Change of Use — Timnath, Colorado · Requirements sheet
Verified 2026-08-14 · Source: https://timnath.org/building-and-construction-services/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use in Timnath, Colorado
Timnath Land Use Code Section 2.9.19 establishes 'Change in Use' as an administrative review procedure, conducted by the Community Development Director, for a structure changing from one permitted use to another that results in no further site development beyond the original approval. All changes in use require building permit submission and approval; if the change would increase impacts (such as traffic) beyond the original approval or existing site conditions, a full Development Site Plan review is required instead, per Section 2.9.9. The Poudre Fire Authority, which reviews Timnath building permit submittals for fire-code compliance, separately charges its own flat Change of Occupancy review fee.
Verified 2026-08-14 · Source
When you need this permit
- A Change in Use review applies when a structure changes from one permitted use to another, per Land Use Code Section 2.9.19; it is an administrative review conducted by the Community Development Director, not a public-hearing process
- All changes in use require building permit submission and approval, per Section 2.9.19
- If a change in use would result in increased impacts (e.g., traffic) beyond the original approval or existing site conditions, a full Development Site Plan review is instead required under Section 2.9.9, at the Community Development Director's determination
- A nonconforming use may only be changed to a new use that conforms to the standards of the applicable zoning district; once a nonconforming use is changed to a conforming use, the prior nonconforming use may not be re-established, per Section 2.11.4.3
- Any nonconforming signs present on the site must be removed before a change of use permit may be issued, per Section 2.11.6.9
- The Town's base building/trade permit fee schedule (Appendix 4-A of Municipal Code Chapter 4), which governs this and other Building Department permits, is not published online as of the last verification; a written fee quote must be obtained from Building and Construction Services
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
The Town's base fee schedule (Appendix 4-A of Municipal Code Chapter 4) is not published online as of the last verification; Show full citationHide
The Town's base fee schedule (Appendix 4-A of Municipal Code Chapter 4) is not published online as of the last verification; contact Building and Construction Services (970-449-4639 / buildings@timnathgov.com) or Planning Services (970-224-3211 x5) for a current written fee quote.The Poudre Fire Authority (PFA), which reviews building permit submittals within the Town of Timnath as one of its four governmental jurisdictions, lists a flat $100.00 'Change of Occupancy' fee… Show full citationHide
The Poudre Fire Authority (PFA), which reviews building permit submittals within the Town of Timnath as one of its four governmental jurisdictions, lists a flat $100.00 'Change of Occupancy' fee under its Development Review Fees in the 2026 Poudre Fire Authority Fee Schedule. This is PFA's fire-code-side review fee and is separate from any Town of Timnath building-permit fee under Appendix 4-A.Review timeline
Inspection process
See the full Timnath inspection guide — scheduling & re-inspection fees →
Tips
- Timnath's 'Change in Use' is a genuinely light-touch administrative review (LUC 2.9.19) ONLY if your new use doesn't increase impacts like traffic beyond the original site approval — if it does, the Community Development Director can bump you into a full Development Site Plan review (LUC 2.9.9) instead, which is a much bigger process.
- If the space has any nonconforming signage, budget time to remove it first — LUC Section 2.11.6.9 requires nonconforming signs to come down before a change of use permit can be issued.
- Because Timnath's base fee schedule (Appendix 4-A) isn't published online, get a written quote from Building and Construction Services before budgeting — don't assume a peer-jurisdiction fee applies.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Timnath building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Timnath's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Timnath yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Timnath lands. Privacy.
Other permits in Timnath
Change of Use in other cities
Compare change of use fees across Colorado →
Look up this fee in a different city →