Conditional Use Permit (Zoning Ordinance Section 6) in Sedgwick, Colorado
A discretionary land-use approval required BEFORE a building permit application, but only for a narrow, explicitly enumerated list of uses per zoning district under the Town's Zoning Ordinance (Section 2-B 'Conditional Uses Permitted' and Section 6 'Conditional Use Review'). This is NOT a commercial-building-permit or TI-permit — it is a use-compatibility review, required in Low Density Residential (R-LD), Mobile Home (R-MH), Commercial 1 (C1), and Commercial Zoning Highway Business (C2) districts alike, each with its own enumerated list. Discovered during an independent 2026-08-02 adversarial re-chase of the jurisdiction's commercial-permit finding; not documented elsewhere in this file prior to this pass. Ordinary commercial construction (Retail, Office, Manufacturing — the categories on the Town's Building Permit form) is unconditionally permitted in C1/C2 and does NOT trigger this process; it only applies to the specific enumerated uses below.
Reviewed 2026-08-02 · Source
When you need this permit
- Applies only to the following enumerated 'Conditional Uses Permitted' per Zoning Ordinance Section 2-B: in Commercial 1 (C1) — public utility stations, rooming or boarding houses, wholesale businesses, campgrounds, transient mobile home parks, and cemeteries; Commercial Zoning Highway Business (C2) — any use conditional under C1; Low Density Residential (R-LD) — public utility stations, multi-family dwellings, cluster housing developments, convenience businesses, rooming or boarding houses, professional activities, cemeteries, mobile homes; Mobile Home (R-MH) — mobile home parks, convenience businesses, public utility stations
- Written application submitted to the Board of Trustees, with evidence demonstrating compliance with the conditions/safeguards for that specific use (Section 6-C)
- Applicant must post a sign on the property (minimum 3 ft x 4 ft, posted at least 4 feet above grade, lettering at least 2 inches) at least 15 days before the Planning Commission review meeting, in a location visible from public right-of-way
- Published notice of the Board of Trustees public hearing in a newspaper of general circulation, at the applicant's expense, at least 15 days before the hearing
- Written notice mailed to owners of adjacent properties at least 15 days before the hearing; applicant must furnish the Town a list of adjacent property owners at least 20 days before the anticipated hearing date
- Planning Commission studies the application and issues a review/recommendation to the Board of Trustees before the Board rules
- Board of Trustees holds the public hearing and grants or denies the permit, which if granted is in force indefinitely provided the use continues to comply with its original conditions
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Planning Commission Review & Recommendation
Application and supporting evidence referred to the Planning Commission for study; the Commission returns a recommendation to the Board of Trustees before the Board rules. In the absence of a Planning Commission, the Board of Trustees assumes this role itself.
- 2
Board of Trustees Public Hearing & Decision
Noticed public hearing (posted sign, published newspaper notice, and mailed notice to adjacent owners all required); Board grants or denies the conditional use, with authority to impose additional conditions
See the full Sedgwick inspection guide — scheduling & re-inspection fees →
Tips
- This is easy to conflate with a commercial-building-permit or TI-permit, but it is not one — it is a discretionary land-use approval that gates a short, specific list of uses (e.g., wholesale businesses, campgrounds, transient mobile home parks, rooming/boarding houses, cemeteries, public utility stations), not commercial construction in general.
- Retail, Office, and Manufacturing projects — the actual commercial categories on the Town's Building Permit form — are unconditionally permitted in Commercial 1 (C1) and Commercial Zoning Highway Business (C2) and do NOT require this process; go straight to the standard $60 Building Permit for those.
- Budget real lead time if your use IS on the conditional list: the notice requirements alone (15-20 days for posting, publication, and mailed notice) mean this cannot be a same-week approval like the general Building Permit.
- The Flood Protection district ('EP') has its own analogous 'special permit' process (Zoning Ordinance Section 2-E) that explicitly follows the same procedure as this Conditional Use Permit process — likely overlapping in practice with the separately-documented Chapter 150 Flood Damage Prevention floodplain requirements on the residential-building-permit entry, though this file has not attempted to reconcile the two flood-related tracks beyond noting both exist.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedgwick building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sedgwick
Conditional Use Permit (Zoning Ordinance Section 6) in other cities
Compare conditional use permit (zoning ordinance section 6) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Sedgwick project checklist
Describe your project once and get every permit, document, and fee it triggers in Sedgwick — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →