Pinetop-Lakeside building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Pinetop-Lakeside, Arizona.
Verified 2026-07-07 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 325 W White Mountain Boulevard, Lakeside, AZ 85929
- Phone
- 928-368-8696 ext. 2
- Office hours
- Monday - Friday, 8 a.m. - 5 p.m. Applications are submitted via the online Civic Review portal (preferred; app.civicreview.com), in person at Town Offices, or by mail to the Community Development Department. Inspections are requested by calling 928-368-8883 (a separate Inspections line from the main Building & Safety number) at least one working day in advance; requests are generally scheduled for the next working day (e.g., a Friday call-in leads to a Monday inspection). Building & Safety and Building Inspections are administered under the Community Development Department (Community Development Manager Jennifer Butterbrodt, 928-368-8696 ext. 301).
- Website
- Official site
Published scheduling rules
- Inspections are requested through a SEPARATE phone line (928-368-8883, Inspections) from the main Building & Safety Department number (928-368-8696 ext. 2) — call at least one working day ahead; a Friday call-in is typically scheduled for the following Monday. (General)
Inspection sequence
Applies to: Residential Building Permit (New Construction / Addition / Remodel), Commercial Building Permit (New Construction / Alteration / Tenant Improvement)
- 1
Foundation
After trenches are excavated and forms erected
- 2
Concrete Slab or Under-Floor
Before concrete is poured
- 3
Shear Wall and Roof Sheeting
Prior to house wrap
- 4
Frame
After roof and all framing complete
- 5
Insulation
Prior to gypsum board installation
- 6
Lath and/or Gypsum Board
Before plastering is applied
- 7
Final Inspection
After completion, ready for occupancy; project must be completed per approved plans with all electrical, plumbing, mechanical, and structural installations finished. Certificate of Occupancy issued upon Building Official certification; occupancy may not occur before issuance.
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed and protections verified per the 2023 NEC as adopted by the Town
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
EVSE circuit wiring, box placement, and panel connections before walls are closed
- 2
Final
Charger installed and protections verified per the 2023 NEC as adopted by the Town
Applies to: Fire Sprinkler and Fire Alarm System Permit
- 1
Fire Protection Underground / Hydrostatic Test (where underground fire line is in scope)
Timber Mesa Fire and Medical District: fire lines shall be visible during hydrostatic testing; center loading of the pipe is acceptable but all joints, valves, thrust blocks and fittings shall be visible. The district inspection covers the fire line supply piping from the inside or outside of the building(s) to the point of connection to the supply water main at the street or to the water main loop, and, where a remote FDC is installed, the supply piping from the building to the remote FDC.
- 2
Fire district inspections (bundled into the plan review and permit fee)
Both districts title their fee lines 'Plan Review & Inspections', bundling the inspections into the permit fee; neither district publishes a named inspection sequence, so none is asserted here. Approved plans bearing the fire district stamp must be on the job site - Timber Mesa states that no inspections or tests will be conducted without them and that this will result in a reinspection fee, and that a contractor who is not prepared must cancel at least two (2) hours before the scheduled time or a reinspection fee may apply.
Applies to: Gas Permit
- 1
Gas Line/Rough-In
Piping installation verified before concealment
- 2
Final
Gas connections and appliance installation verified, pressure test/leak check completed
Applies to: Manufactured, Mobile, or Modular Home Placement Permit
- 1
Foundation/Placement
Verifies ground-level, fully-skirted, or permanent-foundation installation method per Arizona Department of Building and Fire Safety standards
- 2
Final
HUD decal, skirting/foundation, and utility connections verified complete
Applies to: Residential Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Final electrical/building inspection preceding sign-off
Final inspection only: Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pinetop-Lakeside building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Pinetop-Lakeside building permits
Get alerts for Pinetop-Lakeside
We'll email you when Pinetop-Lakeside's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.