EV Charger / EVSE Permit (Electrical Minimum Permit) in Scottsdale, Arizona

Scottsdale has no dedicated EV charger/EVSE retrofit-permit fee line — confirmed on the City's Permit Services page, which lists explicit Minimum Permit examples (service upgrade/change out, panel relocation, temporary power pole, etc.) but does not name an EV charger circuit. An EV charging station (Level 2, up to 400 AMP service classification) installed on an existing single-family residence qualifies as an Electrical Minimum Permit — no plan review required, applied for online through Scottsdale SPUR — the same no-plan-review classification this file's electrical-permit entry documents for a service upgrade or change-out. Separately, Scottsdale has adopted 2021 IGCC EV-charging-infrastructure design requirements (branch-circuit capacity and accessible-space minimums) that apply to NEW commercial/multifamily construction, not to a homeowner's retrofit EV charger installation.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical work must comply with the 2020 National Electrical Code (NEC) with Scottsdale amendments (effective January 1, 2023)
  • Submit permit application through Scottsdale SPUR portal
  • A dedicated EV charger circuit on an existing single-family residence qualifies as a Minimum Permit (no plan review required) provided any associated service upgrade/change-out does not exceed 400 AMP, consistent with the general Minimum Permit electrical classification documented in this file's electrical-permit entry
  • New commercial or multifamily construction is separately subject to Scottsdale's adopted 2021 IGCC EV-charging-infrastructure requirements (e.g., a minimum branch-circuit capacity of 8.3 kVA / 40A at 208/240V per charging space, and a minimum percentage of EV-capable/accessible spaces) — this is a design/build standard enforced at building-permit plan review for new projects, not a separate retrofit permit fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Minimum Permit (single discipline — electrical)Permit Fee Schedule – Miscellaneous, Resolution No. 13661 (FY 2026/27, effective July 1, 2026) — same fee and no-plan-review classification documented in this file's electrical-permit entry; applies to an EV charger circuit since no dedicated EV-charger fee line exists. Source: scottsdaleaz.gov/planning-development/fees.
$121
Minimum Combination Permit (all disciplines — electrical, mechanical, plumbing)Applicable if the EV charger installation is combined with other trade work on the same permit
$379

Review timeline

Plan reviewTypical estimate — confirm current times with the Scottsdale building department
~1–5 business days

How long did your EV Charger / EVSE Permit (Electrical Minimum Permit) permit actually take in Scottsdale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final inspection

    When the EV charger's electrical work is complete and the unit is mounted, per the 2020 NEC with Scottsdale amendments

See the full Scottsdale inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated EV-charger fee line in Scottsdale — a Level 2 EV charger circuit on an existing single-family home qualifies as an Electrical Minimum Permit ($121), the same no-plan-review classification used for a service upgrade or panel relocation.
  • Scottsdale's 2021 IGCC EV-charging-infrastructure requirements (branch-circuit capacity and accessible-space minimums) apply to NEW commercial/multifamily construction at building-permit plan review, not to a homeowner installing a charger at an existing house — don't confuse the two.
  • If the EV charger requires a service upgrade above 400 AMP, it would no longer qualify as a Minimum Permit and would instead require full plan review — confirm the anticipated service size with your electrician before applying.

Frequently asked questions

Scottsdale requires an ev charger / evse permit (electrical minimum permit) for: Electrical work must comply with the 2020 National Electrical Code (NEC) with Scottsdale amendments (effective January 1, 2023); Submit permit application through Scottsdale SPUR portal; A dedicated EV charger circuit on an existing single-family residence qualifies as a Minimum Permit (no plan review required) provided any associated service upgrade/change-out does not exceed 400 AMP, consistent with the general Minimum Permit electrical classification documented in this file's electrical-permit entry; New commercial or multifamily construction is separately subject to Scottsdale's adopted 2021 IGCC EV-charging-infrastructure requirements (e.g., a minimum branch-circuit capacity of 8.3 kVA / 40A at 208/240V per charging space, and a minimum percentage of EV-capable/accessible spaces) — this is a design/build standard enforced at building-permit plan review for new projects, not a separate retrofit permit fee. If your project isn't listed, confirm with City of Scottsdale Planning and Development Services at 480-312-2500 before starting work.

In Scottsdale, the published Minimum Permit (single discipline — electrical) is: $121. Additional published fees: Minimum Combination Permit (all disciplines — electrical, mechanical, plumbing) — $379. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for an ev charger / evse permit (electrical minimum permit) in Scottsdale typically runs 1–5 business days. This is an estimate, not a published figure — confirm current review times with City of Scottsdale Planning and Development Services at 480-312-2500.

You'll need: Application for Single Family Residential (electrical scope). See the required-documents checklist on this page for details on each.

Scottsdale requires 1 inspection(s) for an ev charger / evse permit (electrical minimum permit), in order: Final inspection. Schedule each through City of Scottsdale Planning and Development Services (480-312-2500).

Apply through City of Scottsdale Planning and Development Services at 7447 E. Indian School Road, Suite #105, Scottsdale, AZ 85251. Phone: 480-312-2500, email: OneStopShopStaff@ScottsdaleAZ.gov. Office hours: Mon 8 a.m.–5 p.m.; Tue 8 a.m.–5 p.m.; Wed 9 a.m.–5 p.m.; Thu 8 a.m.–5 p.m.; Fri 8 a.m.–5 p.m. (no new transactions after 4 p.m.); Sat–Sun Closed. Official information: https://www.scottsdaleaz.gov/planning-development.

No. The City's Permit Services page lists no EV-charger-specific permit type or fee. A Level 2 EV charger circuit on an existing single-family residence is processed as an Electrical Minimum Permit ($121), the same no-plan-review category used for a service upgrade or panel relocation.

Yes, for new commercial and multifamily construction — Scottsdale has adopted 2021 IGCC EV-charging-infrastructure provisions requiring minimum branch-circuit capacity (8.3 kVA / 40A at 208/240V per space) and a minimum percentage of accessible EV charging spaces. This is a new-construction design standard reviewed as part of the building permit, not a separate retrofit permit for homeowners installing a charger at an existing property.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Scottsdale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.