EV Charger / Electric Vehicle Charging Station Permit in Lone Tree, Colorado
The City of Lone Tree's 2026 Building Fees schedule has no dedicated EV-charger or EVSE line item -- unlike Solar Electric or Solar Thermal Devices, which have their own flat $480.00 line. Installing a Level 2 (240V) home EV charger requires a City of Lone Tree Electrical Permit, billed under the same valuation-based 'Building, Mechanical, Electrical and Plumbing Permit Fees for All Occupancies' table used for any electrical installation, issued directly by the City's Building Division under the 2023 NEC as adopted.
Verified 2026-07-20 · Source
When you need this permit
- Electrical work must be performed by a contractor holding current Colorado State Electrical Board (DORA) licensure, in addition to the City permit
- Billed under the single shared valuation-based 'Building, Mechanical, Electrical and Plumbing Permit Fees for All Occupancies' table -- not a separate DORA-anchored schedule, since Lone Tree issues its own combined trade permits rather than deferring to the state board
- No Douglas County Use Tax is collected on electrical-only permits/projects (explicit fee-schedule exemption); City Use Tax (2.5%) may still apply per City ordinance
- Permit valuation must include the total value of work, including materials and labor, for the EV charger installation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
New circuit, breaker sizing, and disconnect (if required by the charger manufacturer) verified by City of Lone Tree Building Division before energizing
See the full Lone Tree inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'EV charger' or 'EVSE' line item on Lone Tree's 2026 Building Fees schedule -- unlike Solar Electric/Solar Thermal Devices, which have their own flat $480 fee, an EV charger circuit is billed under the general valuation-based electrical fee table.
- A simple new circuit addition with low materials/labor valuation will typically land in the lowest $23.50 fee tier; a panel or service upgrade will push the project into a higher valuation tier.
- No Douglas County Use Tax applies to electrical-only permits, but the City's own 2.5% Use Tax may still apply -- confirm with Building Division.
- Unlike neighboring Lochbuie (which defers electrical fees to the state DORA schedule), Lone Tree issues its own combined Building/Mechanical/Electrical/Plumbing permits with a locally-published valuation-based fee table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lone Tree building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lone Tree
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Lone Tree project checklist
Describe your project once and get every permit, document, and fee it triggers in Lone Tree — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →