Inspection sequence, scheduling, and re-inspection fees for building permits in Lone Tree, Colorado.

Verified 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
9220 Kimmer Dr., Suite 100, Lone Tree, CO 80124
Phone
720-390-5211
Office hours
7:00 AM - 4:00 PM, Monday-Friday, excluding holidays/weekends. Chief Building Official: Matt Archer. Community Development Director: Kelly First (kelly.first@cityoflonetree.com, 720-509-1274). General city line: 303-708-1818.

Published scheduling rules

  • The City publishes NO numeric plan-review turnaround (days or weeks) for any standard building-permit category anywhere on its site — not on the Building Division page, the Do I Need a Building Permit page, the Roofing Guidelines page, the Building Inspection Scheduling page, the 2026 fee schedule, or the Building Permit Reports archive. Colorado is home-rule with no statewide clock, and every permitType in this file is honestly null/unverified with a documented chase trail rather than an invented figure. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour, if new footings are required

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Residential Addition / Remodel Permit (including Basement Finish)

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour, per 36-inch minimum frost depth

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour, per 36-inch minimum frost depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Deck / Patio Cover Permit

  1. 1

    Footing

    Before concrete pour, per 36-inch minimum frost depth

  2. 2

    Framing

    Deck or patio cover framing and structural connections before cover/finish

  3. 3

    Final Inspection

    Guardrails, stairs, and structural connections complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment, scoped to the TI work

  2. 2

    Final Inspection

    All work complete per approved plans; Certificate of Occupancy review as applicable

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Mid-Roof Inspection

    Required for all roof types when 20-50% of roofing is installed

  2. 2

    Final Roof Inspection

    Required for all roofing materials; no ladder needed unless flagged at mid-roof stage

Applies to: Solar Electric / Solar Thermal Device Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

Lone Tree building permits

Get alerts for Lone Tree

We'll email you when Lone Tree's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.