Residential Solar Permit in Sacramento, California

Sacramento runs residential solar through its own permit path with a SolarAPP route, and the application requires utility paperwork alongside the plans.

Verified 2026-09-11 · Source

When you need this permit

  • The submittal is enumerated: 'Upload the CDD Building Application for Solar Energy Systems, SMUD interconnection letter, construction plans, and equipment specifications'.
  • A planning record is issued and routed: 'A Planning Record Number (e.g., PLN##-#####) will be issued, and the submittal package will be routed for plan review'.
  • 'Upon approval, fees will be invoiced, and permit issued upon payment'.
  • Commercial solar is handled on a separate path from residential.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Solar permit feesThe City states fees are invoiced after approval and the permit issues upon payment; no figure is published on the page.
Invoiced on approval

Review timeline

Plan review
Not published — contact the department

How long did your Residential Solar Permit permit actually take in Sacramento?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Solar inspection

    Scheduled after permit issuance.

Tips

  • THE UTILITY LETTER IS PART OF THE PERMIT SUBMITTAL, not a later step - Sacramento asks for the SMUD interconnection letter up front.
  • FEES COME AFTER APPROVAL HERE. The permit is issued on payment once approved, so the cost is not known at submittal.

Frequently asked questions

The City's own list: the CDD Building Application for Solar Energy Systems, a SMUD interconnection letter, construction plans and equipment specifications. Fees are invoiced on approval and the permit issues on payment.

In Sacramento, the published Solar permit fees is: Invoiced on approval. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Sacramento does not publish a plan-review timeline for this permit. Contact City of Sacramento - Community Development Department, Building Division at 916-264-5011 for current turnaround.

You'll need: CDD Building Application for Solar Energy Systems; SMUD interconnection letter; Construction plans and equipment specifications. See the required-documents checklist on this page for details on each.

Sacramento requires 1 inspection(s) for a residential solar permit, in order: Solar inspection. Schedule each through City of Sacramento - Community Development Department, Building Division (916-264-5011).

Apply through City of Sacramento - Community Development Department, Building Division. Phone: 916-264-5011. Office hours: NOT ASSERTED. Sacramento publishes a Public Counter Information & Appointments page; no hours are stated here. The Building Division help line is 916-264-5011.. Official information: https://www.cityofsacramento.gov/community-development/building.

Sacramento, California has adopted: California Building Standards Code as applied locally. Sacramento's ADU handout names the set it works to: the 'applicable provisions of the current California Building Code (CBC), Residential (CRC), Energy' code, together with Plumbing (CPC), Mechanical (CMC), Electrical (CEC) and local ordinances. NO EDITION YEAR IS ASSERTED - the handout says 'current', and this record does not state the City's adopting ordinance.. Local amendments apply — see the Sacramento overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-09-11.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sacramento building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Sacramento's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Sacramento yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.