Electric Vehicle (EV) Charging Station Permit — Telluride, Colorado · Requirements sheet
Reviewed 2026-08-02 · Source: https://telluride.gov/DocumentCenter/View/13559/2024-Building-Permit-Fees-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station Permit in Telluride, Colorado
Telluride publishes no separate fee, form or process for EV charging station (EVSE) installations -- the Building Permit Fee Schedule and the Building Division's permit list carry no EV charger, EVSE or electric vehicle charging station category. An EV charger installation (new branch circuit for a Level 2 charger, panel work and so on) is billed as an Electrical Permit under the same Table 1-A valuation-based fee schedule used for all electrical work; that is the governing charge for an EV charger circuit. Telluride's 2020 Census population (2,607) is below the 10,000-resident municipal threshold in Colorado HB24-1173 (effective 8/7/2024), so the Town is not a covered municipal permitting agency required to adopt the state model EV-charger permit code, custom standards, or the statute's 3-business-day decision-notification timeline. Telluride does not participate in SolarAPP+, which in any case does not cover EV charger installations.
Reviewed 2026-08-02 · Source
When you need this permit
- Treated as an Electrical Permit — governed by the 2023 NEC as adopted (Ordinance 1620) plus the 2023 Colorado Model Electric Ready and Solar Ready Code
- Administered via SmartGov (twn-telluride-co.smartgovcommunity.com), the same portal used for building, electrical, plumbing, and mechanical permits
- Fee calculated per Table 1-A based on electrical-specific valuation — no distinct EV-charger fee tier is published
- Contractor must hold a current Town of Telluride business license, plus any required Colorado state electrical licensure
- Telluride's 2020 Census population (2,607) is far below the 10,000-resident HB24-1173 municipal threshold, so the Town is not required to adopt the state's model EV-charger permitting code or the statute's 3-business-day decision-notification timeline
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Telluride's published Building Permit Fee Schedule (telluride.gov/DocumentCenter/View/13559/2024-Building-Permit-Fees-PDF) and Building Codes page do not list a separate EV charger / EVSE fee category; Show full citationHide
Telluride's published Building Permit Fee Schedule (telluride.gov/DocumentCenter/View/13559/2024-Building-Permit-Fees-PDF) and Building Codes page do not list a separate EV charger / EVSE fee category; an EV charger install is billed as a standard Electrical Permit under Table 1-A.Review timeline
Inspection process
- 1
Rough Electrical / Final Inspection
Standard electrical rough-in and final inspection covering the new circuit, panel work, and charger connection
See the full Telluride inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'EV charger permit' in Telluride — apply for a standard Electrical Permit through SmartGov and reference the EV charging station in the project description.
- Confirm with the Building Division whether your specific installation (e.g., new subpanel, service upgrade) also triggers a Building Permit in addition to the Electrical Permit.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Telluride building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Telluride's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Telluride yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Telluride lands. Privacy.
Other permits in Telluride
Electric Vehicle (EV) Charging Station Permit in other cities
Compare electric vehicle (ev) charging station permit fees across Colorado →
Look up this fee in a different city →