City of St. Maries building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in City of St. Maries, Idaho.
Verified 2026-07-19 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 602 College Avenue, St. Maries, ID 83861
- Phone
- (208) 245-2577
- Office hours
- Monday-Thursday 8:00 AM to 5:00 PM; Friday 8:00 AM to 3:00 PM, per City of St. Maries Building Department and Forms pages.
- Website
- Official site
Inspection sequence
Applies to: Building Permit
- 1
Designated Points of Construction
St. Maries City Code 9-2-6 requires the Building Inspector to inspect the structure at 'designated points of construction as set forth in the building code adopted by the city,' and prohibits construction from proceeding beyond each designated inspection point until the inspection is completed and signified on the building permit. The city code does not separately enumerate a discrete checklist (e.g., footing/framing/final) beyond this general requirement as of 2026-07-19; the adopted 2018 IBC/IRC govern the specific inspection points.
- 2
Final / Certificate of Compliance
A Certificate of Compliance (a copy of the signed and dated inspection record) is issued once the Building Inspector is satisfied all codes and requirements are met, and must be issued prior to use and/or occupancy — St. Maries City Code 9-2-8.
Applies to: Electric Vehicle (EV) Charging Station Permit
- 1
Electrical Rough-In / Final
Charger circuit, disconnect, and any panel work inspected per the 2017 NEC as locally adopted; no EV-specific inspection checklist is separately published by the City, so this follows the general Building Permit inspection framework at St. Maries City Code 9-2-6.
- 2
Final / Certificate of Compliance
Certificate of Compliance issued once the Building Inspector is satisfied all codes and requirements are met, per St. Maries City Code 9-2-8 — applied to EV charger installations the same as any other building permit.
Applies to: Residential/Commercial Solar Photovoltaic (PV) Permit
- 1
Electrical Rough-In / Interconnection
Panel, disconnect, and interconnection wiring inspected per the 2017 NEC as locally adopted; no solar-specific inspection checklist is separately published by the City, so this follows the general Building Permit inspection framework at St. Maries City Code 9-2-6.
- 2
Final / Certificate of Compliance
Certificate of Compliance issued once the Building Inspector is satisfied all codes and requirements are met, per St. Maries City Code 9-2-8 — applied to solar PV the same as any other building permit.
Final inspection only: Demolition Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of St. Maries building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
City of St. Maries building permits
Get alerts for City of St. Maries
We'll email you when City of St. Maries's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.