Keenesburg building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Keenesburg, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
91 W. Broadway Avenue, Keenesburg, CO 80643
Phone
303-732-4281 ext. 2
Office hours
As of 6/11/2026, permits are processed and issued on Wednesday and Friday only. Building Official Steve Jones is a contract official with Charles Abbott Associates (CAA), a third-party municipal building-department staffing firm; direct line 720-810-5751. Inspections are usually performed the next business day if the inspection request is submitted by 3:00 p.m., via the Town's online Google Forms-based 'Request an Inspection' portal.

Published scheduling rules

  • The Town does not publish a numeric plan-review turnaround (days or weeks) for ANY plan-review-required permit category anywhere on its site — not on the Building Department page, individual permit sub-pages, plan-review checklists, building guides, or the Building Permit Fee Schedule/Impact Fee Schedule PDFs. The only timing commitments are operational: One-Stop Permits 'usually' issue the same day, inspections 'usually' happen the next business day if requested by 3:00 p.m., and permits are only processed/issued Wednesdays and Fridays as of 6/11/2026. Colorado is home-rule with no statewide review-time clock; every plan-review permitType in this file is honestly null/unverified with a documented chase trail rather than an invented figure. (General)

Inspection sequence

Applies to: New Commercial Building Permit

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; Fire District sign-off as applicable

Applies to: New Residential Home Building Permit

  1. 1

    Foundation

    Before concrete pour, per 30-inch minimum frost line depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Residential Addition / Basement Finish Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour, per 30-inch minimum frost line depth

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Deck / Patio Cover / Pole Barn Permit

  1. 1

    Post/Footing Inspection

    Pier depth below 30-inch frost line verified before concrete pour

  2. 2

    Framing Inspection

    Ledger attachment, joist/beam sizing, guardrail framing verified

  3. 3

    Final Inspection

    Guardrails, stair dimensions, decking attachment, and electrical outlet (if applicable) verified

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough Electrical

    Circuit, conduit, and disconnect placement before concealment, if applicable

  2. 2

    Final Inspection

    Charger mounted, circuit labeled, and installation verified per the adopted 2023 NEC

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Framing Inspection

    Required when structural enhancements are needed for panel mounting, both residential and commercial

  2. 2

    Final Electrical Inspection

    Rapid shutdown system tested with inspector present; qualified person per the system's amperage/structure type must attend

Re-inspection fees

Electrical PermitRe-inspection Fee · Applies if work is not ready for inspection or corrections were not made
$80.00
Plumbing Permit (Sewer Repair / Gas Line Pressure Check)Re-inspection Fee
$80.00
Mechanical / HVAC Permit (Furnace, Boiler, Air Conditioner)Re-inspection Fee
$80.00
Roof Replacement PermitRe-inspection Fee
$80.00
Water Heater Replacement PermitRe-inspection Fee
$80.00

Keenesburg building permits

Get alerts for Keenesburg

We'll email you when Keenesburg's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.