Electric Vehicle (EV) Charger / EVSE Permit in Colorado Springs, Colorado

Colorado Springs has no dedicated EV charger/EVSE permit type published by the Pikes Peak Regional Building Department (PPRBD) -- confirmed against PPRBD's Fee Schedule, Download/Forms, and Code pages, none of which contain an EV/EVSE-specific application, checklist, or fee line distinct from the standard valuation-based Electrical Permit (Table B/B.1/C). A residential Level 2 EVSE circuit is billed as ordinary electrical work under the 2023 National Electrical Code (adopted via the 2023 PPRBC). Separately, Colorado's HB24-1173 (Electric Vehicle Charging System Permits, effective 2024) requires 'covered' municipalities (10,000+ population) and counties (20,000+ population) -- a threshold Colorado Springs and El Paso County both clearly exceed -- to have adopted, by December 31, 2025, either the Colorado Energy Office's EV Charging Model Land Use Code, their own objective standards/administrative review ordinance, or an opt-out resolution retaining their existing process for EV CHARGING SYSTEM (i.e., public/commercial charging infrastructure) land-use permitting specifically. Which of these three paths Colorado Springs or El Paso County actually took was NOT confirmed in this research pass -- flagged as a genuine gap rather than assumed, and in any case HB24-1173 targets land-use/siting review for charging systems, not the routine electrical permit fee mechanism that governs a standard home EVSE circuit install (which continues to run through PPRBD's ordinary process below).

Verified 2026-07-20 · Source

When you need this permit

  • Electrical contractors must hold a current State of Colorado electrical license AND be registered with PPRBD to pull permits and perform work in the region
  • Homeowners may pull their own electrical permit only for work on their primary owner-occupied residence Owner-builder
  • EVSE circuit installation, alteration, or panel/service upgrade requires a standard PPRBD Electrical Permit
  • No EV-charger-specific application, checklist, or fee line item was located in PPRBD's published materials
  • Separately, public/commercial EV charging system installations may be subject to Colorado Springs' or El Paso County's land-use review process under HB24-1173 (Electric Vehicle Charging System Permits) -- confirm current compliance-path status (model code adoption, own ordinance, or opt-out) directly with City Planning before pursuing a commercial charging site

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Standalone Electrical Permit (Table C) -- $100 to $500PPRBD Appendix B, Table C -- permit fee tier for electrical work NOT associated with a building permit; the tier a typical residential EVSE circuit install would likely fall into, though no EV/EVSE-specific line item exists
$50.00
Trade Attachment Fee (Table B.1) -- detached accessory structure or dwelling alteration, per tradePPRBD Appendix B, Table B.1 -- applies if the EVSE electrical permit is attached to a building permit (e.g., part of a garage remodel)
$50.00 for each trade

Review timeline

Plan reviewTypical estimate — confirm current times with the Colorado Springs building department
~0–0 business days

How long did your Electric Vehicle (EV) Charger / EVSE Permit permit actually take in Colorado Springs?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    EVSE circuit and connection verified, panel labeled, system energized

See the full Colorado Springs inspection guide — scheduling & re-inspection fees →

Tips

  • PPRBD does not publish a distinct EV/EVSE fee -- a standard home EVSE circuit is billed as ordinary electrical work under Table C ($50 minimum tier) or Table B.1 ($50/trade) if attached to a building permit.
  • Colorado's HB24-1173 imposes a separate, distinct land-use permitting streamlining requirement on Colorado Springs and El Paso County (as covered jurisdictions above the 10,000/20,000 population thresholds) for EV CHARGING SYSTEM siting -- this is most relevant for public/commercial charging stations, not a routine residential Level 2 charger circuit, and this file could not confirm which of the three HB24-1173 compliance paths (model code, own ordinance, or opt-out) the City/County ultimately adopted by the December 31, 2025 deadline.

Frequently asked questions

Colorado Springs requires an electric vehicle (ev) charger / evse permit for: Electrical contractors must hold a current State of Colorado electrical license AND be registered with PPRBD to pull permits and perform work in the region; Homeowners may pull their own electrical permit only for work on their primary owner-occupied residence; EVSE circuit installation, alteration, or panel/service upgrade requires a standard PPRBD Electrical Permit; No EV-charger-specific application, checklist, or fee line item was located in PPRBD's published materials; Separately, public/commercial EV charging system installations may be subject to Colorado Springs' or El Paso County's land-use review process under HB24-1173 (Electric Vehicle Charging System Permits) -- confirm current compliance-path status (model code adoption, own ordinance, or opt-out) directly with City Planning before pursuing a commercial charging site. If your project isn't listed, confirm with Pikes Peak Regional Building Department at (719) 327-2880 before starting work.

PPRBD does not publish a distinct EV/EVSE fee -- a standard residential EVSE circuit is billed as ordinary electrical work under the standalone Table C fee ($50 minimum) or the Table B.1 trade attachment fee ($50/trade) if bundled with a building permit. Separately, Colorado's HB24-1173 requires Colorado Springs and El Paso County (as covered jurisdictions) to have a streamlined land-use review process specifically for EV CHARGING SYSTEM (commercial/public charger) siting -- this file could not confirm which compliance path the City/County took.

Plan review for an electric vehicle (ev) charger / evse permit in Colorado Springs typically runs 0–0 business days. This is an estimate, not a published figure — confirm current review times with Pikes Peak Regional Building Department at (719) 327-2880.

You'll need: Electrical Permit Application (PPRBD web account). See the required-documents checklist on this page for details on each.

Colorado Springs requires 2 inspection(s) for an electric vehicle (ev) charger / evse permit, in order: Rough Electrical, Final. Schedule each through Pikes Peak Regional Building Department ((719) 327-2880).

Apply through Pikes Peak Regional Building Department at 2880 International Circle, Colorado Springs, CO 80910 (Main Office); North Office: 3939 Cordera Crest Avenue, Colorado Springs, CO 80924. Phone: (719) 327-2880, email: Contact via Email Specific Departments form at pprbd.org/Information/Email. Office hours: Permits & Contractor Licensing: 7:30 a.m.–4:15 p.m.; Plan Review, Floodplain, and Enumeration: by appointment only; Inspectors office hours: 7:30–8:30 a.m.. Official information: https://www.pprbd.org/.

Colorado Springs, Colorado has adopted: 2023 Pikes Peak Regional Building Code (PPRBC), 2nd Printing — the regional code framework adopted by reference by all member jurisdictions including Colorado Springs (City Ordinance 23-16); effective June 30, 2023; 2021 International Building Code (IBC) — adopted by reference via the 2023 PPRBC; 2021 International Residential Code (IRC) — adopted by reference via the 2023 PPRBC; 2021 International Mechanical Code (IMC) — adopted by reference via the 2023 PPRBC; 2021 International Fuel Gas Code (IFGC) — adopted by reference via the 2023 PPRBC; 2021 International Plumbing Code (IPC) — adopted by reference via the 2023 PPRBC (NOTE: unlike Denver, the Pikes Peak region uses the IPC, not UPC); 2023 National Electrical Code (NEC) — adopted by reference via the 2023 PPRBC; 2021 International Energy Conservation Code (IECC), with the Colorado Model Electric Ready and Solar Ready Code (CMERSRC) — adopted by reference via the 2023 PPRBC; 2021 International Existing Building Code (IEBC) — adopted by reference via the 2023 PPRBC; 2021 International Swimming Pool and Spa Code (ISPSC) — adopted by reference via the 2023 PPRBC; ASME A17.1-2019 Safety Code for Elevators & Escalators, ASME A17.3-2005 (existing elevators/escalators), ASME A18.1-2017 (vertical platform lifts/stairway chairlifts) — conveyance codes adopted via the 2023 PPRBC; 2017 ICC/ANSI A117.1 Accessibility Standard — adopted via the 2023 PPRBC; The International Fire Code and its amendments are adopted separately by the applicable fire authority (not PPRBD) — contact the local fire district directly for fire code / fire plan submittal requirements. Local amendments apply — see the Colorado Springs overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Colorado Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.