A/C) + $195 Certificate of Occupancy + $379 GIS feePermit Fee Schedule – Single Family Residential, Exhibit A, Resolution No. 13661 (FY 2026/27 effective July 1, 2026; same rates as FY 2025/26 Resolution No. 13391). Source: scottsdaleaz.gov/planning-development/fees.
Single Family Addition — permit fee$237 base fee + $0.94/sq. ft. (livable area with A/C) + $0.54/sq. ft. (covered area non-A/C) + $195 Certificate of Occupancy + $379 GIS feeSingle Family Addition Less than 500 sq. ft. omits the Certificate of Occupancy and GIS fee. Source: Permit Fee Schedule – SFR, Resolution No. 13661.
Single Family Remodel — permit fee$237 base fee + $0.94/sq. ft. × 30% (livable area with A/C) + $0.54/sq. ft. (covered area non-A/C). Remodel with roof modification: $237 base + $0.94/sq. ft. × 70% (livable A/C) + $0.54/sq. ft. (covered non-A/C)Source: Permit Fee Schedule – SFR, Resolution No. 13661.
Plan review fee (Single Family Custom / Addition)$0.54/sq. ft. (livable area with A/C) + $0.34/sq. ft. (covered area non-A/C)Plan Review Fee Schedule – SFR, Resolution No. 13391 (current FY 2025/26). Note: Minimum permit projects (water heater, HVAC change-out, electrical minimum work) do not require a plan review. Source: scottsdaleaz.gov/planning-development/fees.
Re-inspection$121 per re-inspectionPermit Fee Schedule – Miscellaneous, Resolution No. 13661.

Review timeline

~520 business days

Typical estimate — confirm current times with the Scottsdale building department

Inspection process

  1. 1

    Foundation inspection

    When the excavation for footings is completed, with steel reinforcement in place, but before any concrete is placed.

  2. 2

    Under-slab or under-floor inspection

    When under-slab or under-floor plumbing, mechanical and/or electrical is installed, including the subfloor.

  3. 3

    Masonry inspection

    When required reinforcing steel is in place, but before grouting.

  4. 4

    Roof deck — strap & shear wall

    When all roof sheathing is nailed, straps and tie-downs are in place.

  5. 5

    Framing inspection

    When all walls, fire blocking, draft stops and fireplaces are completed and all electrical, plumbing and mechanical work are roughed in, but before any of this work is covered.

  6. 6

    Insulation inspection

    When insulation is in place, prior to installation of gypsum board.

  7. 7

    Lath or gypsum board inspection

    When all lath is in place, but before any plastering is applied.

  8. 8

    Final inspection

    When the building or construction is complete and all electrical, plumbing and mechanical fixtures are in place but before the structure is occupied. A Certificate of Occupancy is issued when all required inspections pass with no code violations.

Tips

Frequently asked questions

How do I apply for a residential building permit in Scottsdale?
All permit applications must be submitted through the Scottsdale SPUR planning and permitting portal. Create a SPUR account, then select 'Apply' and enter the permit type in the search field. Fees can be paid online or in person at the One Stop Shop (7447 E. Indian School Road). Source: City of Scottsdale Permit Services page, scottsdaleaz.gov.
How are residential permit fees calculated in Scottsdale?
Scottsdale uses a square-footage-based fee structure, not a valuation-based one. For a new single-family custom home: $237 base fee + $0.94/sq. ft. of livable (A/C) area + $0.54/sq. ft. of covered (non-A/C) area + $195 Certificate of Occupancy + $379 GIS fee. Source: Permit Fee Schedule – Single Family Residential, Resolution No. 13661 (effective July 1, 2026).

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Scottsdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Scottsdale

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.