Electric Vehicle (EV) Charging Station Permit — City of St. Maries, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://cityofstmaries.org/building-department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station Permit in City of St. Maries, Idaho
Installing an EV charging station (EVSE) within St. Maries city limits has no standalone application, checklist, or fee line published on the City's website (cityofstmaries.org) or in its Fee Schedule (Resolution No. 2026-362, updated 06.22.2026) as of 2026-07-20 — the same gap already documented for solar PV in this jurisdiction (see solar-pv-permit). An EV charger is electrical work covered by St. Maries City Code 9-2-1(A)'s general permit requirement and is processed and billed as a standard Building Permit ('Building Permit - Other Work,' Table 3) under the City's valuation-based Table 3-A fee table, using the Building Permit Application's 'Other' Scope of Work checkbox. Re-fetched the current Fee Schedule PDF directly for this review and confirmed Table 3-A's exact tiers.
Verified 2026-07-20 · Source
When you need this permit
- Unlawful to install or alter any electrical system requiring a building permit within St. Maries city limits without first procuring the permit — St. Maries City Code 9-2-1(A), applied to EV charger circuits and panel work the same as any other electrical installation
- Governed by the 2017 National Electrical Code (with Idaho amendments) as adopted by the City — St. Maries City Code 9-1-1(A)(8)
- The Building Permit Application's 'Important Notice' states separate electrical, plumbing, and mechanical permits are required, but the City's own Fee Schedule does not list distinct city-issued electrical permit fee lines — consistent with electrical trade permitting being folded into the general valuation-based Building Permit fee (Table 3-A) rather than billed as a separate city permit type
- Plan Review Fee (40% of the Building Permit fee) and the separate Planner review fee (Table 2) both apply the same as any other Building Permit, per the City's Fee Schedule
- A field survey is not typically required if the installation does not expand the building footprint, per the exception at St. Maries City Code 9-2-1(A)(1)-(2)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Rough-In / Final
Charger circuit, disconnect, and any panel work inspected per the 2017 NEC as locally adopted; no EV-specific inspection checklist is separately published by the City, so this follows the general Building Permit inspection framework at St. Maries City Code 9-2-6.
- 2
Final / Certificate of Compliance
Certificate of Compliance issued once the Building Inspector is satisfied all codes and requirements are met, per St. Maries City Code 9-2-8 — applied to EV charger installations the same as any other building permit.
See the full City of St. Maries inspection guide — scheduling & re-inspection fees →
Tips
- St. Maries has no dedicated EV-charger permit application, checklist, or fee line published anywhere on its official website as of 2026-07-20 — an EV charger installation is processed as a standard Building Permit ('Other Work') under the general valuation-based Table 3-A fee schedule ($24 for a job valued at $500 or less, $24 + $3/additional $100 up to $2,000, then $69 + $11/additional $1,000 up to $40,000), the same gap already documented for solar PV in this jurisdiction.
- Confirm the exact assessed fee with the Building Department, (208) 245-2577, before budgeting, since the valuation-based table depends on the contractor's total cost estimate for the installation, and add the 40% Plan Review fee plus the $60 Planner review fee for residential projects.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of St. Maries building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of St. Maries
Electric Vehicle (EV) Charging Station Permit in other cities
Compare electric vehicle (ev) charging station permit fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your City of St. Maries project checklist
Describe your project once and get every permit, document, and fee it triggers in City of St. Maries — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →