Telluride building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Telluride, Colorado.
Verified 2026-07-13 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Rebekah Hall, 113 W. Columbia Ave, Telluride, CO 81435 (mailing: PO Box 397, Telluride, CO 81435)
- Phone
- 970-728-5700
- Office hours
- Main Planning & Building Department line 970-728-5700. Building Official Sam Samuelson: 970-728-2143. SmartGov online-portal assistance / Historic Preservation, Planning and Building Coordinator Tammy Brand: 970-728-2175. Building Inspector Bill Spencer: 970-708-2464.
- Website
- Official site
Inspection sequence
Applies to: Residential Addition / Interior Remodel Permit
- 1
Foundation (additions with new footings only)
Before concrete pour, per 48-inch minimum frost depth
- 2
Rough Frame
Framing complete, connection to existing structure verified
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 48-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes
Applies to: Residential/Commercial Solar Photovoltaic (PV) Permit
- 1
Foundation (ground-mount only)
Before concrete pour, per 48-inch minimum frost depth, for ground-mounted racking systems.
- 2
Rough Electrical / Interconnection
Array wiring, disconnect, and panel connections verified before concealment, per 2023 NEC Article 690.
- 3
Final Inspection
All work complete per approved plans and applicable codes.
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Electric Vehicle (EV) Charging Station Permit, Roofing Permit (Re-Roof)
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Telluride building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Telluride building permits
Get alerts for Telluride
We'll email you when Telluride's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.