Inspection sequence, scheduling, and re-inspection fees for building permits in Wickenburg, Arizona.

Reviewed 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
155 N. Tegner Street, Suite C, Wickenburg, AZ 85390
Phone
928-684-5451 ext. 1512
Office hours
Monday - Thursday, 7 a.m. - 6 p.m. (closed Fridays; Town Hall operates a 4/10 workweek). All submittals are digital only via the iworq online portal (portal.iworq.net/WICKENBURG/new-request/700/2581) — the Town explicitly does not accept paper plans. Permit questions: 928-668-0575. Inspection scheduling (online only, same business hours): 928-668-0513. Community Development Director Steve Boyle: 928-668-0512, sboyle@wickenburgaz.gov.

Published scheduling rules

  • Town Hall (and by extension Building Safety) works a 4-day, 10-hour week: Monday-Thursday 7am-6pm, closed Fridays — factor this into any time-sensitive submittal or inspection scheduling. (Residential Building Permit (New Construction))
  • All submittals are digital-only through the Town's iworq online portal (portal.iworq.net/WICKENBURG/new-request/700/2581); the Town does not accept paper plans, and all inspections are scheduled online (Fire Sprinkler / Fire Alarm Permit)

Inspection sequence

Applies to: Commercial Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Footings, reinforcing steel, and foundation elements per the approved foundation plan and 2018 IBC, before concrete pour

  2. 2

    Rough Trades (Electrical/Plumbing/Mechanical) and Framing

    Structural framing and rough electrical (2017 NEC), plumbing (2018 IPC), mechanical (2018 IMC), and fuel-gas (2018 IFGC) work before cover; no commercial-specific published inspection checklist was found — sequence follows the Town's adopted 2018 code suite, confirm milestones with the Building Safety Division

  3. 3

    Final / Occupancy

    All work complete per approved plans; per Zoning Ordinance Section 14-25-9.A.3, the entire project as defined by the approved Development Review plans must be completed before an Occupancy Permit is issued. All inspections scheduled online (928-668-0513), Mon-Thu 7am-6pm

Applies to: Residential Addition / Room Addition / Garage / Deck Permit

  1. 1

    Foundation/Footing

    Required before concrete pour for additions and accessory structures with footings

  2. 2

    Framing

    Structural connections to existing structure or new framing

  3. 3

    Final

    Completed work verified against approved plans; scheduled online during business hours

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour, per IRC/IBC 2018 foundation requirements

  2. 2

    Framing

    Structural framing, connections, and egress per adopted 2018 IRC

  3. 3

    Final

    All work complete per approved plans; all inspections must be scheduled online during business hours (Mon-Thu, 7am-6pm)

Applies to: Swimming Pool / Spa / Pool Barrier Permit

  1. 1

    Pre-Plaster/Pre-Gunite

    Structural steel and plumbing verified before shotcrete/gunite application, for in-ground pools

  2. 2

    Barrier/Fence Final

    Verifies compliance with IRC Appendix G AG105 (height, opening spacing, self-closing/self-latching gates) before pool is filled/used

  3. 3

    Final

    Complete pool/spa system and barrier verified; scheduled online during business hours

Applies to: Change of Use / Certificate of Occupancy Permit

  1. 1

    Alteration Inspections (if construction is performed)

    Rough-in and final inspections on any building, plumbing, mechanical, electrical, or fire-protection work done to serve the new occupancy; scheduled online during business hours (Mon-Thu, 7am-6pm)

  2. 2

    Certificate of Occupancy

    The building official's issuance of the certificate of occupancy, without which the building may not be used or occupied and the occupancy classification may not be changed (IBC § 111.1 as adopted)

Applies to: Commercial Tenant Improvement / Remodel Permit (filed as 'Commercial Remodel/Addition')

  1. 1

    Rough Trades (Electrical/Plumbing/Mechanical) and Framing

    Rough electrical (2017 NEC), plumbing (2018 IPC), mechanical (2018 IMC), fuel gas (2018 IFGC), and any framing/structural alterations (2018 IEBC/IBC) before cover; no TI-specific published inspection checklist was found — confirm required milestones with the Building Safety Division when the permit is issued

  2. 2

    Final

    Completed work verified against approved plans, including ADA-compliance items; scheduled online (928-668-0513), Mon-Thu 7am-6pm

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    Devices installed and connections verified per 2017 NEC; scheduled online during business hours

Applies to: EV Charger Installation Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, where applicable

  2. 2

    Final

    Charger installed and electrical connections verified per 2017 NEC

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Rough-In / Overhead

    Sprinkler piping, hangers, heads, and alarm rough wiring verified before ceilings and walls are closed; scheduled online during business hours (Mon-Thu, 7am-6pm)

  2. 2

    Final

    Completed fire protection system verified against the approved Sprinkler Design Plan / Fire Sprinkler Plan; scheduled online

Applies to: Plumbing / Gas Line / Mechanical Permit

  1. 1

    Rough-In

    After pipes/ductwork installed, before walls closed

  2. 2

    Final

    Fixtures/equipment connected and operational, gas connections leak-tested; scheduled online during business hours

Applies to: Residential Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final

    Racking, roof penetrations, and electrical connections verified per 2017 NEC

Final inspection only: Demolition Permit, Sign Permit

Re-inspection fees

Commercial Building Permit (New Construction)Re-Inspection / Other Inspections · Same fee schedule, pages 2-3 ('Other Inspections and Fees / Re-Inspection Fees / Inspections outside of normal business hours').
$80.00 per hour (or total hourly cost to the jurisdiction, whichever is greater); inspections outside normal business hours carry a two-hour minimum

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wickenburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Wickenburg building permits

Get alerts for Wickenburg

We'll email you when Wickenburg's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.