Inspection sequence, scheduling, and re-inspection fees for building permits in Star, Idaho.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
10769 W. State St., P.O. Box 130, Star, ID 83669
Phone
208-286-7247
Office hours
Inspections scheduled online by 4:00 PM prior business day; next-day inspections only (no weekend inspections)

Published scheduling rules

  • All inspection requests must be submitted online through the IWORQ Portal by 4:00 PM the business day before the inspection is needed — no phone or email inspection requests accepted. (Residential Building Permit (New Construction))
  • All inspection requests must be submitted online through the IWORQ Portal by 4:00 PM the business day before the inspection. (Commercial Building Permit (New Construction & TI))
  • All inspection requests must be submitted online by 4:00 PM the prior business day; no phone or email inspection requests accepted. (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction & TI)

  1. 1

    Footing / Foundation

    Schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Framing / Rough-In

    After framing and rough-in trades complete, before insulation or wall cover.

  3. 3

    Final / Certificate of Occupancy

    All work complete per approved plans and fire authority approval; Certificate of Occupancy issued after passing final inspection.

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing / Foundation

    Schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection. No phone or email inspection requests accepted.

  2. 2

    Framing / Rough-In

    After framing and rough-in trades complete, before insulation or wall cover. Rough and final inspections cannot be scheduled for the same day.

  3. 3

    Final

    All work complete per approved plans; Certificate of Occupancy issued after passing final inspection. Rough and final inspections cannot be scheduled same day.

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final Electrical

    All electrical work complete; scheduled separately from rough inspection.

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection

  2. 2

    Final Electrical

    Charging equipment installed and circuit verified

Applies to: Manufactured / Mobile Home Setup Permit

  1. 1

    Setup / Foundation

    Inspect foundation, tie-downs, and placement; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final

    All work complete including MEP connections; Certificate of Occupancy issued after passing final inspection.

Applies to: Mechanical Permit

  1. 1

    Rough Mechanical

    Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final Mechanical

    All mechanical work complete; scheduled separately from rough inspection (rough and final cannot be same day).

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final Plumbing

    All plumbing work complete; scheduled separately from rough inspection.

Applies to: Residential Swimming Pool Permit

  1. 1

    Bonding / Rough Electrical

    Pool bonding and rough electrical inspection before backfill; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final

    Pool installation complete; all safety barriers in place.

Applies to: Residential/Commercial Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Interconnection wiring, disconnect placement, and conduit before energizing; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final Electrical / Interconnection

    Panel/array wiring complete, disconnect labeled, system ready for utility interconnection.

Final inspection only: Demolition Permit

Re-inspection fees

Residential Building Permit (New Construction)Re-inspection Fee · City of Star Fee Information page (staridaho.org/1249/Fee-Information)
$65.00
Commercial Building Permit (New Construction & TI)Re-inspection Fee · City of Star Fee Information page (staridaho.org/1249/Fee-Information)
$65.00
Mechanical PermitRe-inspection Fee · City of Star MEP Fee Schedule, Resolution 2025-03
$65.00
Electrical PermitRe-inspection Fee · City of Star MEP Fee Schedule, Resolution 2025-03
$65.00
Plumbing PermitRe-inspection Fee · City of Star MEP Fee Schedule, Resolution 2025-03
$65.00
Residential/Commercial Solar Photovoltaic (PV) PermitRe-inspection Fee · City of Star Fee Information page (staridaho.org/1249/Fee-Information).
$65.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Star building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Star building permits

Get alerts for Star

We'll email you when Star's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.