Colorado Springs building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Colorado Springs, Colorado.

Verified 2026-07-17 · Source

How to schedule

Inspections are requested through the building department below.

Address
2880 International Circle, Colorado Springs, CO 80910 (Main Office); North Office: 3939 Cordera Crest Avenue, Colorado Springs, CO 80924
Phone
(719) 327-2880
Office hours
Permits & Contractor Licensing: 7:30 a.m.–4:15 p.m.; Plan Review, Floodplain, and Enumeration: by appointment only; Inspectors office hours: 7:30–8:30 a.m.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend at least 30 inches below undisturbed ground surface (frost depth)

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Insulation / Energy

    Insulation and 2021 IECC (with Colorado Model Electric/Solar Ready Code) compliance before drywall

  5. 5

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour — 30-inch minimum frost depth

  2. 2

    Framing

    Structural framing, egress windows, fire separation (if attached)

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour — 30-inch minimum frost depth

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered

  2. 2

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  3. 3

    Final / Certificate of Occupancy

    All work complete, life safety systems functional

Applies to: Deck / Covered Patio Permit

  1. 1

    Footing

    Before concrete pour for structural post footings — 30-inch minimum frost depth

  2. 2

    Framing

    Structural framing before decking/cover installed

  3. 3

    Final

    Structure complete per approved plans; composite material evaluation report on-site if applicable

Applies to: Plumbing Permit

  1. 1

    Underground / Under-slab

    Before concrete pour — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Demolition Permit (Wrecking Permit)

  1. 1

    Pre-Demolition Utility & Asbestos Verification

    Verification of gas/electric disconnection and CDPHE asbestos clearance before demolition begins

  2. 2

    Final

    Site cleared, debris removed

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    EVSE circuit and connection verified, panel labeled, system energized

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    All devices installed, panel labeled, system energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Roofing Permit (Reroof)

  1. 1

    Mid-Roof (Tile only)

    Roof dry-in inspection required for tile roofs (BTR) — after underlayment, batten strips, and support flashing are in place, before tile is stocked or installed. NOT required for typical asphalt or Direct-to-Deck metal shingle roofs.

  2. 2

    Final

    Completed roof — verify flashing, drip edge, underlayment, and Class A/B covering compliance

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final — Structural / Racking and Electrical

    Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified

Colorado Springs building permits