EV Charger / EVSE Permit — Star, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Star, Idaho
The City of Star has no dedicated electric-vehicle-charging-station permit or fee line. An EV charger circuit added to an existing home is electrical work covered by the general Electrical Permit process (Resolution 2025-03 MEP Fee Schedule): the 'Existing Residential Electrical' flat fee applies to the permit itself, with the 'Additional Branch Circuits' per-circuit fee layered on if more than one circuit is added. A charger installed as part of new residential construction would instead be folded into the applicable 'New Residential Electrical' square-footage tier. No EV/EVSE-specific dollar figure was found on the published fee schedule.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required, purchased separately from any building permit, per the same process documented in this file's Electrical Permit entry
- Apply via the IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Homeowners may perform their own electrical work on their primary/secondary residence; commercial work requires an Idaho state-licensed electrical contractor Owner-builderContractor
- No dedicated EV/EVSE line-item, application, or checklist was found on the City's MEP Fee Schedule (Resolution 2025-03) or Building Department pages
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection
- 2
Final Electrical
Charging equipment installed and circuit verified
See the full Star inspection guide — scheduling & re-inspection fees →
Tips
- Star has no dedicated EV charger permit or fee — apply through the standard Electrical Permit process, and budget for the 'Existing Residential Electrical' flat fee ($65) plus the per-circuit fee ($10) if applicable, unless the charger is part of new construction, in which case it's folded into the square-footage-based New Residential Electrical tier.
- Homeowners can pull their own electrical permit and do their own EV charger wiring on a primary/secondary residence — a licensed contractor is only required for commercial installs. Owner-builderContractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Star building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Star
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Idaho →
Look up this fee in a different city →