Colorado Springs building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Colorado Springs, Colorado.
Verified 2026-07-17 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 2880 International Circle, Colorado Springs, CO 80910 (Main Office); North Office: 3939 Cordera Crest Avenue, Colorado Springs, CO 80924
- Phone
- (719) 327-2880
- Office hours
- Permits & Contractor Licensing: 7:30 a.m.–4:15 p.m.; Plan Review, Floodplain, and Enumeration: by appointment only; Inspectors office hours: 7:30–8:30 a.m.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation / Footings
Before concrete pour — footings must extend at least 30 inches below undisturbed ground surface (frost depth)
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-in before walls closed
- 4
Insulation / Energy
Insulation and 2021 IECC (with Colorado Model Electric/Solar Ready Code) compliance before drywall
- 5
Final
All work complete, ready for Certificate of Occupancy
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings and foundation before concrete pour — 30-inch minimum frost depth
- 2
Framing
Structural framing, egress windows, fire separation (if attached)
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Final
All work complete, ready for Certificate of Occupancy
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings)
Before concrete pour — 30-inch minimum frost depth
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Electrical, plumbing, mechanical rough-in before walls closed
- 4
Final
All work complete per approved plans
Applies to: Commercial Tenant Improvement Permit
- 1
Framing / Structural
After framing complete, before walls covered
- 2
MEP Rough-In
Mechanical, electrical, plumbing rough-in before walls closed
- 3
Final / Certificate of Occupancy
All work complete, life safety systems functional
Applies to: Deck / Covered Patio Permit
- 1
Footing
Before concrete pour for structural post footings — 30-inch minimum frost depth
- 2
Framing
Structural framing before decking/cover installed
- 3
Final
Structure complete per approved plans; composite material evaluation report on-site if applicable
Applies to: Plumbing Permit
- 1
Underground / Under-slab
Before concrete pour — pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected, no leaks, proper venting verified
Applies to: Demolition Permit (Wrecking Permit)
- 1
Pre-Demolition Utility & Asbestos Verification
Verification of gas/electric disconnection and CDPHE asbestos clearance before demolition begins
- 2
Final
Site cleared, debris removed
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final
EVSE circuit and connection verified, panel labeled, system energized
Applies to: Electrical Permit
- 1
Rough-In
Wiring and conduit installed before walls closed
- 2
Final
All devices installed, panel labeled, system energized
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Equipment
Equipment installation and ductwork before walls closed
- 2
Final
Equipment operational, combustion air and venting verified
Applies to: Roofing Permit (Reroof)
- 1
Mid-Roof (Tile only)
Roof dry-in inspection required for tile roofs (BTR) — after underlayment, batten strips, and support flashing are in place, before tile is stocked or installed. NOT required for typical asphalt or Direct-to-Deck metal shingle roofs.
- 2
Final
Completed roof — verify flashing, drip edge, underlayment, and Class A/B covering compliance
Applies to: Solar PV Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final — Structural / Racking and Electrical
Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified
Sources & verification
Verified against official sources. Last reviewed 2026-07-17.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Colorado Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Colorado Springs building permits
Get alerts for Colorado Springs
We'll email you when Colorado Springs's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.