Unincorporated Teller County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Teller County, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 800 Research Drive, Suite 100-B, Tamarac Business Center, Woodland Park, CO 80863
- Phone
- 719-687-3048
- Office hours
- Monday through Friday (except holidays), 7:30 a.m. to 4:00 p.m., closed 11:30 a.m. to 12:30 p.m. for lunch. Building Inspectors answer Building Code questions by phone or in person 7:30-8:30 a.m. Monday-Friday at 719-687-3048; the Plans Examiner is available by appointment only, scheduled by calling 719-686-5405. Source: https://www.tellercounty.gov/Building-Division
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit
- 1
Foundation/Footing
Before concrete pour; verifies soils-report compliance and the engineer/architect-stamped foundation design required under Article IV Section 1604.1
- 2
Framing
Structural framing per approved 2021 IBC engineered plans; coordinated with rough-in inspections under the separate electrical, mechanical, and plumbing permits for the same project
- 3
Final
All work complete per approved plans; precedes issuance of the Certificate of Occupancy, at which point the contractor/subcontractor listing on file must be accurate per Article III Section R105.3.3
Applies to: Residential Deck Permit
- 1
Footing/Pier
Before concrete pour or pier placement -- verify depth and spacing
- 2
Framing
Ledger attachment, water-resistive barrier, joist/beam connections
- 3
Final
Guardrails, stairs, and all work complete per approved plans
Applies to: Single Family Dwelling (SFD) / New Residential Building Permit
- 1
Foundation/Footing (Open Hole)
Before concrete pour; verify soils-report compliance, rebar, and 30-inch minimum frost depth
- 2
Framing
Structural framing per 2021 IRC and approved engineered plans
- 3
Final
All work complete per approved plans; Thermal Envelope Certificate posted
Applies to: Electric Vehicle (EV) Charging Station / EVSE Permit
- 1
Rough-In
EVSE circuit wiring and disconnect placement before concealment, per the general Electrical Permit inspection sequence
- 2
Final
Charging equipment installed and energized per 2023 NEC Article 625 and manufacturer instructions
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and service connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified per 2023 NEC
Applies to: Fire Sprinkler / Fire Alarm System Permit
- 1
Rough-In
Fire alarm wiring/devices or sprinkler piping inspected before concealment; likely performed by the covering fire protection district's AHJ rather than County Building Division staff, though this was not explicitly confirmed
- 2
Final Acceptance Test
System tested and verified operational before approval
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Gas Pressure Test
Ductwork and equipment rough-in before concealment; gas piping pressure test (minimum 10 psi, held 15+ minutes; welded piping 60 psi held 30+ minutes) before concealment or utility turn-on
- 2
Final
Equipment operational, combustion air/clearances verified
Applies to: Plumbing Permit
- 1
Underground/Rough-In
Before concealment -- verify pipe slope, materials, and cleanouts
- 2
Final
Fixtures connected, backflow protection verified where applicable, no leaks
Applies to: Residential Addition / Interior Remodel / Basement Finish Permit
- 1
Framing
Structural framing for additions; not applicable to non-structural interior/basement finish work
- 2
Final
All work complete per approved plans
Applies to: Solar Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel mounting, roof penetration sealing, electrical connections, inverter, and interconnection verified
Applies to: Tenant Improvement (TI) Permit
- 1
Rough-In
Trade rough-ins (electrical, mechanical, plumbing) per the applicable separate trade-permit inspection sequence, coordinated with the commercial building permit's framing inspection where structural work is involved
- 2
Final
Completed work verified against approved plans; a Certificate of Occupancy is issued or updated if the tenant improvement changes occupancy classification
Final inspection only: Change of Use Permit, Demolition Permit, Re-Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teller County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Teller County building permits
Get alerts for Unincorporated Teller County
We'll email you when Unincorporated Teller County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.