Change of Occupancy / Change of Use Permit in Colorado Springs, Colorado
Required whenever an existing structure or space's occupancy classification changes in Colorado Springs (2023 PPRBC, Section RBC 110.1.2). PPRBD's own guidance document (rev. 11/01/24) walks applicants through the International Existing Building Code (IEBC) compliance paths — prescriptive, work area, or performance — that govern how a building is re-evaluated for a new use. PPRBD does not publish a distinct 'change of occupancy' fee line; the project is billed under PPRBD's standard commercial Building Permit process (the same Table A commercial regional modifier and Table B trade-attachment structure documented in this file's Commercial Tenant Improvement Permit entry). Where the project is commercial, the City of Colorado Springs Planning Department's Development Review Enterprise separately assesses its own Commercial-Alteration planning review fee (30% of the PPRBD Regional Building Department fee, capped at $10,000) under Resolution No. 191-25, effective Jan. 1, 2026 — a real, additional City-side cost distinct from PPRBD's fee.
Verified 2026-08-13 · Source
When you need this permit
- All structures undergoing a change of occupancy classification must meet the code provisions for the new occupancy classification regardless of which IEBC compliance path is used — including accessibility, sprinklers, fixture counts, and rated construction (2023 PPRBC RBC110.1.2 / IEBC)
- A Code Study Form (stamped by the design professional of record) plus a full code-data package is required in addition to the plans: scope of work, overall building description (area, height, levels), site description, and a full Building Code Analysis — occupancy classification, mixed-occupancy type, area of each occupancy, required occupancy separation, type of construction, fire areas, presence of fire sprinklers and the reason(s) for them, allowable area/height increase calculations, fire-resistive requirements, and egress/occupant-load calculations
- Architectural submittal required: demolition plan (if applicable), a Life Safety Plan when 2 or more exits are required, floor plans showing scope/dimensions/proper exits/fire-rated assemblies/egress travel distance, reflected ceiling plans, exterior elevations, sections showing fire-rated horizontal assemblies, wall-type/window/stair/restroom-accessibility details, and door schedules with rating/hardware
- Structural submittal required for any modified framing: specifications and design criteria, structural plans for all modified levels, structural sections and details
- 12-year pre-existing, non-conforming occupancy exception: if the Building Owner, Tenant, General Contractor, or a licensed design professional can provide sufficient evidence (e.g. county assessor's records, ownership/lease agreements, past utility bills with the business name) that a specific use of an existing building or space has remained unchanged for more than 12 years, the full change-of-occupancy documentation package does not apply in full — though PPRBD staff may still request additional information if the evidence is deemed insufficient
- Detailed electrical, mechanical, and plumbing plan requirements are covered separately under PPRBD's Commercial Electrical/Mechanical/Plumbing Plan Review handouts, not within the Change of Occupancy document itself
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing / Structural (if modified)
Required only where the change of occupancy involves modified framing or structural work
- 2
MEP Rough-In (if modified)
Mechanical, electrical, plumbing rough-in where the new occupancy requires added or altered systems
- 3
Final / Certificate of Occupancy
All work and code-compliance items complete for the new occupancy classification
See the full Colorado Springs inspection guide — scheduling & re-inspection fees →
Tips
- PPRBD does not charge a separate 'change of occupancy' fee — the project runs through the same commercial Table A/.97 modifier, Table B trade-attachment, and 28% plan-exam structure as this file's Commercial Tenant Improvement Permit entry. Don't budget for a distinct PPRBD line item that doesn't exist.
- Do budget for the City's separate DRE Commercial-Alteration planning fee (30% of the PPRBD Regional Building fee, capped at $10,000, effective Jan. 1, 2026) — this is a real, additional City-side cost on top of PPRBD's fees, easy to miss if you only price out the PPRBD side.
- The Code Study Form is the same hard gate documented in this file's Commercial Tenant Improvement Permit entry — plans without it, stamped by the design professional of record, will not be checked in.
- The 12-year unchanged-use exception can substantially reduce the documentation burden, but the evidence bar is specific (assessor records, lease/ownership agreements, utility bills with the business name) and PPRBD staff retains discretion to request more if what's provided is insufficient.
- If the new occupancy involves fire sprinkler or fire alarm work, that portion runs through Colorado Springs Fire Department's separate Fire Construction Services process (see this file's Fire Sprinkler and Fire Alarm System Permit entry) — not through PPRBD.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Colorado Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Colorado Springs
Change of Occupancy / Change of Use Permit in other cities
Compare change of occupancy / change of use permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Colorado Springs project checklist
Describe your project once and get every permit, document, and fee it triggers in Colorado Springs — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →