Solar Electric / Solar Thermal Device Permit in Lone Tree, Colorado

Required for solar photovoltaic and solar thermal device installations in Lone Tree. Billed as a flat fee under the 2026 Building Division fee schedule, distinct from the valuation-based Building/Mechanical/Electrical/Plumbing table. Douglas County Use Tax is explicitly waived on photovoltaic systems.

Verified 2026-07-06 · Source

When you need this permit

  • Billed as a flat fee, not the valuation-based Building Permit Fee table used for other trades
  • Electrical connection work governed by the 2023 NEC as adopted
  • Douglas County Use Tax not collected on photovoltaic systems
  • Roof-mounted systems on a re-roof-eligible roof are still subject to the City's roofing material and inspection requirements where applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar Electric or Solar Thermal Device Permit Fee2026 Building Division Fee Schedule — flat fee, not valuation-based
$480.00 flat
Douglas County Use Tax
Not collected on photovoltaic systems

Review timeline

Plan review
Not published — contact the department

How long did your Solar Electric / Solar Thermal Device Permit permit actually take in Lone Tree?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

See the full Lone Tree inspection guide — scheduling & re-inspection fees →

Tips

  • Solar is billed as a flat $480 fee in Lone Tree, unlike the valuation-based tables used for most other trade permits — budget accordingly regardless of system size or installed cost.
  • Confirm with the Building Division whether your specific solar installation additionally requires a structural/roofing review if it involves roof penetrations on an aging roof, since the Roofing Guidelines' material and inspection requirements can still apply.

Frequently asked questions

Lone Tree requires a solar electric / solar thermal device permit for: Billed as a flat fee, not the valuation-based Building Permit Fee table used for other trades; Electrical connection work governed by the 2023 NEC as adopted; Douglas County Use Tax not collected on photovoltaic systems; Roof-mounted systems on a re-roof-eligible roof are still subject to the City's roofing material and inspection requirements where applicable. If your project isn't listed, confirm with City of Lone Tree Community Development Department, Building Division at 720-390-5211 before starting work.

The City charges a flat $480.00 fee for a Solar Electric or Solar Thermal Device permit, per the 2026 Building Division fee schedule — this is not calculated from system valuation like most other permit types.

Lone Tree does not publish a plan-review timeline for this permit. Contact City of Lone Tree Community Development Department, Building Division at 720-390-5211 for current turnaround.

You'll need: Building Permit Application (Solar scope). See the required-documents checklist on this page for details on each.

Lone Tree requires 2 inspection(s) for a solar electric / solar thermal device permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Lone Tree Community Development Department, Building Division (720-390-5211).

Apply through City of Lone Tree Community Development Department, Building Division at 9220 Kimmer Dr., Suite 100, Lone Tree, CO 80124. Phone: 720-390-5211, email: building@cityoflonetree.com. Office hours: 7:00 AM - 4:00 PM, Monday-Friday, excluding holidays/weekends. Chief Building Official: Matt Archer. Community Development Director: Kelly First (kelly.first@cityoflonetree.com, 720-509-1274). General city line: 303-708-1818.. Official information: https://cityoflonetree.com/community-development/building/.

Lone Tree, Colorado has adopted: 2021 International Building Code (IBC), as amended — City of Lone Tree Design Criteria & Codes page; 2021 International Residential Code (IRC), as amended; 2021 International Fire Code (IFC); 2021 International Plumbing Code (IPC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC); 2023 National Electrical Code (NEC); 2017 ICC A117.1 Accessibility Code; Note on Chapter 18 (Building Regulations), Lone Tree Municipal Code: search-indexed content confirms the City has adopted the International Building Code, 2021 Edition, as amended, with a certified copy on file with the City Clerk; a local amendment adds Section 105.3.8 'Soils Test,' requiring a soils test prepared by a Colorado-registered professional engineer at building permit application, with an engineering geologist additionally required for hillside/geological-hazard/steep-slope sites at the Building Official's discretion. Full text of Chapter 18 could not be independently re-verified beyond this indexed excerpt because library.municode.com/co/lone_tree serves an Angular single-page app shell (empty of code text without JS rendering) and returned HTTP 403 to both a standard fetch and a full-browser-header curl retry — this is a partial-confidence caveat on the amendment-detail level only, not on the base code-edition list, which is independently confirmed on the City's own actively-maintained Design Criteria & Codes page.; HB22-1362 statewide energy floor (Colorado): as of 2026-07-06 (this review date), HB22-1362 requires that municipalities/counties updating their building code adopt an energy code achieving equivalent-or-better performance than the 2021 IECC + Model Electric and Solar Ready Code (effective window 7/1/2023-6/30/2026), stepping up to the Colorado Energy Code Board's Model Low Energy and Carbon Code (published 9/2/2025) as the new statewide minimum for any code update on or after 7/1/2026. Lone Tree's currently-published adopted energy code is the 2021 IECC (per its own Design Criteria & Codes page, most recent update not dated on-page) — this predates the 7/1/2026 Model Low Energy and Carbon Code trigger point and does not itself violate HB22-1362, since that stricter floor applies only when a jurisdiction next updates its code. Flagged honestly rather than assumed; confirm current status with the Building Division (720-390-5211) before relying on this for a 2026-cycle project, since Lone Tree could adopt updated codes at any time.. Local amendments apply — see the Lone Tree overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lone Tree building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.