Residential/Commercial Solar Photovoltaic (PV) Permit — City of St. Maries, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://cityofstmaries.org/building-department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential/Commercial Solar Photovoltaic (PV) Permit in City of St. Maries, Idaho
Required for installation of a rooftop or ground-mounted solar photovoltaic system within St. Maries city limits. The City has no standalone solar-specific application, checklist, or fee line published on its website (cityofstmaries.org) or in its Fee Schedule (Resolution No. 2026-362, updated 06.22.2026) as of 2026-07-20 — a solar PV system is processed and billed as a standard Building Permit under St. Maries City Code 9-2-1, using the same valuation-based Table 3-A fee table and the Building Permit Application's 'Other' Scope of Work checkbox.
Verified 2026-07-20 · Source
When you need this permit
- Unlawful to construct, install, or alter any structure or electrical system requiring a building permit within St. Maries city limits without first procuring the permit — St. Maries City Code 9-2-1(A), applied to solar PV mounting/racking and interconnection the same as any other structural/electrical work
- Governed by the 2018 IBC/IRC (structural mounting) and the 2017 National Electrical Code (electrical interconnection) as adopted by the Town — St. Maries City Code 9-1-1(A)
- Idaho has no statewide HOA-restriction-on-solar statute of the kind some states carry, and no independent statewide solar-permit-fee cap statute was located as of this review — confirm any HOA-level restriction directly with the property's own covenants rather than assuming a state override applies
- A survey/site plan requirement (per the general Building Permit Application) applies unless the specific exception at St. Maries City Code 9-2-1(A)(1)-(2) is met (demolition-only, fully within existing building envelope, or a valid prior survey exists) — a rooftop-only PV retrofit with no new footprint would typically qualify for this exception
- Plan Review Fee (40% of the Building Permit fee) and the separate Planner review fee (Table 2) both apply to solar PV the same as any other Building Permit, per the City's Fee Schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Rough-In / Interconnection
Panel, disconnect, and interconnection wiring inspected per the 2017 NEC as locally adopted; no solar-specific inspection checklist is separately published by the City, so this follows the general Building Permit inspection framework at St. Maries City Code 9-2-6.
- 2
Final / Certificate of Compliance
Certificate of Compliance issued once the Building Inspector is satisfied all codes and requirements are met, per St. Maries City Code 9-2-8 — applied to solar PV the same as any other building permit.
See the full City of St. Maries inspection guide — scheduling & re-inspection fees →
Tips
- St. Maries has no dedicated solar PV permit application, checklist, or fee line published anywhere on its official website as of 2026-07-20 — a PV system is processed as a standard Building Permit under the general valuation-based Table 3-A fee schedule.
- A rooftop-only PV retrofit that does not expand the building's footprint may qualify for the field-survey exception at City Code 9-2-1(A)(1)-(2), avoiding the need for a new licensed-surveyor field survey.
- No Idaho statewide statute was located capping local solar permit fees (unlike Colorado's C.R.S. § 24-48.5-113) — confirm the exact fee the City will assess directly with the Building Department, (208) 245-2577, before budgeting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of St. Maries building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of St. Maries
Residential/Commercial Solar Photovoltaic (PV) Permit in other cities
Compare residential/commercial solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →
Now live
Build your City of St. Maries project checklist
Describe your project once and get every permit, document, and fee it triggers in City of St. Maries — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →