Commercial Building Permit (New Construction / Core & Shell) in Timnath, Colorado
Required for new commercial, industrial, and multi-family structures in Timnath, including Core & Shell buildings for the Town's growing retail/outlet and business-park development. The Town's Building Permit Application lists 'Commercial' as its own distinct project-type checkbox (separate from 'Tenant Finish'). Plan review follows SAFEbuilt Colorado's dedicated 'New Commercial Plan Submittal Procedure'; the Town of Timnath remains the permit-issuing authority.
Reviewed 2026-08-02 · Source
When you need this permit
- Complete a Town of Timnath Building Permit Application, checking 'Commercial' as the project type, and providing total project valuation plus a separate Commercial-only Electrical Estimated Valuation field
- Applicant/general contractor must hold a current Town of Timnath Contractor License to receive CommunityCore portal access for submittal Contractor
- Submit an electronic set of stamped plans per SAFEbuilt Colorado's New Commercial Plan Submittal Procedure: Town of Timnath-approved Site Plan (all pages — title page, utility drawings, drainage plans, elevations, landscape plans, etc.), Architectural Plans, Project Specifications, Structural Plans (with a soils report and structural calculations), a list of special inspections required by the Building Code, Electrical Plans (load calculations, one-line diagrams, fault current analysis), Mechanical/Plumbing Plans, Fire Protection Plans (if the design includes a fire protection system), and Energy Code Compliance Documents — all sheets must bear the original seal of a Colorado-licensed architect or engineer per C.R.S. (exemptions under section 12-4-112 C.R.S. apply to specific sub-disciplines)
- A complete set of Planning Department site plans (all pages on record with the Town) must also be submitted, per the Town's Building Permit Application submittal-requirements page
- Restaurants and commercial kitchens carry additional design requirements addressed prior to permit issuance: grease interceptor sized per the adopted Plumbing Code (or engineer-designed) for grease-producing operations; an approved fire sprinkler system for restaurants over 5,000 SF or with 50+ occupants; Type I hoods with suppression for grease/smoke-producing cooking equipment, Type II hoods for heat/steam-only equipment; two exits with panic hardware for spaces with a 50+ occupant load; a seating plan for interior/exterior dining areas; and health department (Larimer County) approval as a condition of Certificate of Occupancy
- A Site Grading Certification must be provided to and approved by the Town prior to Certificate of Occupancy for new Commercial/Industrial structures and for additions to existing Commercial/Industrial structures
- Although not required, the Town/SAFEbuilt recommend a pre-application meeting with SAFEbuilt and the fire protection district before applying, submitting a building code summary and question list in advance to speed review
- Certificate of Occupancy requires: all final building inspections (SAFEbuilt) complete, all special inspection reports and engineering letter approvals, final Poudre Fire Authority approval, a grading certificate from the Town Engineer, final site/landscaping approval from the Town Planner, completed parking lot striping, final water district approval with meters set, final sewer district approval, and any outstanding fee-agreement balance paid in full
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 8 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
As with all other trade/base permit fees in this record, Appendix 4-A's valuation-based base building permit fee table was not locatable online; Show full citationHide
As with all other trade/base permit fees in this record, Appendix 4-A's valuation-based base building permit fee table was not locatable online; the Appendix 4-A schedule obtained directly from Ordinance No. 5, Series 2024 (Exhibit 4-A) contains only impact fees, sales/use tax rates, and a returned-check fee — no base building-permit valuation fee line. Contact buildings@timnathgov.com or 970-224-3211 for a quote. Note: the Town's residential Valuation Calculator (2022 ICC Building Valuation Data basis) is explicitly limited to residential elements (Main Floor, Basement, Garage, Deck, etc.) and does not include commercial/mercantile/business occupancy valuation categories, so it cannot be used to estimate commercial fees.CURRENT rate effective 9/2/2024 per Ordinance No. Show full citationHide
CURRENT rate effective 9/2/2024 per Ordinance No. 5, Series 2024, Exhibit 4-A (Appendix 4-A), amending Sec. 4-6-50(a) — supersedes the prior $330.00/1,000 SF rate. For a non-residential Core & Shell building permit, this fee is only assessed and payable at issuance of the tenant-finish permit, not at Core & Shell issuance (Sec. 4-6-50(a)(1)).CURRENT rate effective 9/2/2024 per Ordinance No. Show full citationHide
CURRENT rate effective 9/2/2024 per Ordinance No. 5, Series 2024, Exhibit 4-A — the Town reduced this fee from a prior $267.00/1,000 SF to $0.00. Unlike the Police/Public Buildings/Transportation fees, the ordinance text does not carve out a Core & Shell deferral for this fee (payable at issuance of any building permit for any structure), though it is currently zero regardless.Review timeline
Inspection process
- 1
Footing/Foundation
Prior to concrete placement, per stamped structural plans and soils report
- 2
Framing/Structural
Structural framing per stamped structural plans
- 3
Special Inspections
Per the structural engineer's list of special inspections required by the Building Code; engineering letters of approval required
- 4
Rough Electrical/Mechanical/Plumbing/Fire Protection
Trade rough-ins before concealment, per stamped MEP and (if applicable) fire protection plans
- 5
Final Building Inspection (SAFEbuilt)
All final building inspections from the Town's building inspector (SAFEbuilt) must be complete before Certificate of Occupancy
- 6
Final Poudre Fire Authority Approval
Required before Certificate of Occupancy, per the Town's Commercial Checklist for Issuance of Certificate of Occupancy
- 7
Site Grading Certificate / Site & Landscaping Final Approval
Grading certificate completed by the Town Engineer; final site and landscaping approval from the Town Planner; parking lot striping completed
- 8
Water/Sewer District Final Approval
Final approval from the water district (meters set) and sewer district, per the Commercial Certificate of Occupancy Checklist
See the full Timnath inspection guide — scheduling & re-inspection fees →
Tips
- The Town's Building Permit Application treats 'Commercial' (new construction/Core & Shell) and 'Tenant Finish' as two distinct project-type checkboxes — use the separate commercial-tenant-improvement-permit entry for interior build-outs of existing commercial space.
- The non-residential Capital Improvement Impact Fee rates changed substantially effective September 2, 2024 (Ordinance No. 5, Series 2024) — Police and Transportation fees per 1,000 SF dropped, Public Buildings rose nearly 3x, and Stormwater was zeroed out. Always pull the current Appendix 4-A table (via the adopting ordinance) rather than an older cached fee sheet.
- For a Core & Shell commercial building permit, three of the four non-residential impact fees (Police, Public Buildings, Transportation) are deferred and only become due when the tenant-finish permit is later issued — budget for this two-stage fee timing rather than assuming everything is due at shell permit issuance.
- The Town's own 'Licenses, Fees, and Charges' page lists 'Retail Fees' and 'Office Industrial Fees' as named buttons, but those two and the adjacent 'Building Permit Fees', 'General Permit Fees' and 'One-Stop Fees' buttons all carry an empty href="" with no fee document attached — all five lead nowhere. Ask the Town directly for the applicable fee figures.
- A pre-application meeting with SAFEbuilt Colorado and the fire protection district is optional but recommended by the Town to speed up commercial plan review.
- No published SLA exists for commercial review time, but a real Town of Timnath economic-incentive letter (civicweb document 110110, dated 3/14/2024) shows an actual $500,000 commercial tenant-finish project ran from permit application to permit issuance in about 88 calendar days — useful as a rough real-world data point when budgeting a project timeline, though it is one project's outcome, not a guaranteed turnaround.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Timnath building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Timnath.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Timnath's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Timnath yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Timnath lands. Privacy.
Other permits in Timnath
Commercial Building Permit (New Construction / Core & Shell) in other cities
Compare commercial building permit (new construction / core & shell) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Timnath project checklist
Describe your project once and get every permit, document, and fee it triggers in Timnath — in one checklist. Free, for any city and any number of projects.
Get started →