Kuna building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Kuna, Idaho.

Verified 2026-06-29 · Source

How to schedule

Inspections are requested through the building department below.

Address
751 W. 4th Street, P.O. Box 13, Kuna, ID 83634
Phone
(208) 922-5546
Office hours
Mon–Fri 8:00 AM – 5:00 PM; inspection requests must be submitted prior to 4:00 PM for next business day

Published scheduling rules

  • Inspection requests must be submitted prior to 4:00 PM to receive them the next business day; requests after 4 PM will not be scheduled for the following work day (Residential Building Permit)
  • Schedule inspections online at portal.iworq.net/KUNA/permits/600 (Residential Building Permit)
  • Inspection requests must be submitted prior to 4:00 PM for next business day scheduling — requests received after 4 PM will not be scheduled for the following work day (General)
  • Inspections are scheduled online at portal.iworq.net/KUNA/permits/600 (General)
  • 2026-07-16 rotation audit: all 6 permitTypes' fees, the statewide codesAdopted list, and department contact info re-verified live and updated where needed (see per-permitType notes); Municode city code and the iWorQ inspection portal were NOT independently re-fetched this session, so file-level lastVerified below is intentionally left unchanged pending that check (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation/Slab

    Inspection of foundation prior to concrete pour

  2. 2

    Framing/Rough-In

    Structural framing, rough-in mechanical, electrical, and plumbing

  3. 3

    Fire/Life Safety

    Kuna Fire review for life safety compliance (separate from Building Department inspections)

  4. 4

    Final

    Final inspection of completed project for Certificate of Occupancy

Applies to: Residential Building Permit

  1. 1

    Footing/Foundation

    Inspection of footing and foundation prior to concrete pour

  2. 2

    Framing

    Inspection of framing, sheathing, and rough-in systems before insulation or drywall

  3. 3

    Insulation

    Inspection of insulation installation for energy compliance

  4. 4

    Final

    Final inspection of completed structure for Certificate of Occupancy

Applies to: Electrical Permit

  1. 1

    Rough-In Electrical

    Inspection of rough-in wiring before walls are closed

  2. 2

    Final Electrical

    Final inspection of all electrical installations

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In Electrical

    Inspection of rough-in wiring/circuit before walls are closed, where applicable

  2. 2

    Final Electrical

    Final inspection of the completed EVSE circuit and breaker/disconnect per NEC Article 625

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In Mechanical

    Inspection of mechanical rough-in prior to covering

  2. 2

    Final Mechanical

    Final inspection of mechanical installation

Applies to: Plumbing Permit

  1. 1

    Rough-In Plumbing

    Inspection of rough-in plumbing before walls are closed

  2. 2

    Final Plumbing

    Final inspection of all plumbing installations

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical / Racking

    Racking attachment and rough electrical wiring inspected before panels are energized

  2. 2

    Final Electrical

    Final inspection of the completed electrical interconnection

Final inspection only: Demolition Permit

Re-inspection fees

Residential Building PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
Commercial Building PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
Mechanical / HVAC PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
Electrical PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
Solar Photovoltaic (PV) PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
EV Charger / EVSE PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)
Plumbing PermitRe-inspection Fee · Resolution R57-2021
$65 each (after each failed attempt)

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kuna building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Kuna building permits