Inspection sequence, scheduling, and re-inspection fees for building permits in Timnath, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
Timnath Town Center, 4750 Signal Tree Drive, Timnath, CO 80547
Phone
970-224-3211
Office hours
Weekdays, 8:00 a.m. to 4:30 p.m. Building Permit Technician direct line 970-449-4639; Building Official direct line 970-566-4674; SAFEbuilt, Inc. inspection line 970-674-1036 (call/email by 4:00 p.m. the prior business day for next-business-day scheduling); SAFEbuilt Colorado regional office 970-686-7511 (561 E. Garden Drive, Unit C, Windsor, CO 80550 — SAFEbuilt's own Northern Colorado office, not a separate Timnath location).

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Core & Shell)

  1. 1

    Footing/Foundation

    Prior to concrete placement, per stamped structural plans and soils report

  2. 2

    Framing/Structural

    Structural framing per stamped structural plans

  3. 3

    Special Inspections

    Per the structural engineer's list of special inspections required by the Building Code; engineering letters of approval required

  4. 4

    Rough Electrical/Mechanical/Plumbing/Fire Protection

    Trade rough-ins before concealment, per stamped MEP and (if applicable) fire protection plans

  5. 5

    Final Building Inspection (SAFEbuilt)

    All final building inspections from the Town's building inspector (SAFEbuilt) must be complete before Certificate of Occupancy

  6. 6

    Final Poudre Fire Authority Approval

    Required before Certificate of Occupancy, per the Town's Commercial Checklist for Issuance of Certificate of Occupancy

  7. 7

    Site Grading Certificate / Site & Landscaping Final Approval

    Grading certificate completed by the Town Engineer; final site and landscaping approval from the Town Planner; parking lot striping completed

  8. 8

    Water/Sewer District Final Approval

    Final approval from the water district (meters set) and sewer district, per the Commercial Certificate of Occupancy Checklist

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough Electrical/Mechanical/Plumbing

    Trade rough-ins before concealment, per stamped MEP plans (where applicable to the scope of work)

  2. 2

    Framing/Structural

    Required only where the scope includes structural changes per stamped structural plans

  3. 3

    Final Building Inspection (SAFEbuilt)

    All final building inspections from the Town's building inspector (SAFEbuilt) must be complete before Certificate of Occupancy

  4. 4

    Health Department Approval (restaurant/commercial kitchen TI only)

    Larimer County health department approval required as a Certificate of Occupancy condition for restaurant/commercial-kitchen tenant finishes

  5. 5

    Final Poudre Fire Authority Approval

    Required before Certificate of Occupancy, per the Town's Commercial Checklist for Issuance of Certificate of Occupancy

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Before concrete placement

  2. 2

    Framing

    Structural framing, bracing, and fasteners in place before cover

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment; subject to contemporaneous Colorado electrical/plumbing license review per HB19-1086/SB19-156

  4. 4

    Final Inspection

    All work complete; must occur within 2 years of permit issuance or a new permit is required

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footings

    After trenches excavated and forms erected, prior to concrete placement

  2. 2

    Frame/Rough Inspection

    After roof, framing, bracing, and fasteners (and any utility rough-ins) are in place

  3. 3

    Final Inspection

    After the structure/addition is completed

Applies to: Electric Vehicle (EV) Charger Permit

  1. 1

    Rough Electrical

    Wiring, conduit, and disconnect placement verified before concealment, per the same framework documented in the Electrical Permit entry.

  2. 2

    Final Inspection

    Charger installed, panel labeled, system energized.

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment; subject to contemporaneous state license review

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before concealment

  2. 2

    Final Inspection

    Equipment operational; combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Before concealment — pipe slope, materials, cleanouts

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Mid-Roof Inspection

    May be required depending on scope — confirm with the Building Department upon permit issuance

  2. 2

    Final Roof Inspection

    Required for all re-roof permits

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement, and grounding before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, placards/labels, and electrical connections verified

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Timnath building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Timnath building permits

Get alerts for Timnath

We'll email you when Timnath's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.