Electrical Permit in Lone Tree, Colorado

Required for installation, alteration, or repair of electrical systems in Lone Tree. Issued directly by the City's Building Division as part of its combined Building/Mechanical/Electrical/Plumbing permit program (not deferred to the Colorado State Electrical Board). Governed by the 2023 NEC as adopted. Contractors must hold current Colorado State Electrical Board (DORA) licensure as a matter of state law, in addition to the City permit.

Verified 2026-07-23 · Source

When you need this permit

  • Governed by the 2023 NEC as adopted by the City of Lone Tree
  • Billed from the same shared valuation-based fee table as Building/Mechanical/Plumbing permits (not a separate state-anchored fee schedule)
  • Homeowners may perform electrical work on their own primary residence without a license per Colorado/Douglas-area practice; all other electrical installations require a contractor licensed by the Colorado State Electrical Board (DORA) Owner-builderContractor
  • Exempt from permit: temporary plug-in lighting/devices/equipment, and replacement of receptacles, switches, and lights
  • Confirmed 2026-07-23 via the City's own live Building Division FAQ: 'The Lone Tree Building Division does not issue or require contractor licenses' — only a valid Business License is required for all parties on a permit; there is no separate city trade-contractor registration beyond DORA state licensure Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee (same valuation-based schedule as Building/Mechanical/Plumbing)2026 Building Division Fee Schedule; billed under the single shared 'Building, Mechanical, Electrical and Plumbing Permit Fees for All Occupancies' table, not a separate DORA-anchored schedule
$23.50 minimum, scaling per the valuation tiers in the 2026 Building Fees schedule
Plan Review Fee
65% of Permit Fee, minimum $100.00
Douglas County Use TaxExplicit fee-schedule exemption; City Use Tax (2.5%) may still apply per City ordinance
Not collected on electrical-only permits/projects

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Lone Tree?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

See the full Lone Tree inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike some Colorado jurisdictions that pass through the State Electrical Board's fee schedule directly, Lone Tree bills electrical permits from its own shared local valuation-based fee table — do not assume the CRS 12-23-117(3) state fee schedule applies here.
  • Electrical contractors still need current Colorado State Electrical Board (DORA) licensure regardless of local permit issuance — this is a state-law requirement independent of which jurisdiction issues the local permit.
  • The City does not issue or require its own contractor license — confirmed directly on the Building Division's live FAQ page; a Business License is the only local credential needed for all parties on the permit, in addition to state DORA licensure. Contractor

Frequently asked questions

Lone Tree requires an electrical permit for: Governed by the 2023 NEC as adopted by the City of Lone Tree; Billed from the same shared valuation-based fee table as Building/Mechanical/Plumbing permits (not a separate state-anchored fee schedule); Homeowners may perform electrical work on their own primary residence without a license per Colorado/Douglas-area practice; all other electrical installations require a contractor licensed by the Colorado State Electrical Board (DORA); Exempt from permit: temporary plug-in lighting/devices/equipment, and replacement of receptacles, switches, and lights; Confirmed 2026-07-23 via the City's own live Building Division FAQ: 'The Lone Tree Building Division does not issue or require contractor licenses' — only a valid Business License is required for all parties on a permit; there is no separate city trade-contractor registration beyond DORA state licensure. If your project isn't listed, confirm with City of Lone Tree Community Development Department, Building Division at 720-390-5211 before starting work.

In Lone Tree, the published Electrical Permit Fee (same valuation-based schedule as Building/Mechanical/Plumbing) is: $23.50 minimum, scaling per the valuation tiers in the 2026 Building Fees schedule. Additional published fees: Plan Review Fee — 65% of Permit Fee, minimum $100.00; Douglas County Use Tax — Not collected on electrical-only permits/projects. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lone Tree does not publish a plan-review timeline for this permit. Contact City of Lone Tree Community Development Department, Building Division at 720-390-5211 for current turnaround.

You'll need: Building Permit Application (Electrical scope). See the required-documents checklist on this page for details on each.

Lone Tree requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Lone Tree Community Development Department, Building Division (720-390-5211).

Apply through City of Lone Tree Community Development Department, Building Division at 9220 Kimmer Dr., Suite 100, Lone Tree, CO 80124. Phone: 720-390-5211, email: building@cityoflonetree.com. Office hours: 7:00 AM - 4:00 PM, Monday-Friday, excluding holidays/weekends. Chief Building Official: Matt Archer. Community Development Director: Kelly First (kelly.first@cityoflonetree.com, 720-509-1274). General city line: 303-708-1818.. Official information: https://cityoflonetree.com/community-development/building/.

Lone Tree, Colorado has adopted: 2021 International Building Code (IBC), as amended — City of Lone Tree Design Criteria & Codes page; 2021 International Residential Code (IRC), as amended; 2021 International Fire Code (IFC); 2021 International Plumbing Code (IPC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC); 2023 National Electrical Code (NEC); 2017 ICC A117.1 Accessibility Code; Note on Chapter 18 (Building Regulations), Lone Tree Municipal Code: search-indexed content confirms the City has adopted the International Building Code, 2021 Edition, as amended, with a certified copy on file with the City Clerk; a local amendment adds Section 105.3.8 'Soils Test,' requiring a soils test prepared by a Colorado-registered professional engineer at building permit application, with an engineering geologist additionally required for hillside/geological-hazard/steep-slope sites at the Building Official's discretion. Full text of Chapter 18 could not be independently re-verified beyond this indexed excerpt because library.municode.com/co/lone_tree serves an Angular single-page app shell (empty of code text without JS rendering) and returned HTTP 403 to both a standard fetch and a full-browser-header curl retry — this is a partial-confidence caveat on the amendment-detail level only, not on the base code-edition list, which is independently confirmed on the City's own actively-maintained Design Criteria & Codes page.; HB22-1362 statewide energy floor (Colorado): as of 2026-07-06 (this review date), HB22-1362 requires that municipalities/counties updating their building code adopt an energy code achieving equivalent-or-better performance than the 2021 IECC + Model Electric and Solar Ready Code (effective window 7/1/2023-6/30/2026), stepping up to the Colorado Energy Code Board's Model Low Energy and Carbon Code (published 9/2/2025) as the new statewide minimum for any code update on or after 7/1/2026. Lone Tree's currently-published adopted energy code is the 2021 IECC (per its own Design Criteria & Codes page, most recent update not dated on-page) — this predates the 7/1/2026 Model Low Energy and Carbon Code trigger point and does not itself violate HB22-1362, since that stricter floor applies only when a jurisdiction next updates its code. Flagged honestly rather than assumed; confirm current status with the Building Division (720-390-5211) before relying on this for a 2026-cycle project, since Lone Tree could adopt updated codes at any time.. Local amendments apply — see the Lone Tree overview page for the full list.

No. The City of Lone Tree Building Division issues its own electrical permits as part of a combined Building/Mechanical/Electrical/Plumbing fee schedule; the State Electrical Board only issues permits in areas of Colorado without a local inspection program. Contractors performing electrical work in Lone Tree must still hold a valid Colorado State Electrical Board (DORA) license as a matter of state law.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lone Tree building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.