Electrical Permit — Lone Tree, Colorado · Requirements sheet
Verified 2026-07-23 · Source: https://cityoflonetree.com/wp-content/uploads/2025/12/6.-Building-Fees-2026.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical Permit in Lone Tree, Colorado
Required for installation, alteration, or repair of electrical systems in Lone Tree. Issued directly by the City's Building Division as part of its combined Building/Mechanical/Electrical/Plumbing permit program (not deferred to the Colorado State Electrical Board). Governed by the 2023 NEC as adopted. Contractors must hold current Colorado State Electrical Board (DORA) licensure as a matter of state law, in addition to the City permit.
Verified 2026-07-23 · Source
When you need this permit
- Governed by the 2023 NEC as adopted by the City of Lone Tree
- Billed from the same shared valuation-based fee table as Building/Mechanical/Plumbing permits (not a separate state-anchored fee schedule)
- Homeowners may perform electrical work on their own primary residence without a license per Colorado/Douglas-area practice; all other electrical installations require a contractor licensed by the Colorado State Electrical Board (DORA) Owner-builderContractor
- Exempt from permit: temporary plug-in lighting/devices/equipment, and replacement of receptacles, switches, and lights
- Confirmed 2026-07-23 via the City's own live Building Division FAQ: 'The Lone Tree Building Division does not issue or require contractor licenses' — only a valid Business License is required for all parties on a permit; there is no separate city trade-contractor registration beyond DORA state licensure Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
See the full Lone Tree inspection guide — scheduling & re-inspection fees →
Tips
- Unlike some Colorado jurisdictions that pass through the State Electrical Board's fee schedule directly, Lone Tree bills electrical permits from its own shared local valuation-based fee table — do not assume the CRS 12-23-117(3) state fee schedule applies here.
- Electrical contractors still need current Colorado State Electrical Board (DORA) licensure regardless of local permit issuance — this is a state-law requirement independent of which jurisdiction issues the local permit.
- The City does not issue or require its own contractor license — confirmed directly on the Building Division's live FAQ page; a Business License is the only local credential needed for all parties on the permit, in addition to state DORA licensure. Contractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lone Tree building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lone Tree
Electrical Permit in other cities
Compare electrical permit fees across Colorado →
Look up this fee in a different city →