Required for solar photovoltaic and solar thermal installations in Cripple Creek. Within the B and BB (historic business) zone districts, the Development Code imposes specific placement rules to protect the visual character of the Historic District; outside those districts, standard electrical/building permit review applies under the locally adopted NEC and IBC.

Verified 2026-07-20 · Source

When you need this permit

  • Within the B and BB Zone Districts, solar device placement must follow a preference order: (1) integrated photovoltaic device, (2) detached in a side or rear yard away from the right-of-way, (3) on non-historic structures/additions, (4) on an accessory structure, (5) on the primary structure but not highly visible from a public right-of-way
  • Integrated devices and accessory equipment must match the color of the mounting surface; non-integrated roof-mounted devices on the primary structure must be parallel to the roofline and flush against the roof surface
  • Devices placed on the primary structure may not alter defining historic character features
  • Electrical work governed by the most current NEC edition as adopted by the State of Colorado
  • Electrical contractor must hold current Colorado State Electrical Board (DORA) licensure, verified by the City per its standard random job-site review policy

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit FeeNumeric fee table not located on a City page as of this review; contact the Building Department directly (719-689-3588 Ext. #1)
Set by City Council resolution
Statewide aggregate fee cap on active solar energy system installsStatutory cap on the aggregate of all City-imposed fees/charges related to installing an active solar energy system under 2 megawatts DC, applicable statewide regardless of Cripple Creek's own unpublished electrical fee resolution. Repealed effective December 31, 2029 unless renewed.
$500.00 maximum (residential) / $1,000.00 maximum (commercial), per Colorado C.R.S. 24-48.5-113 (enacted by HB21-1284)

Review timeline

Plan review
Not published — contact the department

How long did your Rooftop Solar / Photovoltaic Permit permit actually take in Cripple Creek?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified; historic-district placement/visibility rules confirmed if applicable

See the full Cripple Creek inspection guide — scheduling & re-inspection fees →

Tips

  • If your property is in the B or BB (historic business) zone district, Cripple Creek's Development Code favors integrated PV or off-structure placement over a conspicuous roof-mounted array on the primary structure — plan your system design around visibility from the public right-of-way early, since a highly visible primary-structure installation is the least-preferred option in the code's stated hierarchy.
  • Outside the historic B/BB districts, solar permitting follows the same NEC-governed electrical permit process and Colorado DORA electrician licensing verification as any other electrical work in Cripple Creek.

Frequently asked questions

Cripple Creek requires a rooftop solar / photovoltaic permit for: Within the B and BB Zone Districts, solar device placement must follow a preference order: (1) integrated photovoltaic device, (2) detached in a side or rear yard away from the right-of-way, (3) on non-historic structures/additions, (4) on an accessory structure, (5) on the primary structure but not highly visible from a public right-of-way; Integrated devices and accessory equipment must match the color of the mounting surface; non-integrated roof-mounted devices on the primary structure must be parallel to the roofline and flush against the roof surface; Devices placed on the primary structure may not alter defining historic character features; Electrical work governed by the most current NEC edition as adopted by the State of Colorado; Electrical contractor must hold current Colorado State Electrical Board (DORA) licensure, verified by the City per its standard random job-site review policy. If your project isn't listed, confirm with City of Cripple Creek Building Department at 719-689-3588 ext. 1 before starting work.

In Cripple Creek, the published Electrical Permit Fee is: Set by City Council resolution. Additional published fees: Statewide aggregate fee cap on active solar energy system installs — $500.00 maximum (residential) / $1,000.00 maximum (commercial), per Colorado C.R.S. 24-48.5-113 (enacted by HB21-1284). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Cripple Creek does not publish a plan-review timeline for this permit. Contact City of Cripple Creek Building Department at 719-689-3588 ext. 1 for current turnaround.

You'll need: Electrical / Building Permit Application — Solar scope. Depending on your project, Cripple Creek may also ask for: Certificate of Appropriateness (if within the B or BB Historic zone districts). See the required-documents checklist on this page for details on each.

Cripple Creek requires 2 inspection(s) for a rooftop solar / photovoltaic permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Cripple Creek Building Department (719-689-3588 ext. 1).

Apply through City of Cripple Creek Building Department at 337 E. Bennett Ave, Cripple Creek, CO 80813 (mailing: P.O. Box 430, Cripple Creek, CO 80813). Phone: 719-689-3588 ext. 1. Office hours: Building Inspector normal duty hours are 7:30 AM to 4:00 PM on Mondays and Fridays only (with an alternate day sometimes added around a holiday week, decided case-by-case). The inspector is typically present in the office at 337 E. Bennett Ave from 7:30-9:00 AM on Monday/Friday mornings for questions in person or by phone (719-689-3588 ext. 1); after 9 AM the inspector is generally in the field performing inspections and returns to the office afterward for consultations. As of May 28, 2026, Martin L. Colgan serves as the City's Combination Inspector (Residential and Commercial Building, Mechanical, Plumbing, and Gas Piping). SAFEbuilt is stated on the City's Building Department page to be the City's new full-service company for plan review, permits, and inspections; the City notes it is currently implementing new permitting software and directs applicants to call the Building Department to ask about the current submission process.. Official information: https://www.cityofcripplecreek.com/building-department.

Cripple Creek, Colorado has adopted: 2018 International Building Code (IBC) — City of Cripple Creek Municipal Code Ch. 18, Art. 2 Sec. 18-2-10 and Art. 3 (adopted by Ord. No. 2019-03, as amended by Ord. No. 2022-06 and Ord. No. 2023-13); 2018 International Residential Code (IRC), including Appendices H, J, and Q — Ch. 18, Art. 4; International Plumbing Code (IPC), most current edition as adopted by the State of Colorado — Ch. 18, Art. 5; 2018 International Mechanical Code (IMC) — Ch. 18, Art. 6; 2015 International Fuel Gas Code (IFGC) — Ch. 18, Art. 7; 2018 International Energy Conservation Code (IECC) — Ch. 18, Art. 8; 2018 International Fire Code (IFC), including all appendices A-N — Ch. 18, Art. 9; 2018 International Existing Building Code (IEBC) — Ch. 18, Art. 10; National Electrical Code (NEC), most current edition as adopted by the State of Colorado — Ch. 18, Art. 11; 2018 International Swimming Pool and Spa Code (ISPSC) — Ch. 18, Art. 12; 2018 International Property Maintenance Code (IPMC) — Ch. 18, Art. 13; ASME A17.1 (2010)/A17.2 (2010)/A17.6 (2010)/A17.3 (2010) and A18.1 (2011) Safety Code for Elevators and Escalators, as adopted by Teller County (SCEE) — Ch. 18, Art. 14; all inspections performed by Teller County's designated ASME Certified Inspector, results submitted to the City Building Department; Manufactured Home Code (locally drafted, not an ICC model code) — Ch. 18, Art. 19, enacted by Ord. No. 2021-11; Note on code currency: Cripple Creek Municipal Code Chapter 18 adopts the 2018-cycle IBC/IRC/IMC/IECC/IFC/IEBC/ISPSC/IPMC by reference (via Ord. No. 2019-03, adopted Aug. 7, 2019), one cycle behind the 2021/2024 editions used by some neighboring Colorado jurisdictions (e.g. Vail's 2024 cycle). The IPC and NEC sections instead float to 'the most current edition as adopted by the State of Colorado,' so those two trades track the state's adoption cycle rather than a fixed local edition. This is the governing, most-recently-verified text of Municode's Cripple Creek library as of this review (chapter carries amendment history through Ord. No. 2023-13, effective 1-3-24).. Local amendments apply — see the Cripple Creek overview page for the full list.

Yes. In the B and BB Zone Districts, the City's Development Code sets an explicit placement preference (integrated PV first, then detached/off-structure placement, then non-historic structures, then accessory structures, with a highly visible primary-structure installation as the least preferred option) to protect the historic visual character, plus matching-color and flush-mounting requirements.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cripple Creek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.