Solar Photovoltaic (PV) Permit in Sedgwick, Colorado
Required for installing a rooftop or ground-mount photovoltaic system within the Town of Sedgwick. There is no dedicated 'Solar' checkbox on the Town's own Application for Building Permit — the closest matching category on the form is 'New/Replace Electrical (State Permit Required),' confirming that electrical work, including solar PV, is NOT reviewed under a town-adopted code (Sedgwick Town Code Chapter 152, 'Building Code,' is explicitly Reserved) but is instead routed to the State of Colorado. Two fees therefore apply: the Town's flat $60.00 Building Permit fee, and a separate State Electrical Permit fee (issued through the Colorado Division of Professions and Occupations/State Electrical Board), which is hard-capped by Colorado law regardless of system size.
Verified 2026-07-20 · Source
When you need this permit
- Submit the Town's Application for Building Permit, checking 'New/Replace Electrical (State Permit Required)' (no dedicated solar checkbox exists on the form)
- A separate State of Colorado Electrical Permit is required for the PV system's electrical installation, obtained from the State Electrical Board (Division of Professions and Occupations, DORA) since the Town has not adopted a local electrical inspection program
- A site plan/drawing showing the location of the proposed installation, property lines, and approximate water/sewer line locations must be attached to the Town application
- Contractors must submit proof of insurance to the Town (sedgwickco@pctelcom.coop) before the Town permit will be issued; not required for owner-performed work Contractor
- Colorado's homeowner exemption allows a property owner to personally perform the electrical/solar work if the property is not for sale, resale, or rent and is not generally open to the public Owner-builder
- Both the State Electrical Permit and the Town's Local Building Permit must be physically posted on the property before starting work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
HARD CAPPED regardless of calculated valuation: $500.00 for residential installations and $1,000.00 for commercial installations, per Colorado state law (C.R.S. Show full citationHide
HARD CAPPED regardless of calculated valuation: $500.00 for residential installations and $1,000.00 for commercial installations, per Colorado state law (C.R.S. § 24-48.5-113, enacted by HB21-1284). This cap applies uniformly statewide, including to State Electrical Board-issued permits.Review timeline
Inspection process
- 1
Zoning Administrator Review (Town)
Zoning-compliance and contractor-insurance check by the Town's Zoning Administrator; results in a written Approved or Denied determination
- 2
State Electrical Inspection
Rough-in and final inspection of the PV electrical installation performed under the State Electrical Permit
See the full Sedgwick inspection guide — scheduling & re-inspection fees →
Tips
- Sedgwick's own Building Permit application form has no 'Solar' checkbox — use 'New/Replace Electrical (State Permit Required)' and expect the actual electrical inspection to be handled entirely by the State of Colorado, not the Town.
- Regardless of which local or state fee table applies, Colorado law hard-caps the electrical permit fee for a solar installation at $500 for residential and $1,000 for commercial, per HB21-1284 (C.R.S. § 24-48.5-113) — this cap binds every jurisdiction and permitting authority in the state.
- The Town's own $60 flat fee is separate from and in addition to the State Electrical Permit fee — budget for both.
- SolarAPP+ (gosolarapp.org) automated permitting was not found listed as active for the Town of Sedgwick as of the last verification.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedgwick building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Sedgwick's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Sedgwick yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Sedgwick lands. Privacy.
Other permits in Sedgwick
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Sedgwick project checklist
Describe your project once and get every permit, document, and fee it triggers in Sedgwick — in one checklist. Free, for any city and any number of projects.
Get started →