Residential Building Permit (New Construction) in Star, Idaho
Required for all new single-family residential construction in Star. Applications submitted and payments made online through the IWORQ Permit Portal. Plans must be 24" × 36", submitted in landscape orientation as PDF. Contractors must register before accessing the portal. Typical review: small residential projects 2–4 weeks; larger residential projects approximately 4–6 weeks. Revisions add 3–4 weeks per cycle.
Verified 2026-06-29 · Source
When you need this permit
- All new construction requires a building permit
- Contractors must complete the Contractor Registration Form before accessing the permit portal
- All plans submitted online via IWORQ Portal (staridpermit.portal.iworq.net); no in-person paper submissions
- Plan size must be 24" × 36" in landscape orientation with space reserved for City approval stamps
- Sewer certificate required from Star Sewer & Water District for all new homes with sewer service
- If structure is in flood plain, contact the City Zoning Administrator before submitting
- Structures 4,000 sq. ft. or more require Fire review for hydrant flow adequacy
- Soils/geotechnical report required if project includes a basement; must be stamped by Idaho licensed engineer
- Structural drawings and calculations must be stamped, signed, and dated by Idaho licensed design professional if applicable
- Fire sprinkler/alarm plans (3 sets, under separate cover) if required — may be deferred
- Energy compliance required: Alternate Energy Path (signed, all pages) or Prescriptive Method
- Plans must include a plan check report as the first pages of the submittal
Required documents
- Req
Residential Submittal Checklist & Standards (Form #312, Rev 02-2026)
City of Star's required residential submittal checklist including site plan, foundation plan, floor plan, roof/floor framing, elevations, wall bracing, wall sections/details, connection details, energy compliance, structural drawings, and MEP floor plan requirements
- Req
Site Plan
Must show location of new structure on site, all existing structures, dimensional setbacks from rear and side yards and from back of sidewalk, driveway width, proposed or existing fences, all property lines and easements, and a short narrative of scope of work with square footage
- Req
Foundation Plan
Must include foundation system type, compliant crawlspace venting, anchor bolt locations, and footing detail. Basements require soils/geotechnical report stamped by Idaho licensed engineer.
- Req
Construction Drawings (Floor Plan, Framing, Elevations, Wall Bracing, Sections and Details)
Complete plan set showing code compliance per 2018 IRC; all rooms labeled with clear dimensions; all sides of structure shown in elevations
- Req
Energy Compliance Documentation
Alternate Energy Path (signed, all pages) or Prescriptive Method demonstrating 2018 IECC compliance
- Req
Contractor Registration Form
Required for all contractors before accessing the permit portal; available on the City of Star Building Department website
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Application Submittal Fee (non-refundable) | $100.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). Applied toward total building permit cost. Not refundable or transferable. |
| Building Permit Fee — Valuation $1 to $500 | $23.50 | Table 1-A, City of Star Building Permit Fees (staridaho.org/ImageRepository/Document?documentId=1637) |
| Building Permit Fee — Valuation $501 to $2,000 | $23.50 for first $500 plus $3.05 per each additional $100 or fraction thereof to $2,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $2,001 to $25,000 | $69.25 for first $2,000 plus $14 per each additional $1,000 or fraction thereof to $25,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $25,001 to $50,000 | $391.75 for first $25,000 plus $10.10 per each additional $1,000 or fraction thereof to $50,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $50,001 to $100,000 | $643.75 for first $50,000 plus $7 per each additional $1,000 or fraction thereof to $100,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $100,001 to $500,000 | $993.75 for first $100,000 plus $5.60 per each additional $1,000 or fraction thereof to $500,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $500,001 to $1,000,000 | $3,233.75 for first $500,000 plus $4.75 per each additional $1,000 or fraction thereof to $1,000,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $1,000,001 to $5,000,000 | $5,608.75 for first $1,000,000 plus $3.65 per each additional $1,000 or fraction thereof to $5,000,000 | Table 1-A, City of Star Building Permit Fees |
| Residential Mechanical Review Fee | $35.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Re-inspection Fee | $65.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Re-review Plans | $50.00 | Must submit original AND updated plans. City of Star Fee Information page. |
| Ada County Highway District — Single Family Detached Impact Fee | $5,803 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). Impact fee paid to ACHD, not City of Star. |
| Star Fire Impact Fee | $2,152 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Star Parks Impact Fee | $4,695.76 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Star Police Impact Fee | $680.88 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Public Safety Mitigation Fee — Police | $3,360 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Public Safety Mitigation Fee — Fire | $3,600 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Ada County Single Family Residential Impact Fees (Jail, EMS, Coroner) | $750 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
Review timeline
14–42 business days
Star’s published plan-review target
Inspection process
- 1
Footing / Foundation
Schedule online via IWORQ Portal before 4:00 PM for next-business-day inspection. No phone or email inspection requests accepted.
- 2
Framing / Rough-In
After framing and rough-in trades complete, before insulation or wall cover. Rough and final inspections cannot be scheduled for the same day.
- 3
Final
All work complete per approved plans; Certificate of Occupancy issued after passing final inspection. Rough and final inspections cannot be scheduled same day.
Tips
- Small residential projects review in 2–4 weeks; larger residential projects approximately 4–6 weeks. Each revision or correction cycle adds 3–4 weeks.
- All inspection requests must be submitted online through the IWORQ Portal by 4:00 PM the business day before the inspection is needed — no phone or email inspection requests accepted.
- Rough and final inspections cannot be scheduled on the same day.
- Contractors must register with the City before accessing the permit portal; use the Contractor Registration Form on the building department website.
- Contact your HOA before contacting the building department — HOA restrictions may be stricter than city code, and the building department has no authority over HOAs.
- A sewer certificate from Star Sewer & Water District (208-286-7388) is required for all new homes on public sewer before obtaining a building permit.
- Plan reviews become null and void if no progress or payment within 180 days of the last plan review completion; expired plan reviews are not eligible for extension or refund.
- Working without a permit may result in double fees, civil penalties, or both.
- Up to 80% refund of permit fee on written request, depending on number of inspections performed; 20% retained as processing cost.
Frequently asked questions
- How long does permit review take in Star?
- Per the Star Building Department FAQ: Mechanical, Electrical, Plumbing permits are same-day if the associated building permit is already approved. Demolition, re-roofing, and siding are same-day. Small residential projects: 2–4 weeks. Larger residential projects: approximately 4–6 weeks. Commercial projects: 4–6 weeks. Each revision or correction cycle adds 3–4 weeks. Star does not offer expedited plan review for a fee.
- How do I schedule an inspection in Star?
- All inspections are scheduled online through the IWORQ Permit Portal (staridpermit.portal.iworq.net) before 4:00 PM the business day before the inspection is needed. Star does not accept inspection requests by phone or email. No weekend inspections are available.
- Can a homeowner pull their own permit in Star?
- Yes. Homeowners can pull permits on their primary or secondary residence without registering as a contractor, but must perform all work themselves and plan to live in the residence within 12 months of completion. If the homeowner will not be doing the work, a licensed contractor must pull the permit.
- When is a building permit required in Star?
- Permits are required for: all new construction; structural additions/remodels; sheds or outbuildings 200 sq. ft. or larger; patio covers/pergolas/awnings (detached over 200 sq. ft. or any attached size); re-roofing projects; fences over 6 ft. tall; retaining walls over 4 ft. (bottom of footing to top); setting manufactured homes; replacing siding over 100 sq. ft. on an existing house; replacing windows or doors where openings are enlarged or reduced; decks 30 or more inches above grade; demolition. No permit is required for concrete slabs or IBC-defined agricultural buildings.
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
- City of Star Building Department — official building department
- Building Department | City of Star (main page, contact, inspection rules)
- Fee Information | City of Star (application fees, permit fees Table 1-A, impact fees)
- Residential Submittal Checklist & Standards — Form #312 Rev 02-2026 (PDF)
- Frequently Asked Questions | City of Star Building Department (review timelines, permit triggers, inspections)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Star building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Star
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.