How to schedule
Inspections are requested through the building department below.
- Address
- 75 S. Frontage Road West, Vail, CO 81657
- Phone
- 970-479-2139
- info@vail.gov
- Office hours
- Town of Vail main line 970-479-2100; Building Department direct line 970-479-2139; Chief Building Official emergency line 970-479-2143. Combination Inspector direct lines also published: Mike Horning (970) 479-2253, Jeff Lake (970) 479-2142.
- Website
- Official site
Inspection sequence
Applies to: Residential Addition / Interior Remodel Permit
- 1
Foundation (additions with new footings only)
Before concrete pour, per 48-inch minimum frost depth
- 2
Rough Frame
Framing complete, connection to existing structure verified
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 48-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes
Applies to: Electric Vehicle (EV) Charging Station / EVSE Permit
- 1
Rough Electrical
EVSE circuit wiring and panel/disconnect installed before concealment
- 2
Final Inspection
Charging equipment installed, system energized and verified per 2023 NEC Article 625
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Solar Thermal / Photovoltaic Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final Inspection
Racking, roof penetrations, and electrical connections verified
Final inspection only: Roofing Permit (Re-Roof)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Vail building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Vail building permits
Get alerts for Vail
We'll email you when Vail's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.