Skip to main content
PermitBase

Solar Permit in Unincorporated Teller County, Colorado

Required for installation of solar photovoltaic or other alternative-energy systems in unincorporated Teller County. Contractors performing the DC (direct current) side of installation must hold Teller County's Alternative Energy Installation Contractor AE/DC-side license; AC-side electrical work requires state electrical licensure.

Verified 2026-07-06 · Source

When you need this permit

  • Solar Permit Application is a distinct, separately listed application category
  • Alternative Energy Installation Contractor AE/DC-side license required for the D/C side of photovoltaic system installation and repair (annual fee $75.00, no testing required, but state licensure may still be required for the A/C side and plumbing-adjacent work such as solar hot water)
  • Covers Photovoltaic Solar Electric, Wind/Water Generated Electric, Solar Hot Water, Solar Heat (Active Space Heating), and Geothermal Energy systems; contractors must follow industry standards/codes and design prepared by a State of Colorado-licensed design professional

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Alternative Energy Installation Contractor AE/DC-side license (annual)Teller County Building Code Article II Section 105.m; testing not required locally, but state licensure may be required for A/C-side electrical or plumbing work
$75.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar Permit permit actually take in Unincorporated Teller County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, roof penetration sealing, electrical connections, inverter, and interconnection verified

See the full Unincorporated Teller County inspection guide — scheduling & re-inspection fees →

Tips

  • A dedicated county contractor license (Alternative Energy Installation Contractor AE/DC-side) exists specifically for solar/renewable installers, separate from the general Electrical Contractor registration. Contractor

Frequently asked questions

Unincorporated Teller County requires a solar permit for: Solar Permit Application is a distinct, separately listed application category; Alternative Energy Installation Contractor AE/DC-side license required for the D/C side of photovoltaic system installation and repair (annual fee $75.00, no testing required, but state licensure may still be required for the A/C side and plumbing-adjacent work such as solar hot water); Covers Photovoltaic Solar Electric, Wind/Water Generated Electric, Solar Hot Water, Solar Heat (Active Space Heating), and Geothermal Energy systems; contractors must follow industry standards/codes and design prepared by a State of Colorado-licensed design professional. If your project isn't listed, confirm with Teller County Building Division (Community Development Department) at 719-687-3048 before starting work.

In Unincorporated Teller County, the published Alternative Energy Installation Contractor AE/DC-side license (annual) is: $75.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Teller County does not publish a plan-review timeline for this permit. Contact Teller County Building Division (Community Development Department) at 719-687-3048 for current turnaround.

You'll need: Solar Permit Application. See the required-documents checklist on this page for details on each.

Unincorporated Teller County requires 2 inspection(s) for a solar permit, in order: Rough Electrical, Final. Schedule each through Teller County Building Division (Community Development Department) (719-687-3048).

Apply through Teller County Building Division (Community Development Department) at 800 Research Drive, Suite 100-B, Tamarac Business Center, Woodland Park, CO 80863. Phone: 719-687-3048. Office hours: Monday through Friday (except holidays), 7:30 a.m. to 4:00 p.m., closed 11:30 a.m. to 12:30 p.m. for lunch. Building Inspectors answer Building Code questions by phone or in person 7:30-8:30 a.m. Monday-Friday at 719-687-3048; the Plans Examiner is available by appointment only, scheduled by calling 719-686-5405. Source: https://www.tellercounty.gov/Building-Division. Official information: https://www.tellercounty.gov/Building-Division.

Unincorporated Teller County, Colorado has adopted: AUTHORITY MODEL: The Teller County Building Division is responsible for regulating building activities to ensure residential and commercial structures comply with applicable codes, and 'issues Permits and Inspects all land/property located within unincorporated Teller County.' Woodland Park, Cripple Creek, and Victor all have their own separate Building Departments for issuing permits and performing inspections within their own municipal jurisdictions. This is a direct, affirmative statement of first-party permit issuance to unincorporated-area residents (not a records/coordination-only office), independently confirmed live 2026-07-06. Source: https://www.tellercounty.gov/Building-Division; Colorado has no statewide mandatory building code for most jurisdictions (home-rule/county-adoption authority under C.R.S. Title 30, Article 28); Teller County adopts and amends its own construction codes for the unincorporated area via the Teller County Building Code, administered by a Board of Review created under C.R.S. 30-28-206 and 207.; Teller County Building Code, as adopted by the Board of County Commissioners, effective 07/01/2023 (Resolution 06-22-2023 (21)), with subsequent amendment Resolution 11-09-2023 affecting contractor-license definitions and fees (Article II). This is the county's own current, in-force code compilation (58-page consolidated document), independently downloaded and read in full 2026-07-06. Source: Teller County Building Code (PDF), https://www.tellercounty.gov/DocumentCenter/View/242/Teller-County-Building-Code-PDF; Article III - 2021 International Residential Code (IRC), including Appendix Chapters AA, AB, AC, AG, AH, AJ, and AN, with numerous county-specific amendments (see localAmendments). Source: Teller County Building Code (PDF), Article III; Article IV - 2021 International Building Code (IBC), including Appendix Chapters G, H, and I, and the 'Building Safety Journal.' Source: Teller County Building Code (PDF), Article IV; Article V - 2021 International Plumbing Code (IPC) as amended by the State of Colorado, including Appendices B, E, and G. Colorado uses the International Plumbing Code (not the Uniform Plumbing Code) for this jurisdiction. Where Article V conflicts with Article III (IRC) or Article IV (IBC), Article V (the Plumbing Code) governs. Source: Teller County Building Code (PDF), Article V, Section 102.1; Article VI - 2021 International Mechanical Code (IMC), including Appendix Chapter A. Source: Teller County Building Code (PDF), Article VI; Article VII - 2021 International Fuel Gas Code (IFGC), including Appendix Chapter A. Source: Teller County Building Code (PDF), Article VII; Article VIII - Mobile/Factory Built/Manufactured Housing Code, with county-specific definitions of Manufactured Home, Factory Built Home (Modular/IRC Code Compliant Unit, per 8 CCR 1302-3), and Mobile Home; a building permit is required for the permanent foundation and all utility connections. Source: Teller County Building Code (PDF), Article VIII; Article IX - 2023 National Electrical Code (NEC/NFPA 70), adopted directly by Teller County (not merely deferred to a state board), governing all electrical alterations, repairs, replacements, equipment, appliances, fixtures, fittings, and appurtenances; where the 2021 IRC/IBC conflict with the NEC, the NEC (Article IX) prevails as the more restrictive code. Source: Teller County Building Code (PDF), Article IX; Article X - 2003 International Fire Code, adopted as the Teller County Fire Code for the unincorporated area by Teller County Ordinance #16. Source: Teller County Building Code (PDF), Article X; Article XII - 2018 International Energy Conservation Code (IECC), including the IECC Appendix for reference only. This is the county's own current adopted edition as of this review (2026-07-06) -- it is the 2018 edition, not the 2021 or 2024 edition. Colorado's HB22-1362 (statewide 'model' energy code adoption requirements for larger/home-rule jurisdictions with updates on a rolling schedule) was checked for applicability: Teller County's own code text does not reference HB22-1362 or a more recent IECC edition anywhere in the 58-page Building Code document, and no separate county page or resolution updating the energy code to a post-2018 edition was found. This is reported honestly as the genuinely current adopted edition rather than assumed to have been superseded. Source: Teller County Building Code (PDF), Article XII; Article XIII - Safety Code for Elevators and Escalators (ASME A17.1-2019, A17.3-2011, A18.1-2011, ASME QEI-2013, ANSI/ASSE A10.4-2007); all inspections performed by a State of Colorado-designated ANSI Certified Inspector with results submitted to the Building Department. Source: Teller County Building Code (PDF), Article XIII; Article XIV - 2021 International Existing Building Code (IEBC). Source: Teller County Building Code (PDF), Article XIV; Article XV - Uniform Code for the Abatement of Dangerous Buildings, 1997 edition. Source: Teller County Building Code (PDF), Article XV; Article XVII - Penalties: violations of the Teller County Building Code are unlawful and punishable per C.R.S. 30-28-209 and 30-28-210. Source: Teller County Building Code (PDF), Article XVII. Local amendments apply — see the Unincorporated Teller County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teller County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.