Change of Use / Certificate of Occupancy Permit in Wickenburg, Arizona
In Wickenburg a change of use turns on the Certificate of Occupancy. Town Code Chapter 8 adopts the International Building Code with Section 111 amended, and IBC § 111.1 as adopted reads: 'A building or structure shall not be used or occupied, and a change of the occupancy classification of a building or structure or portion thereof shall not be made, until the building official has issued a certificate of occupancy therefore as provided herein.' The Town Code separately adopts the 2018 International Existing Building Code, which under IBC § 101.4.7 as amended governs 'the repair, alteration, change of occupancy, addition to and relocation of existing buildings.' The Certificate of Occupancy itself is obtained at Town Hall through the Community Development Department. Running alongside the building-code track is the zoning track: the Town's adopted fee schedule carries dedicated Comm. Dvlp./Planning line items for Zoning Verification, Administrative Use Permit, Temporary Use Permit, and Conditional Use Permit, which is how a proposed new use is cleared against Chapter 14 before it can occupy.
Reviewed 2026-07-23 · Source
When you need this permit
- IBC § 111.1 as adopted by Town Code Chapter 8: a building or structure shall not be used or occupied, and a change of the occupancy classification of a building or structure or portion thereof shall not be made, until the building official has issued a certificate of occupancy; issuance of a certificate of occupancy is not an approval of a violation of the code or other Town ordinances
- The 2018 International Existing Building Code is adopted and, per IBC § 101.4.7 as amended, governs the repair, alteration, change of occupancy, addition to and relocation of existing buildings
- Certificate of Occupancy intake: per the Town's Permits page, 'The Certificate of Occupancy can be obtained at Town Hall through the Community Development Department located at 155 North Tegner Street or by emailing kbruce@wickenburgaz.gov'
- Information the applicant must provide for the Certificate of Occupancy (Permits page): use classification; type of construction; zoning; contact information for the owner of the building; mailing address for the owner; legal description; building address; building location; and building value
- Zoning clearance track: confirm the proposed use against Town Code Chapter 14 (Zoning). The Town's adopted fee schedule carries distinct Comm. Dvlp./Planning line items for Zoning Verification, Administrative Use Permit, Temporary Use Permit, Conditional Use Permit, and Amended Conditional Use Permit — the mechanism by which a use that is not permitted outright is cleared
- Any construction work performed to effect the change of use (alterations, added or relocated plumbing/mechanical/electrical, fire-protection system changes) requires its own permit under Town Code § 8-1-6 and is submitted digitally through the iworq portal; the Town does not accept paper plans
- A double permit fee penalty applies if work is determined to have begun without a required permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Alteration Inspections (if construction is performed)
Rough-in and final inspections on any building, plumbing, mechanical, electrical, or fire-protection work done to serve the new occupancy; scheduled online during business hours (Mon-Thu, 7am-6pm)
- 2
Certificate of Occupancy
The building official's issuance of the certificate of occupancy, without which the building may not be used or occupied and the occupancy classification may not be changed (IBC § 111.1 as adopted)
See the full Wickenburg inspection guide — scheduling & re-inspection fees →
Tips
- The gate in Wickenburg is the Certificate of Occupancy, not a separately named 'change of use permit' — IBC § 111.1 as adopted by Town Code Chapter 8 bars both occupying the building and changing its occupancy classification until the building official issues the certificate.
- There is no downloadable C-of-O form. The Town's Permits page directs applicants to Town Hall's Community Development counter at 155 North Tegner Street or to kbruce@wickenburgaz.gov, and lists the nine items to have ready (use classification, type of construction, zoning, owner contact, owner mailing address, legal description, building address, building location, building value).
- Clear the zoning question before the building question. A $150.00 Zoning Verification is the cheapest way to confirm the proposed use is permitted; if it is not, the path runs through a $50.00 Administrative Use Permit or a $1,000.00 Conditional Use Permit, and those costs dwarf the alteration permit on a small tenant change.
- The Town adopts the 2018 International Existing Building Code specifically to govern change of occupancy in existing buildings — expect the alteration scope to be evaluated under IEBC compliance methods rather than as new construction.
- Watch the unpermitted-work penalty: '$100.00 or double the building permit fee, whichever is greater' applies if alteration work for the new use starts before the permit issues.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wickenburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Wickenburg
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Wickenburg project checklist
Describe your project once and get every permit, document, and fee it triggers in Wickenburg — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →