A residential solar permit is required for roof-mounted solar panel installations in Scottsdale. Roof-mounted solar panels that comply with Scottsdale's placement guidelines qualify for a Small Scope Review (SSR) rather than full plan review. All permits are applied for through the Scottsdale SPUR portal. Scottsdale publishes Solar Panel Placement Guidelines for Commercial Buildings and a 2021 Residential Solar-Ready Requirements document on its building codes page.

Verified 2026-07-16 · Source

When you need this permit

  • Apply through Scottsdale SPUR portal
  • Roof-mounted solar panels complying with Scottsdale's placement guidelines qualify for Small Scope Review
  • Projects in FEMA (A) flood zones or ESL zoning do not qualify for Small Scope Review
  • Scottsdale publishes residential solar-ready requirements; all PV installations must comply with the 2020 NEC with Scottsdale amendments and the 2021 IRC

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Solar Residential permit feePermit Fee Schedule – Miscellaneous, Resolution No. 13661 (FY 2026/27, effective July 1, 2026). Source: scottsdaleaz.gov/planning-development/fees.
$168
Solar Water HeatersPermit Fee Schedule – Miscellaneous, Resolution No. 13661. Separate line from Solar Residential (PV).
$90

Review timeline

Plan reviewTypical estimate — confirm current times with the Scottsdale building department
~1–10 business days

How long did your Residential Solar PV Permit permit actually take in Scottsdale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final inspection

    Verify installation complies with the 2020 NEC with Scottsdale amendments and approved plans/placement guidelines.

See the full Scottsdale inspection guide — scheduling & re-inspection fees →

Tips

  • Roof-mounted solar that complies with Scottsdale's placement guidelines qualifies for Small Scope Review — faster turnaround than full plan review.
  • Solar residential permit fee is a flat $168 (FY 2026/27); solar water heaters are $90.
  • Scottsdale publishes solar placement guidelines for both residential and commercial; review the guidelines before designing the installation.

Frequently asked questions

Scottsdale requires a residential solar pv permit for: Apply through Scottsdale SPUR portal; Roof-mounted solar panels complying with Scottsdale's placement guidelines qualify for Small Scope Review; Projects in FEMA (A) flood zones or ESL zoning do not qualify for Small Scope Review; Scottsdale publishes residential solar-ready requirements; all PV installations must comply with the 2020 NEC with Scottsdale amendments and the 2021 IRC. If your project isn't listed, confirm with City of Scottsdale Planning and Development Services at 480-312-2500 before starting work.

In Scottsdale, the published Solar Residential permit fee is: $168. Additional published fees: Solar Water Heaters — $90. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a residential solar pv permit in Scottsdale typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with City of Scottsdale Planning and Development Services at 480-312-2500.

You'll need: Application for Single Family Residential (solar scope). Depending on your project, Scottsdale may also ask for: 2021 Residential Solar-Ready Requirements (PDF). See the required-documents checklist on this page for details on each.

Scottsdale requires 1 inspection(s) for a residential solar pv permit, in order: Final inspection. Schedule each through City of Scottsdale Planning and Development Services (480-312-2500).

Apply through City of Scottsdale Planning and Development Services at 7447 E. Indian School Road, Suite #105, Scottsdale, AZ 85251. Phone: 480-312-2500, email: OneStopShopStaff@ScottsdaleAZ.gov. Office hours: Mon 8 a.m.–5 p.m.; Tue 8 a.m.–5 p.m.; Wed 9 a.m.–5 p.m.; Thu 8 a.m.–5 p.m.; Fri 8 a.m.–5 p.m. (no new transactions after 4 p.m.); Sat–Sun Closed. Official information: https://www.scottsdaleaz.gov/planning-development.

Scottsdale, Arizona has adopted: 2021 International Building Code (IBC) with Scottsdale amendments — effective January 1, 2023 (per City Council adoption); 2021 International Residential Code (IRC) with Scottsdale amendments — effective January 7, 2023; 2021 International Mechanical Code (IMC) with Scottsdale amendments — effective January 1, 2023; 2021 International Fuel Gas Code (IFGC) with Scottsdale amendments — effective January 1, 2023; 2021 International Plumbing Code (IPC) with Scottsdale amendments — effective January 1, 2023; 2021 International Fire Code (IFC) with Scottsdale amendments — effective January 1, 2023; 2021 International Existing Building Code (IEBC) with Scottsdale amendments — effective January 1, 2023; 2021 International Swimming Pool and Spa Code (ISPSC) with Scottsdale amendments — effective January 1, 2023; 2021 International Energy Conservation Code (IECC) with Scottsdale amendments — effective January 7, 2023; 2021 International Green Construction Code (IgCC) with Scottsdale amendments — effective July 1, 2023 (mandatory); 2020 National Electrical Code (NEC) with Scottsdale amendments — effective January 1, 2023. Local amendments apply — see the Scottsdale overview page for the full list.

Apply through the Scottsdale SPUR portal. Roof-mounted solar that complies with Scottsdale's placement guidelines qualifies for a Small Scope Review. The permit fee is a flat $168. Source: City of Scottsdale Permit Services page and Permit Fee Schedule – Miscellaneous, Resolution No. 13661.

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Scottsdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.