Inspection sequence, scheduling, and re-inspection fees for building permits in Snowflake, Arizona.

Verified 2026-07-07 · Source

How to schedule

Inspections are requested through the building department below.

Address
81 West 1st South, Snowflake, Arizona 85937
Phone
928-536-7103 ext. 232
Office hours
Town Hall business hours (928-536-7103); Building Official Scott Allen reachable at ext. 232. Inspection requests must be submitted at least 24 hours in advance by calling Town Hall, the Building Official, or by emailing the Building Official; inspections are conducted Monday through Friday, per the current Building Permit Requirements and Demolition Permit Requirements handouts.

Inspection sequence

Applies to: Residential Building Permit (New Construction, Additions, Remodels)

  1. 1

    Foundation/Footing

    Before concrete pour; verifies finished-floor elevation amendment (6 in above road crown / 12 in above gutter flow line) and design criteria compliance

  2. 2

    Framing

    Structural framing, shear wall method/locations, connections, egress per 2018 IRC and Town design criteria

  3. 3

    Rough Electrical/Mechanical/Plumbing

    Combined rough-in inspection prior to wall closure

  4. 4

    Final / Certificate of Occupancy

    All work complete per approved plans; a newly constructed building may not be occupied until final inspection passes and a Certificate of Occupancy is issued, no exceptions

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verifies all utilities disconnected, all meters removed, and construction fencing in place

  2. 2

    Underground Inspection

    Sewer lines disconnected and capped within 5 feet of the property line; all underground utilities, footings, and foundations removed and trenches remain open for inspection; no debris may remain or be buried on site

  3. 3

    Final

    All demolition debris removed; backfill and final grading/compaction complete; construction fencing removed; surrounding properties, easements, and rights-of-way checked/repaired for any damage

Applies to: Commercial Building Permit (New Construction, Additions, Tenant Improvements)

  1. 1

    Progress Inspections (24-hour advance request)

    The Town publishes no commercial-specific inspection checklist; per the Building Permit Requirements handout, all inspections must be requested at least 24 hours in advance, are conducted Monday-Friday, and work cannot continue until each inspection is completed and the Inspection Card is signed

  2. 2

    Final / Certificate of Occupancy

    A newly constructed building may not be occupied until after the final inspection and a Certificate of Occupancy is issued by the Building Official — 'no exceptions' per the Building Permit Requirements handout

Re-inspection fees

Residential Building Permit (New Construction, Additions, Remodels)Reinspection Fee · Town of Snowflake Comprehensive Fee Schedule; assessed for incomplete work, missed corrections, unavailable inspection card/plans, no access provided, or plan deviations
$75
Demolition Permit
Demolition Permit Fee · Town of Snowflake Demolition Permit Requirements handout states 'FEES AND SERVICES: See the current fee schedule'; Show full citationDemolition Permit Fee · Town of Snowflake Demolition Permit Requirements handout states 'FEES AND SERVICES: See the current fee schedule'; the published Comprehensive Fee Schedule does not itemize a demolition-specific fee distinct from Admin-Minimum Building Permit Fee ($50) and Admin-Reinspection Fee ($75)
See current fee schedule (Minimum Building Permit Fee $50 baseline applies per the Town's Comprehensive Fee Schedule; no demolition-specific fee line item was separately published)
Solar Photovoltaic (PV) PermitReinspection Fee · Town of Snowflake Comprehensive Fee Schedule
$75
EV Charger / EVSE PermitReinspection Fee · Town of Snowflake Comprehensive Fee Schedule
$75
Commercial Building Permit (New Construction, Additions, Tenant Improvements)Reinspection Fee · Comprehensive Fee Schedule; assessed for incomplete work, missed corrections, unavailable inspection card/plans, no access, or plan deviations
$75

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Snowflake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Snowflake building permits

Get alerts for Snowflake

We'll email you when Snowflake's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.