Electrical Permit in Star, Idaho

Required for all electrical work on residential and commercial properties in Star. Purchased separately from the building permit. Approved and issued same day if associated building permit is already approved. Fee schedule based on Resolution 2025-03 (approved 6/17/2025).

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
New Residential Electrical — Single Family under 1,500 sq. ft.$130.00City of Star MEP Fee Schedule, Resolution 2025-03 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule)
New Residential Electrical — Single Family 1,501–2,500 sq. ft.$195.00City of Star MEP Fee Schedule, Resolution 2025-03
New Residential Electrical — Single Family 2,501–3,500 sq. ft.$260.00City of Star MEP Fee Schedule, Resolution 2025-03
New Residential Electrical — Single Family 3,501–4,500 sq. ft.$325.00City of Star MEP Fee Schedule, Resolution 2025-03
New Residential Electrical — Modular/Manufactured/Mobile Home$65.00City of Star MEP Fee Schedule, Resolution 2025-03
Existing Residential Electrical$65.00City of Star MEP Fee Schedule, Resolution 2025-03
Additional Branch Circuits (existing residential)$10.00 per circuitCity of Star MEP Fee Schedule, Resolution 2025-03
Swimming Pool (residential)$195.00City of Star MEP Fee Schedule, Resolution 2025-03
Spas, Hot Tubs, and Hydro Massage Tubs$65.00City of Star MEP Fee Schedule, Resolution 2025-03
Temporary Construction Services$65.00City of Star MEP Fee Schedule, Resolution 2025-03. Full credit/refund for temp pole permit if no inspection performed.
Commercial/Other — valuation-basedUp to $10,000: multiply by 2% add $60; $10,001–$100,000: subtract $10,000, multiply by 1%, add $260; over $100,001: subtract $100,001, multiply by 0.5%, add $1,160City of Star MEP Fee Schedule, Resolution 2025-03. Applies to commercial, industrial, solar, fire alarm, new SF residential over 4,500 sq. ft., multi-family.
Re-inspection Fee$65.00City of Star MEP Fee Schedule, Resolution 2025-03

Review timeline

11 business days

Star’s published plan-review target

Inspection process

  1. 1

    Rough Electrical

    Before walls are closed; schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection.

  2. 2

    Final Electrical

    All electrical work complete; scheduled separately from rough inspection.

Tips

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Star building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Star

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.